Automated production release system

Assignee: International Business Machines Corp
•
Filing: 1987-12-01
•
Granted: 1989-12-12
•
Expires: 2007-12-01
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A conceptual decision analysis tool for production release planning displays management parameters and objectives and prompts the user to define priorities. This encourages the user to plan based on management criteria. The user keys in the priorities and the system automatically analyzes the impact of planned release on the manufacturing process using a simulation process and re-evaluates the order release priorities and sequence. This capability is used before any order is actually released to manufacturing. The system also provides the capability of analyzing the impact of the orders even after the user pre-sets priorities to release certain orders. The system calculates the revised sequence and produces impact statements on such management criteria as manufacturing throughput, work-in-process inventory and cycle time.

Inventors

  • 👤 Bharath Natarajan

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-25 08:11
CPC Classifications
G; G06; G06Q; G06Q10/00; G06Q10/06; G06Q10/08; G06Q10/087; G06Q10/0872; G06Q10/0877; G05; G05B; G05B2219/00; G05B2219/30; G05B2219/32; G05B2219/32301; Y; Y02; Y02P; Y02P90/00; Y02P90/02; Y10; Y10S; Y10S706/00; Y10S706/902; Y10S706/903; Y10S706/904

Claims Analysis

Total Claims: 10
Claim 1
Independent Claim 112 words
An automated production release system for implementation on a computer, said system providing for the production release planning information for a manufacturing environment to aid a user to make decisions that will improve the production release process, comprising the steps of: prompting the user to define management priorities between maximizing throughput, minimizing work-in-process inventory and minimizing manufacturing cycle time; simulating the manufacturing environment using a predefined set of order release and dispatching rules to test for varying alternatives in the production release process; selecting the result of the various alternatives which optimize the management priorities input by the user; and generating a revised sequence of production release orders for the manufacturing environment.
Claim 2
Dependent Claim 112 words
An automated production release system for implementation on a computer, said system providing for the production release planning information for a manufacturing environment to aid a user to make decisions that will improve the production release process, comprising the steps of: prompting the user to define management priorities between maximizing throughput, minimizing work-in-process inventory and minimizing manufacturing cycle time; simulating the manufacturing environment using a predefined set of order release and dispatching rules to test for varying alternatives in the production release process; selecting the result of the various alternatives which optimize the management priorities input by the user; and generating a revised sequence of production release orders for the manufacturing environment.
Claim 3
Dependent Claim 71 words
The automated production release system as recited in claim 1 wherein said computer includes a database and a query system and further comprising the steps of: capturing in the database decision variables generated in said step of simulating; responding to a user input via the query system to access the decision variables captured in the database; and displaying an analysis of tested combinations of the tested alternatives in the production release.
Claim 4
Dependent Claim 46 words
The automated production release system as recited in claim 2 further comprising the step of responding to a user input via the query system to select a decision rule and evaluate the tested alternatives based on the management criteria of throughput, work-in-process inventory and cycle time.
Claim 5
Dependent Claim 46 words
The automated production release system as recited in claim 1 further comprising the step of displaying in a split screen format a list of orders for processing in the manufacturing environment and said revised sequence of production release orders with an assigned priority for each order.
Claim 6
Dependent Claim 30 words
The automated production release system as recited in claim 4 further comprising the step of displaying management priorities defined by the user correlated with said revised sequence of production orders.
Claim 7
Dependent Claim 59 words
The automated production release system as recited in claim 1 further comprising the steps of: providing an option to the user of changing said predefined set of order release and dispatching rules to make a new set of order release and dispatching rules; and performing said simulating step according to said new set of order release and dispatching rules.
Claim 8
Dependent Claim 71 words
The automated production release system as recited in claim 6 wherein said computer includes a database and a query system and further comprising the steps of: capturing in the database decision variables generated in said step of simulating; responding to a user input via the query system to access the decision variables captured in the database; and displaying an analysis of tested combinations of the tested alternatives in the production release.
Claim 9
Dependent Claim 46 words
The automated production release system as recited in claim 7 further comprising the step of displaying in a split screen format a list of orders for processing in the manufacturing environment and said revised sequence of production release orders with an assigned priority for each order.
Claim 10
Dependent Claim 30 words
The automated production release system as recited in claim 8 further comprising the step of displaying management priorities defined by the user correlated with said revised sequence of production orders.

References Cited (Backward Citations)

US3946212A Cited
US4408291A Cited
US4459663A Cited
US4644480A Cited
US4591983A Cited
US4719587A Cited
US4796194A Cited
US4807108A Cited
US4807108B1 Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1992-12-11 1993-06-12 1993-12-12 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1996-12-11 1997-06-12 1997-12-12 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2000-12-11 2001-06-12 2001-12-12 $7700.00 Window Closed / Lapsed