Claims Analysis
Total Claims: 35
Claim 1
Independent Claim
157 words
A method of operating a manufacturing control system for computer control of work flow in an automatic manufacturing production line with a plurality of work stations at which the progress of work is monitored, by the steps comprising, assigning priority ratings (PR) to each lot of WIP materials with said priority ratings (PR) ranging from a low priority rating to a high priority rating, making fuzzy logic tests of parameters of lots of WIP materials and making adjustments based upon said tests as follows: a) measuring the velocity of work flow parameter and adjusting PR rating as a function of said velocity, b) testing whether a lot exceeds a maximum time and increasing the PR rating if the lot exceeds said maximum time, c) batching when higher priority lots are absent, then upgrading the priority rating (PR) of said lot, and d) testing whether a Kanban is below target and if so, then upgrading the PR rating.
Claim 2
Independent Claim
157 words
A method of operating a manufacturing control system for computer control of work flow in an automatic manufacturing production line with a plurality of work stations at which the progress of work is monitored, by the steps comprising, assigning priority ratings (PR) to each lot of WIP materials with said priority ratings (PR) ranging from a low priority rating to a high priority rating, making fuzzy logic tests of parameters of lots of WIP materials and making adjustments based upon said tests as follows: a) measuring the velocity of work flow parameter and adjusting PR rating as a function of said velocity, b) testing whether a lot exceeds a maximum time and increasing the PR rating if the lot exceeds said maximum time, c) batching when higher priority lots are absent, then upgrading the priority rating (PR) of said lot, and d) testing whether a Kanban is below target and if so, then upgrading the PR rating.
Claim 3
Dependent Claim
80 words
A method in accordance with claim 1 comprising: clocking passage of WIP materials to measure depletion and accumulation of material at a work station with increases in priority rating as a function of the difference of target velocity minus actual velocity of work with an increase of 1 priority rating (PR) level as the cumulative value of said difference exceeds a predetermined percentage, whereby automation of production control of a manufacturing process is provided by improved automation of work scheduling.
Claim 4
Dependent Claim
53 words
A method in accordance with claim 1 comprising: testing to determine whether highest priority lots are present in the WIP materials to determine whether to batch or stop batching mixed lots of WIP materials, and stopping batching when highest priority lots are present, or batching lots when no highest priority lots are present.
Claim 5
Dependent Claim
71 words
A method in accordance with claim 1 comprising: testing to determine whether highest priority lots are present in the WIP materials to determine whether a current lot is behind by more than a maximum time, upgrading priority rating by one level when said current lot is behind by more than said maximum time, or continuing with current priority rating when said current lot is behind by less than said maximum time.
Claim 6
Dependent Claim
76 words
A method in accordance with claim 1 for batching of PR=2 to PR=5 lots when higher priority lots are absent, comprising the steps as follows: testing to determine whether highest priority lots are present in the WIP materials to determine whether priority PR=1 lots appear in the current lot queue, If YES, then generating a signal to stop batching of PR=2 to PR=5, or If NO then generating a signal for batching PR2 to PR5 lots.
Claim 7
Dependent Claim
71 words
A method in accordance with claim 1 comprising the steps as follows: test to determine whether the queue time for lot is more than T 1 hours, If YES, then upgrade the priority rating, PR=X level by one level by sending a signal to the production line, If NO, proceed to the wait, then retest function, and after the upgraded lot has been run, reset to the default priority rating PR=5.
Claim 8
Dependent Claim
52 words
A method in accordance with claim 6 comprising the steps as follows: testing to determine the queue time for a lot, the DELTA between the Expected Date Out (EDO) and the Original Commitment Date (OCD), and providing an upgrade of the priority rating PR=X if WIP is less than the set limit.
Claim 9
Dependent Claim
41 words
A method in accordance with claim 7 comprising the steps as follows: providing one promotion for each N 1 days the EDO falls behind the OCD, and after the upgraded lot has been run, resetting to the default priority rating PR=5.
Claim 10
Dependent Claim
29 words
A method in accordance with claim 8 comprising the step as follows: wherein said test is made to determine whether the value of N 1 equals 3 days behind.
Claim 11
Dependent Claim
55 words
A method in accordance with claim 1 comprising the steps as follows: test to determine whether the cumulative moves in a Kanban are X% below target, If YES, then upgrade the priority rating, PR=X by one level, and If NO then continue to test whether the cumulative moves in a Kanban are X% below target.
Claim 12
Dependent Claim
30 words
A method in accordance with claim 10 comprising the step as follows: wherein said test is made to determine whether the cumulative moves in a Kanban are 5% below target.
Claim 13
Dependent Claim
61 words
A method in accordance with claim 1 comprising: providing an increase in the priority rating of a lot as a function of increasing queue time, providing an increase in the priority rating of a lot as a function of the difference comprising the expected date out minus commitment date, and resetting to a default priority rating, after the lot is run.
Claim 14
Dependent Claim
79 words
A method in accordance with claim 12 comprising: clocking passage of WIP materials to measure depletion and accumulation of material at a work station with increases in priority rating as a function of the difference of target velocity minus actual velocity of work with an increase of 1 priority rating level as the cumulative value of said difference exceeds a predetermined percentage, whereby automation of production control of a manufacturing process is provided by improved automation of work scheduling.
Claim 15
Dependent Claim
52 words
A method in accordance with claim 12 comprising: testing to determine whether highest priority lots are present in the WIP materials to determine whether to batch or stop batching mixed lots of WIP materials, stopping batching when highest priority lots are present, or batching lots when no highest priority lots are present.
Claim 16
Dependent Claim
71 words
A method in accordance with claim 12 comprising: testing to determine whether highest priority lots are present in the WIP materials to determine whether the current lot is behind by more than a maximum time, upgrading priority rating by one level when said current lot is behind by more than said maximum time, or continuing with current priority rating when said current lot is behind by less than said maximum time.
Claim 17
Dependent Claim
77 words
A method in accordance with claim 12 for batching of PR=2 to PR=5 lots when higher priority lots are absent, comprising the steps as follows: test to determine whether highest priority lots are present in the WIP materials to determine whether priority PR=1 lots appear in the current lot queue, and If YES, then generate a signal to stop batching of PR=2 to PR=5, or If NO then generate a signal for batching PR2 to PR5 lots.
Claim 18
Dependent Claim
72 words
A method in accordance with claim 12 comprising the steps as follows: test to determine whether the queue time for lot is more than T 1 hours, and If YES, then upgrade the priority rating, PR=X level by one level by sending a signal to the production line, If NO, proceed to the wait, then retest function, and after the upgraded lot has been run, reset to the default priority rating PR=5.
Claim 19
Dependent Claim
30 words
A method in accordance with claim 17 comprising the steps as follows: wherein said test is made to determine whether the cumulative moves in a Kanban are 5% below target.
Claim 20
Dependent Claim
116 words
A method in accordance with claim 12 for batching of PR=2 to PR=5 lots when higher priority lots are absent, comprising the steps as follows: test to determine whether highest priority lots are present in the WIP materials to determine whether priority PR=1 lots appear in the current lot queue, If YES, then generate a signal to stop batching of PR=2 to PR=5, or If NO then generate a signal for batching PR2 to PR5 lots, test to determine the queue time for a lot, the DELTA between the Expected Date Out (EDO) and the Original Commitment Date (OCD) and providing an upgrade of the priority rating PR=X if WIP is less than the set limit.
Claim 21
Dependent Claim
100 words
A method in accordance with claim 12 comprising the steps as follows: test to determine whether the queue time for lot is more than T 1 hours, If YES, then upgrade the priority rating, PR=X level by one level by sending a signal to the production line, If NO, proceed to the wait, then retest function and after the upgraded lot has been run, reset to the default priority rating PR=5, providing one promotion for each N 1 days the EDO falls behind the OCD, and after the upgraded lot has been run, reset to the default priority rating PR=5.
Claim 22
Dependent Claim
55 words
A method in accordance with claim 12 comprising the steps as follows: test to determine whether the cumulative moves in a Kanban are X% below target, If YES, then upgrade the priority rating, PR=X by one level, and If NO then continue to test whether the cumulative moves in a Kanban are X% below target.
Claim 23
Dependent Claim
116 words
A method in accordance with claim 12 comprising the steps as follows: test to determine whether the queue time for lot is more than T 1 hours, If YES, then upgrade the priority rating, PR=X level by one level by sending a signal to the production line, If NO, proceed to the wait, then retest function and after the upgraded lot has been run, reset to the default priority rating PR=5, providing one promotion for each N 1 days the EDO falls behind the OCD, after the upgraded lot has been run, reset to the default priority rating PR=5, and said test is made to determine whether the value of N 1 equals 3 days behind.
Claim 24
Dependent Claim
117 words
A manufacturing control system providing computer control of work flow in an automatic manufacturing production line with a plurality of work stations at which the progress of work is monitored, by the means comprising: means for assigning priority ratings to each lot of WIP materials with said priority ratings ranging from a low priority rating to a high priority rating, means for providing an increase in the priority rating of a lot as a function of increasing queue time, means for providing an increase in the priority rating of a lot as a function of the difference expected date out minus commitment date, and means for resetting to a default priority rating, after the lot is run.
Claim 25
Dependent Claim
117 words
A manufacturing control system providing computer control of work flow in an automatic manufacturing production line with a plurality of work stations at which the progress of work is monitored, by the means comprising: means for assigning priority ratings to each lot of WIP materials with said priority ratings ranging from a low priority rating to a high priority rating, means for providing an increase in the priority rating of a lot as a function of increasing queue time, means for providing an increase in the priority rating of a lot as a function of the difference expected date out minus commitment date, and means for resetting to a default priority rating, after the lot is run.
Claim 26
Dependent Claim
81 words
A system in accordance with claim 23 comprising: means for clocking passage of WIP materials to measure depletion and accumulation of material at a work station with increases in priority rating as a function of the difference of target velocity minus actual velocity of work with an increase of 1 priority rating level as the cumulative value of said difference exceeds a predetermined percentage, whereby automation of production control of a manufacturing process is provided by improved automation of work scheduling.
Claim 27
Dependent Claim
56 words
A system in accordance with claim 23 comprising: means for testing to determine whether highest priority lots are present in the WIP materials to determine whether to batch or stop batching mixed lots of WIP materials, means for stopping batching when highest priority lots are present, or batching lots when no highest priority lots are present.
Claim 28
Dependent Claim
72 words
A system in accordance with claim 23 comprising: means for testing to determine whether highest priority lots are present in the WIP materials to determine whether current lot is behind by more than a maximum time, upgrading priority rating by one level when said current lot is behind by more than said maximum time, or continuing with current priority rating when said current lot is behind by less than said maximum time.
Claim 29
Dependent Claim
81 words
A system in accordance with claim 23 for batching of PR=2 to PR=5 lots when higher priority lots are absent, comprising means for performing the functions as follows: means for testing to determine whether highest priority lots are present in the WIP materials to determine whether priority PR=1 lots appear in the current lot queue, If YES, then generate a signal to stop batching of PR=2 to PR=5, or If NO, then generate a signal for batching PR2 to PR5 lots.
Claim 30
Dependent Claim
57 words
A system in accordance with claim 27 comprising means for performing the functions as follows: means for testing to determine the queue time for a lot, the DELTA between the Expected Date Out (EDO) and the Original Commitment Date (OCD) and providing an upgrade of the priority rating PR=X if WIP is less than the set limit.
Claim 31
Dependent Claim
44 words
A system in accordance with claim 27 comprising means for performing the functions as follows: providing one promotion for each three days that the EDO falls behind the OCD, and after the upgraded lot has been run, reset to the default priority rating PR=5.
Claim 32
Dependent Claim
32 words
A system in accordance with claim 29 comprising means for performing the function as follows: wherein said test is made to determine whether the value of N 1 equals 3 days behind.
Claim 33
Dependent Claim
77 words
A system in accordance with claim 23 comprising means for performing the functions as follows: means for testing to determine whether the queue time for a lot is more than T 1 hours, If YES, then upgrade the priority rating, PR=X level by one level by sending a signal to the production line, If NO, proceed to the wait, then retest function, and after the upgraded lot has been run, reset to the default priority rating PR=5.
Claim 34
Dependent Claim
61 words
A system in accordance with claim 23 comprising means for performing the functions as follows: means for testing to determine whether the cumulative moves in a Kanban are X% be low target, If YES, then upgrade the priority rating, PR=X by one level, or If NO, then continue to test whether the cumulative moves in a Kanban are X% below target.
Claim 35
Dependent Claim
33 words
A system in accordance with claim 32 comprising means for performing the functions as follows: wherein said test is made to determine whether the cumulative moves in a Kanban are 5% below target.