Abstract

Abstract Method of and system for monitoring the operation of a stamping press including a punch and a die for forming parts from a blank based on processed punch tonnages measurements at predetermined locations in the working stroke. The method includes selecting at least two punch locations at which a press variable measurement will be made and operating the stamping press so as to produce production parts to measure a production press operating variable at the locations for each production part produced. The method also includes processing the production press operating variables to obtain production operating parameters and comparing the production operating parameters to predetermined operating limits representing limits within which the variation in blank thickness and work hardening coefficient of the sheet metal are in control and acceptable stampings are being produced.

Inventors

  • 👤 Suresh M. Mangrulkar

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-01 17:19
CPC Classifications
G; G05; G05B; G05B19/00; G05B19/02; G05B19/418; G05B19/41875; B; B30; B30B; B30B15/00; B30B15/26; G01; G01L; G01L5/00; G01L5/0061; G01L5/0076; G05B2219/00; G05B2219/30; G05B2219/32; G05B2219/32191; G05B2219/50; G05B2219/50197; Y; Y02; Y02P; Y02P90/00; Y02P90/02

Claims Analysis

Total Claims: 13
Claim 1
Independent Claim 155 words
A method of monitoring the operation of a stamping press including a punch and a die for forming parts from a blank, the method comprising: selecting at least two ram locations at which a press variable measurement will be made; operating the stamping press so as to produce production parts to measure a production press operating variable at the locations for each production part produced; operating the stamping press so as to produce a predetermined number of baseline parts to measure baseline mean press operating variables at the locations; processing the press operating variables to obtain press operating parameters; determining a deviation of the press operating variables from the baseline mean press operating variables; and comparing the press operating parameters to predetermined operating limits representing limits within which acceptable stampings are produced; wherein the step of processing includes estimating a deviation in the blank thickness (dTh) based on the press operating parameters for the locations.
Claim 2
Independent Claim 155 words
A method of monitoring the operation of a stamping press including a punch and a die for forming parts from a blank, the method comprising: selecting at least two ram locations at which a press variable measurement will be made; operating the stamping press so as to produce production parts to measure a production press operating variable at the locations for each production part produced; operating the stamping press so as to produce a predetermined number of baseline parts to measure baseline mean press operating variables at the locations; processing the press operating variables to obtain press operating parameters; determining a deviation of the press operating variables from the baseline mean press operating variables; and comparing the press operating parameters to predetermined operating limits representing limits within which acceptable stampings are produced; wherein the step of processing includes estimating a deviation in the blank thickness (dTh) based on the press operating parameters for the locations.
Claim 3
Dependent Claim 59 words
The method of claim 1 wherein the deviation in blank thickness is estimated according to the following relationship: dTh=((ΔLf.sub.2 +ΔLf.sub.1)/2)*(B.sub.t) wherein ΔLf 2 and ΔLf 1 are deviations in the production press operating variables from associated baseline mean press operating variables expressed as fractions, and B t is the thickness of the blank used to form the baseline parts.
Claim 4
Dependent Claim 34 words
The method of claim 1 wherein the step of processing includes estimating a parameter (dN) proportional to a deviation in the work hardening coefficient based on the production press operating variables at the locations.
Claim 5
Dependent Claim 42 words
The method of claim 3 wherein the parameter (dN) is estimated according to the following relationship: dN=(ΔLf.sub.2 -ΔLf.sub.1) wherein ΔLf 2 and ΔLf 1 are deviations in the production press operating variables from associated baseline mean press operating variables expressed as fractions.
Claim 6
Independent Claim 157 words
A method of monitoring the operation of a stamping press including a punch and a die for forming parts from a blank, the method comprising: selecting at least two ram locations at which a press variable measurement will be made; operating the stamping press so as to produce a predetermined number of baseline parts to measure a baseline mean tonnage at the locations; operating the stamping press so as to produce production parts to measure a press tonnage at the locations for the production parts produced; establishing operating limits based on the baseline mean tonnages at the locations, the operating limits representing limits within which the stamping process is in control or producing acceptable parts; processing the tonnages at the locations to obtain press operating parameters, the processing including determining a deviation of the tonnages from the baseline mean tonnages; and estimating a deviation in the blank thickness (dTH) based on the production tonnages at the locations.
Claim 7
Independent Claim 157 words
A method of monitoring the operation of a stamping press including a punch and a die for forming parts from a blank, the method comprising: selecting at least two ram locations at which a press variable measurement will be made; operating the stamping press so as to produce a predetermined number of baseline parts to measure a baseline mean tonnage at the locations; operating the stamping press so as to produce production parts to measure a press tonnage at the locations for the production parts produced; establishing operating limits based on the baseline mean tonnages at the locations, the operating limits representing limits within which the stamping process is in control or producing acceptable parts; processing the tonnages at the locations to obtain press operating parameters, the processing including determining a deviation of the tonnages from the baseline mean tonnages; and estimating a deviation in the blank thickness (dTH) based on the production tonnages at the locations.
Claim 8
Dependent Claim 57 words
The method of claim 5 wherein the deviation in the blank thickness is estimated according to the following relationships: dTH=((ΔLf.sub.2 +ΔLf.sub.1)/2)*(B.sub.t) wherein ΔLf 2 and ΔLf 1 are deviations in the production tonnages from the associated baseline mean tonnages expressed as fractions, and B t is the thickness of the blank used to form the baseline parts.
Claim 9
Dependent Claim 32 words
The method of claim 5 wherein the step of establishing includes estimating a parameter (dN) proportional to a deviation in the work hardening coefficient based on the production tonnages at the locations.
Claim 10
Dependent Claim 39 words
The method of claim 7 wherein the parameter (dN) is estimated according to the following relationship: dN=(ΔLf.sub.2 -ΔLf .sub.1) wherein ΔLf 2 and ΔLf 1 are deviations in the production tonnages from the associated baseline tonnages expressed as fractions.
Claim 11
Dependent Claim 204 words
For use with a stamping press including a punch and a die for forming parts, a system for monitoring the process of forming the parts, the system comprising: means for selecting at least two ram locations at which a press variable measurement will be made while the press is operating; means for measuring a baseline mean operating variable at the locations while a predetermined number of baseline parts are being produced; means for measuring a press operating variable at the locations while production parts are being produced; means for establishing operating limits based on the baseline mean operating variables, the operating limits representing limits within which the stamping process is in control or producing acceptable parts; means for processing the press operating variables to obtain press operating parameters, including means for estimating a deviation in the blank thickness (dTH), based on the press operating variables for the locations, according to the following relationship: dTH=((ΔLf.sub.2 +ΔLf.sub.1) wherein ΔLf 2 and ΔLf 1 are deviations in the production operating variables expressed as fractions, and B t is the thickness of the blank used to form the baseline parts; and means for comparing the press operating parameters to the operating limits for the purpose of process control.
Claim 12
Dependent Claim 204 words
For use with a stamping press including a punch and a die for forming parts, a system for monitoring the process of forming the parts, the system comprising: means for selecting at least two ram locations at which a press variable measurement will be made while the press is operating; means for measuring a baseline mean operating variable at the locations while a predetermined number of baseline parts are being produced; means for measuring a press operating variable at the locations while production parts are being produced; means for establishing operating limits based on the baseline mean operating variables, the operating limits representing limits within which the stamping process is in control or producing acceptable parts; means for processing the press operating variables to obtain press operating parameters, including means for estimating a deviation in the blank thickness (dTH), based on the press operating variables for the locations, according to the following relationship: dTH=((ΔLf.sub.2 +ΔLf.sub.1) wherein ΔLf 2 and ΔLf 1 are deviations in the production operating variables expressed as fractions, and B t is the thickness of the blank used to form the baseline parts; and means for comparing the press operating parameters to the operating limits for the purpose of process control.
Claim 13
Dependent Claim 56 words
The system of claim 9 wherein the means for processing includes estimating a parameter (dN) proportional to a deviation in the work hardening coefficient, based on the production operating variables for the locations, according to the following relationship: d=(ΔLf.sub.2 -ΔLf.sub.1) wherein ΔLf 2 and ΔLf 1 are deviations in the production operating variables expressed as fractions.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1998-06-12 1998-12-12 1999-06-13 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2002-06-12 2002-12-12 2003-06-13 $3760.00 Window Closed / Lapsed