← Back to Patent Explorer
US5058087A Expired / Lapsed US ⏱️ 0.0 years remaining

Process for determining the electrical duration of signal paths

Assignee: Siemens AG
•
Filing: 1987-05-05
•
Granted: 1991-10-15
•
Expires: 2007-05-05
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract In particular in automatic testing equipment for integrated circuits, all signal sections at the test piece joint should ideally be of the same electrical length. The signal sections used in the test consist, in the case of reception, of cable, comparator, error logic, etc. If the signal sections are of different electrical durations, then in the case of reception, the transmitted signal must be connected. In a process for determining the electrical duration of signal sections, each of which has a transmitter and a receiver and at the end connecting points for example for an integrated circuit, the connecting points (AS) of all signal sections (SS) are short-circuited, all receivers up to the receiver of the signal section to be measured are then switched off, all transmitters up to the transmitter of the signal section to be measured are switched on and simultaneously emit a pulse which is transmitted to the connecting point. At the short-circuited connecting points (AS) of the signal sections (SS), a central pulse (21) is then produced which is transmitted over the signal section to be measured to its receiver (E). The time at which the pulse produced by the central pulse enters the receiver (E) is recorded and entered in a table. The above-mentioned process is carried out for all signal sections. The measurements so obtained give the relative durations of the various signal sections. The process for determining the duration of signal sections requires only that the connecting points of the signal sections be connected with one another through a short-circuit bridge (KB).

Inventors

  • 👤 Klaus Welzhofer
  • 👤 Antun Vuksic

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-30 17:58
CPC Classifications
G; G01; G01R; G01R31/00; G01R31/28; G01R31/317; G01R31/3181; G01R31/319; G01R31/31903; G01R31/31908; G01R31/3191; G01R27/00; G01R27/28; G01R31/31917; G01R31/31924; G01S; G01S7/00; G01S7/02; G01S7/28; G01S7/285; G01S7/295; G01S7/298

Claims Analysis

Total Claims: 21
Claim 1
Independent Claim 183 words
A method for determining the electric transit time of signal runs which are in each instance connected at one end to a connecting point and which have at the other end a transmitter and a receiver comprising the steps of: a) short circuiting the connecting points (AS) of all signal runs (SS), b) turning off all receivers (E) except the receiver of the signal run to be measured, c) turning on all transmitters (S) except the transmitter of the signal run to be measured and simultaneously delivering a transmission pulse which is transmitted to the associated connecting point, d) superposing the transmission pulses at the shortcircuited connecting points (AS) to form a central pulse (ZI), and transmitting said central pulse over the signal run to be measured to the associated receiver, e) establishing the time of occurrence of a pulse triggered by the central pulse at the output of the receiver of the signal run to be measured and entering that time in a table as a measured value characterizing the transit time, f) repeating steps a) to e) for all signal runs.
Claim 2
Independent Claim 183 words
A method for determining the electric transit time of signal runs which are in each instance connected at one end to a connecting point and which have at the other end a transmitter and a receiver comprising the steps of: a) short circuiting the connecting points (AS) of all signal runs (SS), b) turning off all receivers (E) except the receiver of the signal run to be measured, c) turning on all transmitters (S) except the transmitter of the signal run to be measured and simultaneously delivering a transmission pulse which is transmitted to the associated connecting point, d) superposing the transmission pulses at the shortcircuited connecting points (AS) to form a central pulse (ZI), and transmitting said central pulse over the signal run to be measured to the associated receiver, e) establishing the time of occurrence of a pulse triggered by the central pulse at the output of the receiver of the signal run to be measured and entering that time in a table as a measured value characterizing the transit time, f) repeating steps a) to e) for all signal runs.
Claim 3
Dependent Claim 25 words
The method according to claim 1, wherein said measured values stored in the table are normalized, said measured values being normalized using the lowest value.
Claim 4
Dependent Claim 66 words
The method according to claim 1 or 2, further comprising the step of starting strobe pulses at a fixed time in comparison with the triggering of transmission pulses to establish a time of occurrence of the central pulse (ZI) at the receiver of the signal run to be measured, the number of strobe pulses provided for control of the transmitter by the central pulse are counted.
Claim 5
Dependent Claim 38 words
The method according to claim 1, wherein said receiver (E) is a comparator which delivers the output pulse when the pulse triggered by the central pulse exceeds a reference value (UR) and a strobe pulse (CL) is present.
Claim 6
Dependent Claim 47 words
The method according to claim 1, wherein the signal runs (SS) comprise the transmitter (S), a line (L) connected to the output, and the receiver (E) connected at the junction point between transmitter and line, the free end of the line (L) forming the connecting point (AS).
Claim 7
Dependent Claim 24 words
The method according to claim 1, wherein the signal runs (SS) form the reception signal path from the test pin of an automatic tester.
Claim 8
Dependent Claim 38 words
The method according to claim 2, wherein said receiver (E) is a comparator which delivers the output pulse when the pulse triggered by the central pulse exceeds a reference value (UR) and a strobe pulse (CL) is present.
Claim 9
Dependent Claim 38 words
The method according to claim 3, wherein said receiver (E) is a comparator which delivers the output pulse when the pulse triggered by the central pulse exceeds a reference value (UR) and a strobe pulse (CL) is present.
Claim 10
Dependent Claim 47 words
The method according to claim 2, wherein the signal runs (SS) comprise the transmitter (S), a line (L) connected to the output, and the receiver (E) connected at the junction point between transmitter and line, the free end of the line (L) forming the connecting point (AS).
Claim 11
Dependent Claim 47 words
The method according to claim 3, wherein the signal runs (SS) comprise the transmitter (S), a line (L) connected to the output, and the receiver (E) connected at the junction point between transmitter and line, the free end of the line (L) forming the connecting point (AS).
Claim 12
Dependent Claim 47 words
The method according to claim 4, wherein the signal runs (SS) comprise the transmitter (S), a line (L) connected to the output, and the receiver (E) connected at the junction point between transmitter and line, the free end of the line (L) forming the connecting point (AS).
Claim 13
Dependent Claim 47 words
The method according to claim 7, wherein the signal runs (SS) comprise the transmitter (S), a line (L) connected to the output, and the receiver (E) connected at the junction point between transmitter and line, the free end of the line (L) forming the connecting point (AS).
Claim 14
Dependent Claim 47 words
The method according to claim 8, wherein the signal runs (SS) comprise the transmitter (S), a line (L) connected to the output, and the receiver (e) connected at the junction point between transmitter and line, the free end of the line (L) forming the connecting point (AS).
Claim 15
Dependent Claim 24 words
The method according to claim 2, wherein the signal runs (SS) form the reception signal path from the test pin of an automatic tester.
Claim 16
Dependent Claim 24 words
The method according to claim 3, wherein the signal runs (SS) form the reception signal path from the test pin of an automatic tester.
Claim 17
Dependent Claim 24 words
The method according to claim 4, wherein the signal runs (SS) form the reception signal path from the test pin of an automatic tester.
Claim 18
Dependent Claim 24 words
The method according to claim 5, wherein the signal runs (SS) form the reception signal path from the test pin of an automatic tester.
Claim 19
Dependent Claim 24 words
The method according to claim 8, wherein the signal runs (SS) form the reception signal path from the test pin of an automatic tester.
Claim 20
Dependent Claim 24 words
The method according to claim 9, wherein the signal runs (SS) form the reception signal path from the test pin of an automatic tester.
Claim 21
Dependent Claim 24 words
The method according to claim 13, wherein the signal runs (SS) form the reception signal path from the test pin of an automatic tester.

References Cited (Backward Citations)

US4097801A Cited
DE2752331A1 Cited
DE2833608A1 Cited
US4569599A Cited
US4688947A Cited
US4792932A Cited
US4841500A Cited
US4866685A Cited
US4878209A Cited
US4858208A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1994-10-14 1995-04-15 1995-10-15 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1998-10-14 1999-04-15 1999-10-15 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2002-10-14 2003-04-15 2003-10-15 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag