Patent US5577377A successfully refreshed from Google Patents.
← Back to Patent Explorer
US5577377A Expired / Lapsed US ⏱️ 0.0 years remaining

Combined cycle with steam cooled gas turbine

Assignee: General Electric Co
•
Filing: 1995-05-16
•
Granted: 1996-11-26
•
Expires: 2015-05-16
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract In a method of operating a combined cycle system including a gas turbine, a steam turbine and a multi-pressure heat recovery steam generator, an improvement includes supplying gas turbine cooling duty steam from a high pressure section of the steam turbine and from an intermediate pressure evaporator in the multi-pressure heat recovery steam generator, conducting the gas turbine cooling duty steam to the gas turbine for cooling hot gas turbine parts, and then returning the gas turbine cooling duty steam to an intermediate pressure section of the steam turbine. In a start-up procedure, steam is extracted from a first pass of a high pressure superheater in the multi-pressure heat recovery steam generator, mixed with steam discharged from the high pressure superheater and then supplied to the gas turbine cooling duty system. In this same start-up procedure, the gas turbine cooling duty steam is returned to the system condenser, bypassing the intermediate pressure section of the steam turbine. Related apparatus is also disclosed.

Inventors

  • 👤 Leroy O. Tomlinson

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-30 20:11
CPC Classifications
F; F02; F02C; F02C6/00; F02C6/18; F01; F01K; F01K23/00; F01K23/02; F01K23/06; F01K23/10; F01K23/106; F02C7/00; F02C7/12; F02C7/16; F02C7/18; F05; F05D; F05D2260/00; F05D2260/20; F05D2260/232; F05D2260/2322; Y; Y02; Y02E; Y02E20/00; Y02E20/16

Claims Analysis

Total Claims: 14
Claim 1
Independent Claim 108 words
In a method of operating a combined cycle system including a gas turbine, a steam turbine and a multi-pressure heat recovery steam generator, wherein gas turbine exhaust is used in the heat recovery steam generator for reheating steam from the steam turbine, the improvement comprising supplying gas turbine cooling duty steam from a high pressure section of the steam turbine and from an intermediate pressure evaporator in the multi-pressure heat recovery steam generator, conducting the gas turbine cooling duty steam to the gas turbine for cooling hot gas turbine parts, and then returning the gas turbine cooling duty steam to an intermediate pressure section of the steam turbine.
Claim 2
Dependent Claim 108 words
In a method of operating a combined cycle system including a gas turbine, a steam turbine and a multi-pressure heat recovery steam generator, wherein gas turbine exhaust is used in the heat recovery steam generator for reheating steam from the steam turbine, the improvement comprising supplying gas turbine cooling duty steam from a high pressure section of the steam turbine and from an intermediate pressure evaporator in the multi-pressure heat recovery steam generator, conducting the gas turbine cooling duty steam to the gas turbine for cooling hot gas turbine parts, and then returning the gas turbine cooling duty steam to an intermediate pressure section of the steam turbine.
Claim 3
Dependent Claim 32 words
The method of claim 1 wherein, early in start-up, prior to the availability of any cooling steam, the gas turbine hot stationary and rotating parts are cooled with filtered compressor discharge air.
Claim 4
Dependent Claim 36 words
The method of claim 1 wherein, during start-up, as start-up cooling steam is being established, the start-up cooling steam is bypassed around the intermediate pressure section of the steam turbine to warm the piping and valves.
Claim 5
Dependent Claim 46 words
The method of claim 1 wherein, during start-up, steam is extracted from a first pass of a high pressure superheater in the multi-pressure heat recovery steam generator, mixed with steam discharged from the high pressure superheater and then supplied to the gas turbine cooling duty system.
Claim 6
Dependent Claim 28 words
The method of claim 1 wherein, during staff-up, the gas turbine cooling duty steam is returned to a condenser, bypassing the intermediate pressure section of the steam turbine.
Claim 7
Dependent Claim 79 words
The method of claim 1 wherein the heat recovery steam generator includes a high pressure superheater and wherein the method includes controlling temperature in the high pressure superheater by: a) extracting superheater steam from a first pass of the superheater; b) conducting the extracted steam outside the heat recovery steam generator; and c) reintroducing the extracted steam at the inlet of the final superheater, which occurs first in the gas path, ahead of all other HRSG heat transfer surfaces.
Claim 8
Dependent Claim 35 words
The method of claim 1 wherein the gas turbine cooling duty steam is mixed with steam from a reheater in the heat recovery steam generator upstream of the intermediate pressure section of the steam turbine.
Claim 9
Dependent Claim 90 words
In a combined cycle system including a gas turbine, a steam turbine and a multi-pressure heat recovery steam generator, the improvement comprising means for supplying gas turbine cooling duty steam from a high pressure section of the steam turbine and from an intermediate pressure evaporator in the multi-pressure heat recovery steam generator; means for conducting the gas turbine cooling duty steam to the gas turbine for cooling hot gas turbine pans; and means for returning the gas turbine cooling duty steam to an intermediate pressure section of the steam turbine.
Claim 10
Dependent Claim 90 words
In a combined cycle system including a gas turbine, a steam turbine and a multi-pressure heat recovery steam generator, the improvement comprising means for supplying gas turbine cooling duty steam from a high pressure section of the steam turbine and from an intermediate pressure evaporator in the multi-pressure heat recovery steam generator; means for conducting the gas turbine cooling duty steam to the gas turbine for cooling hot gas turbine pans; and means for returning the gas turbine cooling duty steam to an intermediate pressure section of the steam turbine.
Claim 11
Dependent Claim 60 words
The improvement of claim 8 wherein a start-up circuit is provided which includes means for extracting steam from a first pass of a high pressure superheater in the multi-pressure heat recovery steam generator; means for mixing the extracted steam with steam discharged from the high pressure superheater; and means for supplying the mixed steam to the gas turbine cooling system.
Claim 12
Dependent Claim 45 words
The improvement of claim 8 and including means for mixing the gas turbine cooling duty steam with steam from a reheater in the heat recovery steam generator before the gas turbine cooling duty steam is returned to the intermediate pressure section of the steam turbine.
Claim 13
Dependent Claim 28 words
The improvement of claim 9 wherein means are provided for returning gas turbine cooling duty steam to a condenser, bypassing the intermediate pressure section of the steam turbine.
Claim 14
Dependent Claim 61 words
The improvement of claim 8 wherein the heat recovery steam generator includes a multi-pass superheater and wherein means are provided for controlling temperature in the superheater by extracting steam from a first pass of the superheater, for conducting the extracted steam outside the heat recovery steam generator, and for reintroducing the extracted steam at the inlet end of the final superheater.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1999-11-26 2000-05-27 2000-11-26 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2003-11-26 2004-05-27 2004-11-26 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2007-11-26 2008-05-27 2008-11-26 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag