Claims Analysis
Total Claims: 8
Claim 1
Independent Claim
92 words
An automated production dispatch system for implementation on a computer, said system providing for the dispatch information for a manufacturing environment to aid a user to make decisions that will improve the dispatch process, comprising the steps of: monitoring production release and dispatch orders generated by a production planning process; simulating the manufacturing environment subject to a production disruption based on defined management dispatch criteria to generate an estimate of order tardiness, work-in-process inventory and cycle time; and testing the estimate to determine if the estimate is acceptable according to predefined criteria.
Claim 2
Dependent Claim
92 words
An automated production dispatch system for implementation on a computer, said system providing for the dispatch information for a manufacturing environment to aid a user to make decisions that will improve the dispatch process, comprising the steps of: monitoring production release and dispatch orders generated by a production planning process; simulating the manufacturing environment subject to a production disruption based on defined management dispatch criteria to generate an estimate of order tardiness, work-in-process inventory and cycle time; and testing the estimate to determine if the estimate is acceptable according to predefined criteria.
Claim 3
Dependent Claim
52 words
The automated production dispatch system as recited in claim 1 wherein if the estimate is not acceptable, performing the steps of: prompting the user to define dispatch priorities between minimizing order tardiness, minimizing work-in-process inventory and minimizing manufacturing cycle time; and generating revised dispatch sequence of dispatch orders for the manufacturing environment.
Claim 4
Dependent Claim
71 words
The automated production dispatch system as recited in claim 2 wherein said computer includes a database and a query system and further comprising the steps of: capturing in said database decision variables generated in said step of simulating; responding to a user input via the query system to access the decision variables captured in the database; and displaying an analysis of tested combinations of the tested alternatives in the production release.
Claim 5
Dependent Claim
46 words
The automated production dispatch system as recited in claim 3 further comprising the step of responding to a user input via the query system to select a decision rule and evaluate the tested alternatives on the management criteria of order tardiness, work-in-process inventory and cycle time.
Claim 6
Dependent Claim
30 words
The automated production dispatch system as recited in claim 4 further comprising the step of displaying management criteria defined by the user correlated with said revised sequence of dispatch orders.
Claim 7
Dependent Claim
48 words
The automated production dispatch system as recited in claim 2 further comprising the steps of: providing an option to the user of changing said management dispatch criteria to make a new set of dispatch rules; and performing said simulating step according to said new set of dispatch rules.
Claim 8
Dependent Claim
72 words
The automated production dispatch system as recited in claim 6 wherein said computer includes a database and a query system and further comprising the steps of: capturing in said database decision variables generated in said step of simulating; responding to a user input via the query system to access the decision variables captured in the database; and displaying an analysis of tested combinations of the tested alternatives in the production dispatch system.