US4467216A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Multiple fixed hydraulic geometry turbine control system
Assignee: J-UB ENGINEERS Inc A CORP OF IDAHO
•
Filing: 1982-04-06
•
Granted: 1984-08-21
•
Expires: 2002-04-06
Abstract
Abstract A plurality of selected fixed hydraulic geometry turbine generators are programmed for operation at rated efficiencies by interrupting flow to the turbines under control of a programmable power controller receiving water level, flow and power monitoring inputs. The turbines selected are of discreet sizes simultaneously operative only under maximum flow conditions of the hydropower source, and otherwise operated in accordance with an optimum duty schedule to match varying flow conditions.
Inventors
- 👤 Robert E. Murphy
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-05 01:19
CPC Classifications
H; H02; H02J; H02J3/00; H02J3/38; F; F03; F03B; F03B15/00; F03B15/02; F03B15/04; F03B15/06; F03B15/08; H02J3/46; H02J3/466; Y; Y02; Y02E; Y02E10/00; Y02E10/20
Claims Analysis
Total Claims: 13
Claim 1
Independent Claim
114 words
A method of generating energy from a variable flow hydropower source by operating in parallel a plurality of fixed hydraulic geometry turbines respectively driving electric generators connected to a common output bus, including the steps of: monitoring flow from the hydropower source to detect substantial deviation from a maximum available flow adapted to drive all of the turbines at substantially the respective rated efficiencies thereof; selecting the turbines through which flow from the hydropower source is interrupted when said deviation occurs to substantially match the monitored flow with uninterrupted flow through the remaining turbines operating with acceptable deviation from the respective rated efficiencies thereof; and enabling only the generators driven by the operating turbines.
Claim 2
Independent Claim
114 words
A method of generating energy from a variable flow hydropower source by operating in parallel a plurality of fixed hydraulic geometry turbines respectively driving electric generators connected to a common output bus, including the steps of: monitoring flow from the hydropower source to detect substantial deviation from a maximum available flow adapted to drive all of the turbines at substantially the respective rated efficiencies thereof; selecting the turbines through which flow from the hydropower source is interrupted when said deviation occurs to substantially match the monitored flow with uninterrupted flow through the remaining turbines operating with acceptable deviation from the respective rated efficiencies thereof; and enabling only the generators driven by the operating turbines.
Claim 3
Dependent Claim
38 words
The method of claim 1 including the step of: monitoring operating conditions of the turbines and the generators to modify said selection of the turbines for protection thereof against overload and loss of power in the output bus.
Claim 4
Dependent Claim
34 words
The method of claim 2 wherein the flow through the turbines operating substantially at the rated efficiencies is interrupted and restored in accordance with a programmed duty schedule to substantially match the monitored flow.
Claim 5
Dependent Claim
34 words
The method of claim 1 wherein the flow through the turbines operating substantially at the rated efficiencies is interrupted and restored in accordance with a programmed duty schedule to substantially match the monitored flow.
Claim 6
Dependent Claim
137 words
In a system of generating energy from a variable flow hydropower source by flow in parallel through a plurality of fixed geometry turbines respectively driving electric generators connected to a common output bus, flow control means for interrupting flow from the hydropower source through the respective turbines, sensing means connected to each of the generators for detecting operation of the respective turbines substantially below rated efficiencies thereof in response to decreases in flow therethrough, power control logic means operatively connecting said sensing means to the flow control means for effecting said interruption in flow through the turbines operating below the rated efficiencies to substantially match variable flow conditions of the hydropower source with total optimum flow through the turbines remaining in operation, and means for disabling the generators driven by the turbines through which flow is interrupted.
Claim 7
Dependent Claim
137 words
In a system of generating energy from a variable flow hydropower source by flow in parallel through a plurality of fixed geometry turbines respectively driving electric generators connected to a common output bus, flow control means for interrupting flow from the hydropower source through the respective turbines, sensing means connected to each of the generators for detecting operation of the respective turbines substantially below rated efficiencies thereof in response to decreases in flow therethrough, power control logic means operatively connecting said sensing means to the flow control means for effecting said interruption in flow through the turbines operating below the rated efficiencies to substantially match variable flow conditions of the hydropower source with total optimum flow through the turbines remaining in operation, and means for disabling the generators driven by the turbines through which flow is interrupted.
Claim 8
Dependent Claim
59 words
The combination of claim 5 including means operatively connected to the common output bus and the generators for monitoring operating conditions thereof, and means interfacing the monitoring means with the power controlling logic means for modifying selection of the turbines through which flow is interrupted to protect the generators against overload and loss of power in the output bus.
Claim 9
Dependent Claim
30 words
The combination of claim 6 said power controlling logic means includes a data processing unit through which the turbines are disabled and enabled in accordance with a programmed duty schedule.
Claim 10
Dependent Claim
31 words
The combination of claim 5 wherein said power controlling logic means includes a data processing unit through which the turbines are disabled and enabled in accordance with a programmed duty schedule.
Claim 11
Dependent Claim
21 words
The combination of claim 5 wherein said turbines are of different sizes operating at the rated efficiencies under optimum flow rates.
Claim 12
Independent Claim
85 words
A method of generating energy from a variable flow hydropower source operating fixed hydraulic geometry turbines in parallel, including the steps of: selecting a plurality of said turbines of different discreet sizes for simultaneous operation at rated efficiencies under maximum flow conditions of the hydropower source; disabling each of the turbines when operation substantially deviates from the rated efficiency thereof; and scheduling operation of the turbines at substantially rated efficiencies in accordance with a program to substantially match varying flow conditions of the hydropower source.
Claim 13
Independent Claim
85 words
A method of generating energy from a variable flow hydropower source operating fixed hydraulic geometry turbines in parallel, including the steps of: selecting a plurality of said turbines of different discreet sizes for simultaneous operation at rated efficiencies under maximum flow conditions of the hydropower source; disabling each of the turbines when operation substantially deviates from the rated efficiency thereof; and scheduling operation of the turbines at substantially rated efficiencies in accordance with a program to substantially match varying flow conditions of the hydropower source.
References Cited (Backward Citations)
US2861195A
Cited
US3300647A
Cited
US3556668A
Cited
US3651331A
Cited
US3703663A
Cited
US3842249A
Cited
US3848171A
Cited
US3935488A
Cited
US3939356A
Cited
US4195231A
Cited
US4201923A
Cited
US4201924A
Cited
US4245163A
Cited
US4164661A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1987-08-21 | 1988-02-20 | 1988-08-21 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1991-08-21 | 1992-02-20 | 1992-08-21 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1995-08-21 | 1996-02-20 | 1996-08-21 | $7700.00 | Window Closed / Lapsed |