Abstract

Abstract A method for intermittent steam injection which comprises completing wells in more than one zone and selecting a number of wells as steam injectors. As interwell communication (temperature breakthrough) develops, producers are shut-in to allow for the reservoir pressure to build up and heat to propagate from the channel of communication (e.g., fractures) to the reservoir matrix. The injection phase is followed by blowdown. Thereafter, shut in producers and, in certain other cases, injectors are put on production.

Inventors

  • 👤 Bassem R. Alameddine

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 20:19
CPC Classifications
E; E21; E21B; E21B43/00; E21B43/30; E21B43/16; E21B43/24

Claims Analysis

Total Claims: 9
Claim 1
Independent Claim 127 words
A method to improve vertical sweep efficiency during intermittent steam injection into a multi-layered oil containing reservoir comprising: a. injecting a substantially large volume of steam into said reservoir via at least one injector well into a lower level of said reservoir while at least one producer well is shut in which pressurizes the reservoir and propagates heat away from any induced fracture; b. allowing the reservoir pressure to increase as steam injection continues until steam has entered each layer of the reservoir; c. shutting in the injector well and allowing each layer of the reservoir to heat up so as to reduce the viscosity of oil contained in each layer; and d. opening the producer well and producing oil to the surface thereby completing one cycle.
Claim 2
Independent Claim 127 words
A method to improve vertical sweep efficiency during intermittent steam injection into a multi-layered oil containing reservoir comprising: a. injecting a substantially large volume of steam into said reservoir via at least one injector well into a lower level of said reservoir while at least one producer well is shut in which pressurizes the reservoir and propagates heat away from any induced fracture; b. allowing the reservoir pressure to increase as steam injection continues until steam has entered each layer of the reservoir; c. shutting in the injector well and allowing each layer of the reservoir to heat up so as to reduce the viscosity of oil contained in each layer; and d. opening the producer well and producing oil to the surface thereby completing one cycle.
Claim 3
Dependent Claim 20 words
The method as recited in claim 1 where after step (d), steps (a) through (d) are repeated for eight cycles.
Claim 4
Dependent Claim 30 words
The method as recited in claim 1 where the volume of steam injected is increased during each subsequent cycle which results in deeper contact of the reservoir matrix by steam.
Claim 5
Dependent Claim 25 words
The method as recited in claim 1 were oil is produced from the formation for about 200 to 300 days before commencing another injection cycle.
Claim 6
Dependent Claim 23 words
The method as recited in claim 1 where initially steam comprising over 10% of the reservoir's pore volume is injected into the reservoir.
Claim 7
Dependent Claim 33 words
The method as recited in claim 1 where the injector well in step (d) is shut in for a desired time and thereafter oil is produced from both the injector and producer wells.
Claim 8
Dependent Claim 18 words
The method as recited in claim 1 where at least two injector and two producer wells are utilized.
Claim 9
Dependent Claim 53 words
The method as recited in claim 1 where after step (d), steps (a) through (d) are repeated for three cycles where the volume of steam injected is increased during each subsequent cycle and thereafter, steps (a) through (d) are repeated for four cycles during which the volume of steam injected is kept constant.

References Cited (Backward Citations)

CA733808A Cited
US3332482A Cited
US3796262A Cited
US3771598A Cited
US4130163A Cited
US4182416A Cited
US4257650A Cited
US4271905A Cited
US4262745A Cited
US4445573A Cited
US4612989A Cited
US4635720A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1994-01-21 1994-07-23 1995-01-22 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1998-01-21 1998-07-23 1999-01-22 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2002-01-21 2002-07-23 2003-01-22 $7700.00 Window Closed / Lapsed