Abstract

Abstract A method and apparatus for a combined turbine installation includes a gas turbine group with a compressor having a water cooler, a combustion chamber and a gas turbine, and having a steam turbine installation with a waste heat boiler heated by the exhaust gas from the gas turbine. The waste heat boiler includes an evaporator, drum, enconomizer and superheater, a steam turbine downstream of the waste heat boiler and a combined feed water tank/flash evaporator unit. The feed water tank/flash evaporator is supplied with condensate from a condenser fitted downstream of the steam turbine. Cooling water heated by the compressed air is evaporated in at least one state and the steam produced is fed to the waste heat boiler for further heating, or directly to the steam turbine. In addition, the unevaporated residual water is fed to the feed water tank/flash evaporation unit, and after mixing with the condensate from the steam turbine, is supplied to the compressor cooler.

Inventors

  • 👤 Hans U. Frutschi

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-27 22:21
CPC Classifications
F; F01; F01K; F01K23/00; F01K23/02; F01K23/06; F01K23/10; F01K23/106; F02; F02C; F02C6/00; F02C6/18; F02C7/00; F02C7/12; F02C7/14; F02C7/141; F02C7/143; F05; F05D; F05D2260/00; F05D2260/20; F05D2260/211; Y; Y02; Y02E; Y02E20/00; Y02E20/16

Claims Analysis

Total Claims: 11
Claim 1
Independent Claim 138 words
A method for operating a combined gas turbine and steam turbine installation, comprising the steps of: compressing air for the gas turbine in at least two stages; cooling compressed air from a first compressor stage prior to further compression with water in a cooling unit; evaporating to steam at least part of the water heated by the compressed air in at least a first stage; heating further the steam from the first stage in a waste heat boiler; supplying the further heated steam to the steam turbine; condensing exhaust steam from a steam turbine; collecting the condensed steam in a combined feed water tank and evaporation unit; directing heated water not evaporated to steam to the feed water tank and evaporation unit; and, supplying water from the feed water tank and evaporation unit to the compressor cooling unit.
Claim 2
Independent Claim 138 words
A method for operating a combined gas turbine and steam turbine installation, comprising the steps of: compressing air for the gas turbine in at least two stages; cooling compressed air from a first compressor stage prior to further compression with water in a cooling unit; evaporating to steam at least part of the water heated by the compressed air in at least a first stage; heating further the steam from the first stage in a waste heat boiler; supplying the further heated steam to the steam turbine; condensing exhaust steam from a steam turbine; collecting the condensed steam in a combined feed water tank and evaporation unit; directing heated water not evaporated to steam to the feed water tank and evaporation unit; and, supplying water from the feed water tank and evaporation unit to the compressor cooling unit.
Claim 3
Dependent Claim 52 words
The method as claimed in claim 1, wherein the water heated by the compressor air is directed to a steam drum integrated with the waste heat boiler as the first stage and therein partially evaporates, and the steam formed in the drum is superheated before it is fed to the steam turbine.
Claim 4
Dependent Claim 45 words
The method as claimed in claim 1, wherein residual water not evaporated in the first stage is fed to the combined feed water heater and flash evaporator and there expanded to steam, the steam being fed to the steam turbine at a suitable pressure location.
Claim 5
Dependent Claim 68 words
The method as claimed in claim 1, wherein the first stage evaporation comprises feeding the heated cooling water to a flash evaporator for evaporation to steam, further heating the steam formed in the flash evaporator in the waste heat boiler and feeding the heated steam to the turbine, wherein residual water not evaporated in the flash evaporator is fed to the combined feed water tank and flash evaporator.
Claim 6
Dependent Claim 67 words
The method as claimed in claim 4, wherein residual water not evaporated in the flash evaporator is fed to a second flash evaporator and therein evaporated to steam, the steam formed in the second flash evaporator being supplied to an intermediated stage of the steam turbine and residual water not evaporated in the second flash evaporator is fed to the combined feed water tank and flash evaporator.
Claim 7
Dependent Claim 167 words
A combined gas turbine and steam turbine installation, comprising: a gas turbine group having a two stage compressor, a cooler to cool air compressed in a first stage using water, a combustion chamber downstream of the compressor, and a gas turbine downstream of the combustion chamber; and a steam turbine group having a waste heat boiler connected to receive exhaust from the gas turbine, the waste heat boiler integrated with an evaporation vessel, the evaporation vessel having at least a superheater integrated with the waste heat boiler, a steam turbine connected downstream of the superheater, a condenser connected to receive and condense exhaust steam from the steam turbine and combined feed water tank and flash evaporator connected downstream of the condenser; wherein the combined feed water tank is connected to supply water to the cooler for the compressor, and the cooler is connected to deliver heated water to at least the evaporation vessel to evaporate a quantity of steam from the heated water for the steam turbine.
Claim 8
Dependent Claim 167 words
A combined gas turbine and steam turbine installation, comprising: a gas turbine group having a two stage compressor, a cooler to cool air compressed in a first stage using water, a combustion chamber downstream of the compressor, and a gas turbine downstream of the combustion chamber; and a steam turbine group having a waste heat boiler connected to receive exhaust from the gas turbine, the waste heat boiler integrated with an evaporation vessel, the evaporation vessel having at least a superheater integrated with the waste heat boiler, a steam turbine connected downstream of the superheater, a condenser connected to receive and condense exhaust steam from the steam turbine and combined feed water tank and flash evaporator connected downstream of the condenser; wherein the combined feed water tank is connected to supply water to the cooler for the compressor, and the cooler is connected to deliver heated water to at least the evaporation vessel to evaporate a quantity of steam from the heated water for the steam turbine.
Claim 9
Dependent Claim 64 words
The installation as claimed in claim 6, wherein the evaporation vessel comprising a drum integrated with the waste heat boiler by an economizer connected to receive water from the combined feed water tank and flash evaporator and deliver heated water to the drum, an evaporator to evaporate water from the drum and return steam to the drum and a superheater to heat the steam.
Claim 10
Dependent Claim 81 words
The installation as claimed in claim 6, wherein the evaporation vessel comprises at least one flash evaporator connected to receive heated water from the compressor cooler, and further comprising a drum integrated with the waste heat boiler by an economizer connected to receive water from the combined feed water tank and flash evaporator and deliver heated water to the drum, an evaporator to evaporate water from the drum and return steam to the drum and a superheater to heat the steam.
Claim 11
Dependent Claim 66 words
The installation as claimed in claim 8, wherein a plurality of evaporation vessels are connected in series, a first of said vessels being integrated with the waste heat boiler by a superheater and wherein each succeeding evaporation vessel is matched to the respectively previous evaporation vessel with respect to pressure and temperature, each of the evaporation vessels being connected to deliver steam to the steam turbine.

References Cited (Backward Citations)

US3335565A Cited
DE2731097A1 Cited
US4261166A Cited
US4896499A Cited
US4896499B1 Cited
GB2153912A Cited
SU1195020A1 Cited
US4720968A Cited
DE4137946A1 Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1998-02-06 1998-08-08 1999-02-07 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2002-02-06 2002-08-08 2003-02-07 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2006-02-06 2006-08-08 2007-02-07 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag