Claims Analysis
Total Claims: 9
Claim 1
Independent Claim
260 words
A factory for processing jobs-in-progress, and producing completed work, said factory comprising: a plurality of machines for receiving and processing ones of said jobs-in-progress and at least a portion of said plurality of machines having waiting queues, said machines providing status information relating to respective ones of said waiting queues; a source of orders; a source of user-selected job release criteria, said criteria including at least one of a respective utilization factor and a respective job on-time factor assigned to respective ones of said machines; storing means, responsive to said source of orders, for storing pending orders, and for releasing a selected order for inclusion in said jobs-in-progress in response to selection information; and means, responsive to information from said storing means, to said source of job release criteria and to said machine status information, for producing and revising said selection information so as to establish a Factory Profile curve of an optimum release strategy for said factory, determining a corresponding curve of predicted actual processing for each of said jobs from a trial start date through the expected completion of said job in said factory, comparing said actual job curve for each of said jobs with said Factory Profile optimum curve, and accepting said job for processing by said factory on said trial start date if said actual job curve closely follows said Factory Profile curve, within predefined bounds, throughout the processing time for said job, and otherwise determining a new curve of predicted actual processing for said job from a new trial start date and repeating said comparison.
Claim 2
Dependent Claim
260 words
A factory for processing jobs-in-progress, and producing completed work, said factory comprising: a plurality of machines for receiving and processing ones of said jobs-in-progress and at least a portion of said plurality of machines having waiting queues, said machines providing status information relating to respective ones of said waiting queues; a source of orders; a source of user-selected job release criteria, said criteria including at least one of a respective utilization factor and a respective job on-time factor assigned to respective ones of said machines; storing means, responsive to said source of orders, for storing pending orders, and for releasing a selected order for inclusion in said jobs-in-progress in response to selection information; and means, responsive to information from said storing means, to said source of job release criteria and to said machine status information, for producing and revising said selection information so as to establish a Factory Profile curve of an optimum release strategy for said factory, determining a corresponding curve of predicted actual processing for each of said jobs from a trial start date through the expected completion of said job in said factory, comparing said actual job curve for each of said jobs with said Factory Profile optimum curve, and accepting said job for processing by said factory on said trial start date if said actual job curve closely follows said Factory Profile curve, within predefined bounds, throughout the processing time for said job, and otherwise determining a new curve of predicted actual processing for said job from a new trial start date and repeating said comparison.
Claim 3
Dependent Claim
45 words
The factory of claim 1, wherein said selection information producing means further includes a means for determining a range enclosing said Factory Profile curve and wherein said acceptance criteria is satisfied if said actual job curve falls within said range enclosing said Factory Profile curve.
Claim 4
Dependent Claim
37 words
The factory of claim 2, wherein said selection information producing means further includes a means for adjusting said range about said Factory Profile curve to provide a wider range for jobs having a higher than normal priority.
Claim 5
Dependent Claim
424 words
The factory of claim 2, wherein said selection information producing means further includes a computational means for computing said start date for acceptance using a BestStartDate algorithm: ______________________________________
Let Ethmax be maximum Threshold Error
Let Ethmin (E = Error) be minimum Threshold Error
Emin <- Eth
Emax <- 0 is the max error without going over the
threshold value
Sd <- Desired.sub.-- Sd (desired start date), SDc <- Sd, i.e.
current Sd is originally set to the Desired.sub.-- Sd
Nr, N1 no of right shifts and left shifts allowed
Nr is a function of order priority, i.e. as order priority
increases then Nr becomes smaller; N1 is a management-
determined finished good inventory function, stating how
early, in the worst case, completion of the order will be
acceptable. Note that these two parameters decide on the
boundaries of the search space. They can be either
predefined or can be decided at the time of order entry.
n is shift counter; +ve for right shifts & -ve for left
shifts; n <- 0
Wc is the current window.sub.-- no
w <- Wc
Allocate: Set t <- end.sub.-- of(w) /* t the max time unit in w,
e.g.,
last day of week w */
Allocate until t OR all steps done otherwise EXIT
Evaluate e(t), where t is the end of current window
If e(t) > Ethmin THEN
BEGIN
if e(t) < Emin THEN BestSD <- SDc,
Emin <- e(t);
/*else the previous SD was better*/
find.sub.-- a.sub.-- better.sub.-- sd;
auto allocate i
END-begin
ELSE /* error term is still smaller than
threshold */
BEGIN
w <- w+1
Emax <- e(t)
GOTO allocate
END-begin;
If e(t) > Ethmax
THEN warning: Promised due date is too
good for this priority class;
print(BestSD, Emin, Emax);
END BestStartDate.
PROCEDURE find.sub.-- a.sub.-- better.sub.-- sd:
If n=<0 & n>N1
THEN shiftleftORright(-)
/* note that N1 is a -ve number */
Else IF n<Nr THEN shiftleftORright(+);
ELSE /* UNSUCCESSFUL release */
DO ONE OF THE FOLLOWING
Increase job's priority; not recommended if done too often;
Decrease job's priority, i.e., increasing Nr the search
space this is relaxing constraints;
Decrease(make more negative) N1, this is also relaxing WIP
constraint;
Suspend release until a later time;
Other alternatives are changing Eth and CI* etc but these
are not recommended since they would have a global effect.
END-else;
END.sub.-- find.sub.-- a better.sub.-- sd.
PROCEDURE shiftleftORright (.sup.˜): /* .sup.˜ is - if
shiftleft and + if
shiftright */
n <- n.sup.˜ 1
w <- w.sup.˜ 1
Wc <- w
SDc <- max(starttime(w), Today)
END shiftleftORright.
______________________________________
Claim 6
Dependent Claim
14 words
The factory of claim 2, wherein said selection information producing means comprises a computer.
Claim 7
Dependent Claim
18 words
The factory of claim 2, wherein said order storing means comprises a data base stored on a computer.
Claim 8
Dependent Claim
22 words
The factory of claim 2, wherein said selection information producing means and said order storing means are comprised on the same computer.
Claim 9
Dependent Claim
26 words
The factory of claim 2, wherein said machines are controlled by a computer system directly connected to said information producing means and order storing means computer.