Claims Analysis
Total Claims: 8
Claim 1
Independent Claim
278 words
A method of relocating a selected layer of soil in a strip mining operation in which the remaining overburden above a mineral seam is separately removed along the highwall side of an elongated pit and deposited in a previously mined out area adjacent to the opposite side of the pit, comprising the steps of: (a) sectioning an area of said selected layer into a series of rectangles arranged end-to-end parallel to the pit; (b) further dividing each of said rectangles into a series of side-by-side strips, each extending parallel to the pit and the length of the rectangle; (c) excavating the selected layer starting at one end of the nearest strip in a first rectangle and progressing along said strip to its opposite end; (d) transferring the loosened soil over and across the pit and distributing it on said separately relocated overburden material in a strip substantially corresponding to the strip from which said soil came; (e) repeating steps (c) and (d) to excavate and transfer the soil from the next adjacent strip in the first rectangle and deposit it in a corresponding strip adjacent the first deposited strip; (f) repeating step (e) until all of the soil from the first rectangle has been removed and relocated to a corresponding rectangle on the reclamation side; (g) repeating steps (c) through (f) to excavate and transfer the soil from the next adjacent rectangular area; and (h) repeating step (g) until all of the soil from the row of rectangles has been transferred over and across the pit and deposited on the relocated overburden in a pattern of aligned rectangles corresponding to the originally surveyed rectangles on the highwall side.
Claim 2
Independent Claim
278 words
A method of relocating a selected layer of soil in a strip mining operation in which the remaining overburden above a mineral seam is separately removed along the highwall side of an elongated pit and deposited in a previously mined out area adjacent to the opposite side of the pit, comprising the steps of: (a) sectioning an area of said selected layer into a series of rectangles arranged end-to-end parallel to the pit; (b) further dividing each of said rectangles into a series of side-by-side strips, each extending parallel to the pit and the length of the rectangle; (c) excavating the selected layer starting at one end of the nearest strip in a first rectangle and progressing along said strip to its opposite end; (d) transferring the loosened soil over and across the pit and distributing it on said separately relocated overburden material in a strip substantially corresponding to the strip from which said soil came; (e) repeating steps (c) and (d) to excavate and transfer the soil from the next adjacent strip in the first rectangle and deposit it in a corresponding strip adjacent the first deposited strip; (f) repeating step (e) until all of the soil from the first rectangle has been removed and relocated to a corresponding rectangle on the reclamation side; (g) repeating steps (c) through (f) to excavate and transfer the soil from the next adjacent rectangular area; and (h) repeating step (g) until all of the soil from the row of rectangles has been transferred over and across the pit and deposited on the relocated overburden in a pattern of aligned rectangles corresponding to the originally surveyed rectangles on the highwall side.
Claim 3
Independent Claim
198 words
A method of relocating a soil layer in a strip mining operation in which the overburden underlaying said soil layer and overlaying the targeted mineral seam is separately removed along the highwall side of an elongated pit and deposited in a previously mined out area on the opposite side of the pit, comprising the steps of: (a) dividing an area of the soil layer into a series of rectangles aligned end-to-end parallel to the pit; (b) further dividing each of said rectangles into a series of side-by-side strips extending parallel to the pit and end-to-end of the rectangle; (c) providing an excavator on the highwall bench and excavating the soil layer from each rectangular area starting with the strip nearest the pit and proceeding end-to-end thereof and then in similar fashion strip-by-strip across the width of the rectangle; (d) providing a cantilevered cross-pit conveyor on the highwall and concurrently with step (c) conveying the excavated soil across the pit and depositing it on the separately relocated overburden in a series of side-by-side elongated piles corresponding to the strips from which said soil layer was excavated; and (e) proceeding to the next rectangle and repeating steps (c) and (d).
Claim 4
Independent Claim
198 words
A method of relocating a soil layer in a strip mining operation in which the overburden underlaying said soil layer and overlaying the targeted mineral seam is separately removed along the highwall side of an elongated pit and deposited in a previously mined out area on the opposite side of the pit, comprising the steps of: (a) dividing an area of the soil layer into a series of rectangles aligned end-to-end parallel to the pit; (b) further dividing each of said rectangles into a series of side-by-side strips extending parallel to the pit and end-to-end of the rectangle; (c) providing an excavator on the highwall bench and excavating the soil layer from each rectangular area starting with the strip nearest the pit and proceeding end-to-end thereof and then in similar fashion strip-by-strip across the width of the rectangle; (d) providing a cantilevered cross-pit conveyor on the highwall and concurrently with step (c) conveying the excavated soil across the pit and depositing it on the separately relocated overburden in a series of side-by-side elongated piles corresponding to the strips from which said soil layer was excavated; and (e) proceeding to the next rectangle and repeating steps (c) and (d).
Claim 5
Dependent Claim
67 words
A method as recited in claim 2, wherein step (d) comprises: providing a long cantilevered cross-pit conveyor pivotally mounted on a base positioned on the highwall and concurrently with step (c) conveying the excavated soil across the pit and by pivoting the cross-pit conveyor distributing said soil in a series of side-by-side elongated but slightly curved windrows corresponding substantially to the strips from which it was excavated.
Claim 6
Independent Claim
250 words
A method of separately excavating and relocating a layer of topsoil and a layer of sub-soil across an elongated pit in a strip mining operation, comprising the steps of: (a) dividing an undisturbed area of said layers into a series of rectangles aligned end-to-end parallel to the pit; (b) further dividing each of said rectangles into a series of side-by-side strips extending the length of the rectangle parallel to the pit; (c) stripping the topsoil layer off of a first of said rectangles and forming it into an elongated pile along the edge of said rectangle nearest the pit; (d) loading said stripped topsoil onto a cross-pit conveyor, conveying it across the pit and depositing it in a corresponding elongated pile beyond the far side of a rectangular area on the other side of the pit which conforms to said first rectangle; (e) excavating the sub-soil layer of said first rectangle starting with the strip nearest the pit and proceeding strip-by-strip across the width of said first rectangle; (f) concurrently with step (e) transferring the excavated sub-soil across the pit using the cross pit conveyor and depositing it in a series of side-by-side elongated piles corresponding to the strips from which it was excavated to cover the corresponding rectangular area on the other side of the pit; and (g) repeating steps (c) through (f) for each successive rectangle on the highwall side until all of the desired topsoil and sub-soil has been relocated to the other side of the pit.
Claim 7
Independent Claim
250 words
A method of separately excavating and relocating a layer of topsoil and a layer of sub-soil across an elongated pit in a strip mining operation, comprising the steps of: (a) dividing an undisturbed area of said layers into a series of rectangles aligned end-to-end parallel to the pit; (b) further dividing each of said rectangles into a series of side-by-side strips extending the length of the rectangle parallel to the pit; (c) stripping the topsoil layer off of a first of said rectangles and forming it into an elongated pile along the edge of said rectangle nearest the pit; (d) loading said stripped topsoil onto a cross-pit conveyor, conveying it across the pit and depositing it in a corresponding elongated pile beyond the far side of a rectangular area on the other side of the pit which conforms to said first rectangle; (e) excavating the sub-soil layer of said first rectangle starting with the strip nearest the pit and proceeding strip-by-strip across the width of said first rectangle; (f) concurrently with step (e) transferring the excavated sub-soil across the pit using the cross pit conveyor and depositing it in a series of side-by-side elongated piles corresponding to the strips from which it was excavated to cover the corresponding rectangular area on the other side of the pit; and (g) repeating steps (c) through (f) for each successive rectangle on the highwall side until all of the desired topsoil and sub-soil has been relocated to the other side of the pit.
Claim 8
Dependent Claim
39 words
A method as recited in claim 4 including the further steps of: (a) leveling the piles of relocated sub-soil over each of said rectangles; and (b) spreading said pile of relocated topsoil across the corresponding rectangle of leveled sub-soil.