Patent US7721552B2 successfully refreshed from Google Patents.
← Back to Patent Explorer
US7721552B2 Expired / Lapsed US ⏱️ 0.0 years remaining

Method for operation of a gas turbine group

Assignee: Phoenix Biopower AB
•
Filing: 2005-11-30
•
Granted: 2010-05-25
•
Expires: 2025-11-30
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method of operating a gas turbine power plant comprising of a first gas turbine group, consisting of a compressor and a turbine which are connected mechanically with one another, and a second gas turbine group, including a combustion device, which is placed in the gas flow stream between the first group's compressor and turbine, whereby the second gas turbine group consists of a compressor, a fuel injection device, a combustion chamber and a turbine, whereby the second gas turbine group's compressor and turbine are mechanically coupled to one another and at least one of the gas turbine groups having a device for the extraction of work, whereby the fact that a first flow of water and/or steam is heated with heat from the flue gas from the first group's turbine, that further amounts of water and/or steam are heated with heat from a gas stream that is compressed by the first group's compressor, and the produced water and/or steam is injected into the gas stream in such amounts that at least 60% of the oxygen content of the air in the stream is consumed through combustion in the combustion device, and in that the combustion gas that is fed into the turbine of the second gas turbine group has a pressure in the range 50-300 bar.

Inventors

  • 👤 Hans-Erik Hansson
  • 👤 Mats Westermark

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-26 20:40
CPC Classifications
F; F23; F23L; F23L7/00; F23L7/002; F23L7/005; F01; F01K; F01K21/00; F01K21/04; F01K21/047; F02; F02C; F02C3/00; F02C3/20; F02C3/30; F02C3/305; F02C6/00; F02C6/18; F02C7/00; F02C7/08; F02C7/12; F02C7/14; F02C7/141; F02C7/143; F05; F05D; F05D2260/00; F05D2260/20; F05D2260/232; F05D2260/2322; Y; Y02; Y02E; Y02E20/00; Y02E20/14

Claims Analysis

Total Claims: 22
Claim 1
Independent Claim 245 words
A method of operating a gas turbine power plant wherein the power plant is comprised of: a first gas turbine group, comprised of a first compressor and a first turbine which are connected mechanically with one another, a second gas turbine group comprised of a combustion device, which is placed in a gas flow stream between the first group's first compressor and first turbine, a second compressor, a fuel injection device, a combustion chamber and a second turbine, the second gas turbine group's second compressor and second turbine are mechanically coupled to one another, at least one of the first and second gas turbine groups having a device for extraction of useful work, the method comprising: producing flue gas from the first turbine and heating a first flow of water and/or steam with heat from the flue gas from the first group's turbine, compressing the gas stream from the first turbine in the first compressor, using heat from the compressed gas stream for heating further amounts of water and/or steam with heat from the gas stream that is compressed by the first group's first compressor, injecting the produced water and/or steam into the gas flow stream in such amounts that at least 60% of the oxygen content of the air in the gas flow stream is consumed through combustion in the combustion device, and feeding combustion gas into the second turbine of the second gas turbine group at a pressure in the range 50-300 bar.
Claim 2
Independent Claim 245 words
A method of operating a gas turbine power plant wherein the power plant is comprised of: a first gas turbine group, comprised of a first compressor and a first turbine which are connected mechanically with one another, a second gas turbine group comprised of a combustion device, which is placed in a gas flow stream between the first group's first compressor and first turbine, a second compressor, a fuel injection device, a combustion chamber and a second turbine, the second gas turbine group's second compressor and second turbine are mechanically coupled to one another, at least one of the first and second gas turbine groups having a device for extraction of useful work, the method comprising: producing flue gas from the first turbine and heating a first flow of water and/or steam with heat from the flue gas from the first group's turbine, compressing the gas stream from the first turbine in the first compressor, using heat from the compressed gas stream for heating further amounts of water and/or steam with heat from the gas stream that is compressed by the first group's first compressor, injecting the produced water and/or steam into the gas flow stream in such amounts that at least 60% of the oxygen content of the air in the gas flow stream is consumed through combustion in the combustion device, and feeding combustion gas into the second turbine of the second gas turbine group at a pressure in the range 50-300 bar.
Claim 3
Dependent Claim 33 words
A method according to claim 1 , further comprising injecting the further amount of water into the gas stream between the first group's first compressor and the second gas turbine group's second compressor.
Claim 4
Dependent Claim 66 words
A method according to claim 2 , wherein the further amounts of water that entirely or partially have the form of steam optionally are introduced in the gas stream downstream of the second gas turbine group's compressor, and are introduced in such amounts that at least 60% of the oxygen content of the air in the gas stream is consumed through combustion in the combustion device.
Claim 5
Dependent Claim 44 words
A method according to claim 1 , further comprising choosing operational characteristics such that the temperature of the gas flow entering the first gas turbine group's first turbine is at most 1200° C. and the pressure of the gas flow is between 5-60 bar.
Claim 6
Dependent Claim 33 words
A method according to claim 1 , further comprising choosing operational characteristics that cause a flue gas exit temperature from the first gas turbine group's first turbine in the range of 200-500° C.
Claim 7
Dependent Claim 37 words
A method according to claim 1 , wherein the first gas turbine group comprises a gas turbine unit, which is optimized for non-humidified operation, wherein the gas turbine unit has one or multiple shafts and includes intercooling.
Claim 8
Dependent Claim 68 words
A method according to claim 1 , further comprising arranging and operating the second gas turbine group's second turbine so that the pressure of the gas stream from the first gas turbine group's first compressor and to the first gas turbine group's first turbine, respectively, is re-allotted such that the first gas turbine group is well-suited to operate with the media and flow data associated with humidified cycles.
Claim 9
Dependent Claim 56 words
A method according to claim 6 , further comprising regulating inlet guide vanes of the first compressor of the first gas turbine group to reduce the flow of air obtained during operation of the power plant, and reducing the capacity of the first gas turbine group's first compressor through removing one or more compressor stages thereof.
Claim 10
Dependent Claim 72 words
A method according to claim 1 , further comprising complementing the first gas turbine group's first compressor with an extraction device and operating the extraction device to extract the compressed air, which is sealed against the axle, and complementing the first gas turbine group's first turbine with an injection device, which is also sealed against the axle, and returning the flue gas by injection into the first gas turbine group's first turbine.
Claim 11
Dependent Claim 52 words
A method according to claim 1 , further comprising: choosing an exit temperature of the first gas turbine group's first compressor to enable production of steam of sufficiently high pressure to be used to cool at least one of the second turbine and the combustion chamber of the second gas turbine group.
Claim 12
Dependent Claim 41 words
A method according to claim 1 , further comprising introducing combustion gases into the second gas turbine group's second turbine, the combustion gases having a pressure in the region of 50-300 bar and a temperature in the region of 1000-2000 K.
Claim 13
Dependent Claim 90 words
A method according to claim 1 , further comprising humidifying the gas exit flow from the second gas turbine group's second compressor prior to the second gas turbine group's combustion device, by passing at least a part of the gas flow through a humidifier, heat exchanging inlet and outlet gas streams from the heat exchanger via a recuperator, where inlet water to the humidifier is heated with heat from the gas outlet stream from at least one of the first compressor and the turbine of the first gas turbine group.
Claim 14
Dependent Claim 35 words
A method according to claim 1 , further comprising using at least a part of a water content of the flue gases to provide the process with at least one of feed water and steam.
Claim 15
Dependent Claim 43 words
A method according to claim 1 , further comprising regulating the output of work from the process through changing the amount of water that is transferred to the gas stream, whereby a lower power output is obtained through a lower degree of humidification.
Claim 16
Dependent Claim 43 words
A method according to claim 1 , further comprising introducing at least a part of the steam used for cooling into the gas stream after use for cooling, in the second gas turbine group's combustion chamber, for further use as the working fluid.
Claim 17
Dependent Claim 33 words
A method according to claim 1 , wherein no significant amount of heat is transferred to the gas stream between the second gas turbine group's second turbine and the first group's first turbine.
Claim 18
Dependent Claim 28 words
A method according to claim 1 , further comprising regulating the second gas turbine group's second compressor by regulating a lead guide vane or by regulating rotational speed.
Claim 19
Dependent Claim 30 words
A method according to claim 1 , wherein at least 10% of the useful work obtained from the process is extracted via a transmission of the second gas turbine group.
Claim 20
Dependent Claim 176 words
A method according to claim 1 , further comprising arranging a heat exchanger in the hot air flow downstream of the first compressor of the first gas turbine group, and flowing water through the heat exchanger for heating of the water, preheating the water in an exhaust gas heat exchanger upstream of a flue gas condenser from which the exhaust gas is exhausted from the first gas turbine group to the environment, producing the water by the flue gas condenser and heating a part flow of the water, in a preheated condition, by a heat exchanger, wherein the water is passed by flue gas from the first turbine of the first gas turbine group, wherein the water which is heated by the heat exchangers is at least partially transformed into steam, and the water is fed into one of the combustion chamber, the second turbine of the second gas turbine group or the compressed gas flow from the compressor of the second gas turbine group, for cooling the second turbine of the second gas turbine group.
Claim 21
Dependent Claim 25 words
A method according to claim 19 , wherein the water, which is fed into the combustion chamber, at least partially has the form of steam.
Claim 22
Dependent Claim 61 words
A method according to claim 19 , further comprising producing steam by an external boiler and feeding the produced steam into one of the combustion chamber, the second turbine of the second gas turbine group or the compressed gas flow from the compressor of the second gas turbine group, for cooling of the second turbine of the second gas turbine group.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 2013-05-24 2013-11-23 2014-05-25 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2017-05-24 2017-11-23 2018-05-25 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2021-05-24 2021-11-23 2022-05-25 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag