Command and control system for controlling operational sequencing of multiple turbogenerators using a selected control mode
Assignee: Capstone Green Energy Corp
•
Filing: 2000-10-12
•
Granted: 2003-12-16
•
Expires: 2020-10-12
Abstract
Abstract A command and control system and method for multiple turbogenerators in a grid parallel system includes a master controller to start, sequence, coordinate power commands, and provide fault handling to each of the individual turbogenerators and the specific control modes. A bidirectional power meter, that measures the load consumption (or production when a turbogenerator system is installed) in a building or application, may also be utilized. This power meter can provide a reference or setpoint to the master controller for controlling the individual turbogenerators.
Inventors
- 👤 Edward C. Edelman
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-06 11:35
CPC Classifications
H; H02; H02J; H02J3/00; H02J3/38; H02J3/46; H02J3/466; H02J3/40
Claims Analysis
Total Claims: 30
Claim 1
Independent Claim
162 words
A command and control system for a plurality of turbogenerators, comprising: a plurality of individual turbogenerators, each of said plurality of individual turbogenerators having a controller; a command and control system bus, each of said plurality of individual turbogenerator controllers operably connected to said command and control system bus; a plurality of disconnect switches, a disconnect switch provided in each operable connection of an individual turbogenerator controller to said command and control bus; a bidirectional power meter; a master controller operably associated with each of the turbogenerator controllers and with said bi-directional power meter to control operational sequencing of the individual turbogenerators in a selected control mode; and a junction box operably connecting an electric utility, said power meter, the output of the plurality of individual turbogenerators, and a load, wherein said operational sequencing includes the starting stopping and loading of each of said plurality of individual turbogenerators, and wherein a turbogenerator is automatically restarted in the event of a fault shutdown.
Claim 2
Dependent Claim
162 words
A command and control system for a plurality of turbogenerators, comprising: a plurality of individual turbogenerators, each of said plurality of individual turbogenerators having a controller; a command and control system bus, each of said plurality of individual turbogenerator controllers operably connected to said command and control system bus; a plurality of disconnect switches, a disconnect switch provided in each operable connection of an individual turbogenerator controller to said command and control bus; a bidirectional power meter; a master controller operably associated with each of the turbogenerator controllers and with said bi-directional power meter to control operational sequencing of the individual turbogenerators in a selected control mode; and a junction box operably connecting an electric utility, said power meter, the output of the plurality of individual turbogenerators, and a load, wherein said operational sequencing includes the starting stopping and loading of each of said plurality of individual turbogenerators, and wherein a turbogenerator is automatically restarted in the event of a fault shutdown.
Claim 3
Dependent Claim
43 words
The command and control system of claim 1 , and in addition: a timed relay operably associated with said command and control system bus, said bi-directional power meter, and said junction box to prevent the feedback of electrical power to the electric Utility.
Claim 4
Dependent Claim
50 words
The command and control system of claim 1 , wherein said selected control mode is a utility load following mode in which utility power consumption and turbogenerator power generation are compared to produce an error signal which is integrated over a defined specified time to produce a power demand signal.
Claim 5
Dependent Claim
52 words
The command and control system of claim 1 wherein said selected control mode is a utility base load mode in which a defined utility power signal and the power meter signal are compared to produce an error signal which is integrated over a defined specified time to produce a power demand signal.
Claim 6
Dependent Claim
51 words
The command and control system of claim 1 wherein said selected control mode is a base load mode in which the power meter signal and a base load demand signal are compared to produce an error signal which is integrated over a defined specified time to produce a power demand signal.
Claim 7
Dependent Claim
19 words
The command and control system of claim 1 wherein said master controller includes a sequencing and control logic system.
Claim 8
Dependent Claim
23 words
The command and control system of claim 6 wherein said sequencing and control logic system includes a proportional-plus-integrated control to regulate power demand.
Claim 9
Dependent Claim
26 words
The command and control system of claim 1 wherein the operational sequencing is based on the use time of each of said plurality of individual turbogenerators.
Claim 10
Dependent Claim
19 words
The command and control system of claim 8 wherein the turbogenerator with the least use time is stared first.
Claim 11
Dependent Claim
20 words
The command and control system of claim 8 wherein the turbogenerator with the most use time is shut down first.
Claim 12
Dependent Claim
27 words
The command and control system of claim 1 wherein the starting of each of the plurality of turbogenerators is selected to minimize the total power draw requirements.
Claim 13
Dependent Claim
26 words
The command and control system of claim 1 wherein an inactive turbogenerator is automatically restarted in the event of a fault shutdown of an active turbogenerator.
Claim 14
Dependent Claim
25 words
The command and control system of claim 1 wherein said selected control mode includes power hysterisis bands, rate limits and set points integrated over time.
Claim 15
Dependent Claim
142 words
A control system for a plurality of turbogenerators, comprising: a plurality of turbogenerators, each of said plurality of individual turbogenerators having a controller; a control system bus, each of said plurality of turbogenerator controllers operably connected to said control system bus; a switch provided in each operable connection of an individual turbogenerator controller to said control bus; a power meter; a master controller operably associated with each of the turbogenerator controllers and with the power meter to control the operational sequences for the individual turbogenerators in a selected control mode; and a junction box operably connecting an electric utility, said power meter, the output of the plurality of individual turbogenerators, and a load, wherein the operational sequences include a start sequence, a stop sequence and a load sequence, and wherein a turbogenerator is automatically restarted in the event of a fault shutdown.
Claim 16
Dependent Claim
142 words
A control system for a plurality of turbogenerators, comprising: a plurality of turbogenerators, each of said plurality of individual turbogenerators having a controller; a control system bus, each of said plurality of turbogenerator controllers operably connected to said control system bus; a switch provided in each operable connection of an individual turbogenerator controller to said control bus; a power meter; a master controller operably associated with each of the turbogenerator controllers and with the power meter to control the operational sequences for the individual turbogenerators in a selected control mode; and a junction box operably connecting an electric utility, said power meter, the output of the plurality of individual turbogenerators, and a load, wherein the operational sequences include a start sequence, a stop sequence and a load sequence, and wherein a turbogenerator is automatically restarted in the event of a fault shutdown.
Claim 17
Dependent Claim
37 words
The control system of claim 14 , further comprising: a timed relay operably associated with said control system bus, said power meter, and said junction box to prevent the feedback of electrical power to the electric utility.
Claim 18
Dependent Claim
48 words
The control system of claim 14 , wherein said selected control mode is a utility load following mode in which utility power consumption and turbogenerator power generation are compared to produce an error signal which is integrated over a defined specified time to produce a power demand signal.
Claim 19
Dependent Claim
50 words
The control system of claim 14 wherein said selected control mode is a utility base load mode in which a defined utility power signal and the power meter signal are compared to produce an error signal which is integrated over a defined specified time to produce a power demand signal.
Claim 20
Dependent Claim
49 words
The control system of claim 14 wherein said selected control mode is a base load mode in which the power meter signal and a base load demand signal are compared to produce an error signal which is integrated over a defined specified time to produce a power demand signal.
Claim 21
Dependent Claim
17 words
The control system of claim 14 wherein said master controller includes a sequencing and control logic system.
Claim 22
Dependent Claim
21 words
The control system of claim 19 wherein said sequencing and control logic system includes a proportional-plus-integrated control to regulate power demand.
Claim 23
Dependent Claim
24 words
The control system of claim 14 wherein the start sequence is based on the use time of each of said plurality of individual turbogenerators.
Claim 24
Dependent Claim
17 words
The control system of claim 21 wherein the turbogenerator with the least use time is started first.
Claim 25
Dependent Claim
18 words
The control system of claim 21 wherein the turbogenerator with the most use time is shut down first.
Claim 26
Dependent Claim
26 words
The control system of claim 14 wherein the start sequence of each of the plurality of turbogenerators is selected to minimize the total power draw requirements.
Claim 27
Dependent Claim
24 words
The control system of claim 14 wherein an inactive turbogenerator is automatically restarted in the event of a fault shutdown of an active turbogenerator.
Claim 28
Dependent Claim
23 words
The control system of claim 14 wherein said selected control mode includes power hysteresis bands, rate limits and set points integrated over time.
Claim 29
Dependent Claim
13 words
The control system of claim 14 wherein the switch is a disconnect switch.
Claim 30
Dependent Claim
15 words
The control system of claim 14 wherein the power meter is a bi-directional power meter.
References Cited (Backward Citations)
US2163140A
Cited
US2920211A
Cited
US2917635A
Cited
US3041833A
Cited
US3221172A
Cited
US3151250A
Cited
US3591844A
Cited
US3678284A
Cited
US3651331A
Cited
US3611717A
Cited
US3806785A
Cited
US3663948A
Cited
US3805517A
Cited
US3621365A
Cited
US3718837A
Cited
US3675037A
Cited
US3775649A
Cited
US3703663A
Cited
US3830055A
Cited
US3867846A
Cited
US4019315A
Cited
US3846693A
Cited
US3986038A
Cited
US4195231A
Cited
US3908130A
Cited
US4017790A
Cited
US4087711A
Cited
US3930367A
Cited
US4021704A
Cited
US4114048A
Cited
US4069424A
Cited
US4062186A
Cited
US4062185A
Cited
US4033115A
Cited
US4349744A
Cited
US4071897A
Cited
US4118926A
Cited
US4144482A
Cited
US4245163A
Cited
US4149233A
Cited
US4305129A
Cited
GB2007926B
Cited
US4164661A
Cited
EP0012219A1
Cited
USRE30589E
Cited
US4262209A
Cited
US4508487A
Cited
US4270165A
Cited
US4276590A
Cited
US4340820A
Cited
US4447787A
Cited
US4346304A
Cited
US4414804A
Cited
US4361791A
Cited
US4425613A
Cited
US4413676A
Cited
US4469954A
Cited
US4467216A
Cited
US4450363A
Cited
US4532761A
Cited
US4788873A
Cited
US4631954A
Cited
US4590416A
Cited
US4460834A
Cited
US4597037A
Cited
US4597259A
Cited
US4626761A
Cited
US4633157A
Cited
US4647834A
Cited
US4680691A
Cited
US4763058A
Cited
US4733341A
Cited
US4698577A
Cited
US4684875A
Cited
US4764712A
Cited
US4845418A
Cited
US4731547A
Cited
US4885519A
Cited
US4926105A
Cited
US4897994A
Cited
US5084825A
Cited
US4827152A
Cited
US5390068A
Cited
US5168208A
Cited
US4994981A
Cited
US4924170A
Cited
US5204595A
Cited
US5053635A
Cited
US5099408A
Cited
US5302906A
Cited
US5166595A
Cited
US5191519A
Cited
US5194801A
Cited
US5257180A
Cited
US5166597A
Cited
US5327718A
Cited
US5206802A
Cited
US5177676A
Cited
EP0535382B1
Cited
US5572097A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 2006-12-15 | 2007-06-16 | 2007-12-16 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 2010-12-15 | 2011-06-16 | 2011-12-16 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 2014-12-15 | 2015-06-16 | 2015-12-16 | $7700.00 | Window Closed / Lapsed |