Method and device for forming a fluid permeation control layer of the ground

Assignee: Individual
•
Filing: 1987-05-14
•
Granted: 1989-06-13
•
Expires: 2007-05-14
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract There is provided a method for forming a subterranean fluid permeation control layer in an area of ground. The method comprises the steps of forming a first portion of a trench of a predetermined depth from the surface of the ground and sequentially widening the trench along one side of the previously formed trench while selectively, simultaneously applying a fluid permeation layer substantially along the bottom surface of the previously formed trench and while at least partly covering the layer with earth removed from the widened portion of the trench being formed until the entire area of the ground is covered. The invention also provides a device for carrying out this method.

Inventors

  • 👤 Shlomo Pinto

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 08:24
CPC Classifications
A; A01; A01G; A01G25/00; E; E02; E02D; E02D19/00; E02D19/06; E02D19/12; E02D19/18; E02D31/00; E02D31/02; E02F; E02F3/00; E02F3/04; E02F3/76; E02F3/7663; E02F3/7668; E02F3/7695; E02F5/00; E02F5/02; E02F5/10; A01G25/003

Claims Analysis

Total Claims: 19
Claim 1
Independent Claim 163 words
A method for forming a subterranean fluid permeation control layer in an area of ground for controlling fluid passage therethrough, comprising the steps of: (a) forming a first portion of a trench of a predetermined depth from the surface of the ground; (b) widening said trench along one side thereof to form a widened portion; (c) applying a fluid permeation control layer substantially along the bottom surface of said first portion of said trench; (d) only partly covering said layer with earth removed from a widened portion of said trench such that at least the edge of said layer adjacent said one side of the trench remains uncovered; and (e) selectively repeating steps (b), (c) and (d) until the entire area of the ground is lined by the permeation control layer, wherein, in repeating step (c) a newly applied layer is applied along the bottom surface of an adjacent, previously widened portion of the trench, partly contacting and overlapping an adjoining applied layer.
Claim 2
Independent Claim 163 words
A method for forming a subterranean fluid permeation control layer in an area of ground for controlling fluid passage therethrough, comprising the steps of: (a) forming a first portion of a trench of a predetermined depth from the surface of the ground; (b) widening said trench along one side thereof to form a widened portion; (c) applying a fluid permeation control layer substantially along the bottom surface of said first portion of said trench; (d) only partly covering said layer with earth removed from a widened portion of said trench such that at least the edge of said layer adjacent said one side of the trench remains uncovered; and (e) selectively repeating steps (b), (c) and (d) until the entire area of the ground is lined by the permeation control layer, wherein, in repeating step (c) a newly applied layer is applied along the bottom surface of an adjacent, previously widened portion of the trench, partly contacting and overlapping an adjoining applied layer.
Claim 3
Dependent Claim 31 words
The method as claimed in claim 1 wherein said layer is a layer of sheet material which is applied on said bottom surface by rolling the same off a supply roll.
Claim 4
Dependent Claim 24 words
The method as claimed in claim 1 wherein said layer is formed by spraying fluid repellent material upon the bottom surface of said trench.
Claim 5
Dependent Claim 23 words
The method as claimed in claim 2 further comprising the step of causing the sheets adhere to each other along the overlapping area.
Claim 6
Dependent Claim 24 words
The method as claimed in claim 1 further comprising the step of smoothing the bottom surface of the trench prior to applying said layer.
Claim 7
Dependent Claim 29 words
The method as claimed in claim 2 further comprising the step of pressing said sheet material against the bottom of the trench after applying the same on the ground.
Claim 8
Dependent Claim 25 words
The method as claimed in claim 2 further comprising the step of securing at least portions of one of the sheet edges in the ground.
Claim 9
Independent Claim 138 words
A device for forming a subterranean fluid permeation control layer in an area of ground for controlling fluid passage therethrough, comprising: a chassis having a front and a rear end; earth digging means mounted on said chassis and associated with means for removing the dug-out earth from the ground to form a trench; powered conveying means mounted on said chassis for conveying said dug-out earth to a location laterally displaced from said earth digging means; and an applicator mounted on said chassis and arranged to apply a fluid permeation control layer substantially along the bottom surface of an initially formed or widened trench, laterally displaced from said earth digging means; said conveying means being constructed and arranged such that the dug-out earth from an adjacent trench covers only a part of said layer leaving an edge thereof uncovered.
Claim 10
Independent Claim 138 words
A device for forming a subterranean fluid permeation control layer in an area of ground for controlling fluid passage therethrough, comprising: a chassis having a front and a rear end; earth digging means mounted on said chassis and associated with means for removing the dug-out earth from the ground to form a trench; powered conveying means mounted on said chassis for conveying said dug-out earth to a location laterally displaced from said earth digging means; and an applicator mounted on said chassis and arranged to apply a fluid permeation control layer substantially along the bottom surface of an initially formed or widened trench, laterally displaced from said earth digging means; said conveying means being constructed and arranged such that the dug-out earth from an adjacent trench covers only a part of said layer leaving an edge thereof uncovered.
Claim 11
Dependent Claim 12 words
The device as claimed in claim 8 further comprising driving means therefor.
Claim 12
Dependent Claim 19 words
The device as claimed in claim 8 wherein said earth digging means includes a plough share and a scraper.
Claim 13
Dependent Claim 28 words
The device as claimed in claim 8 wherein said earth digging means includes at least one earth cutter angularly oriented with respect to the axis of said chassis.
Claim 14
Independent Claim 155 words
A device for forming a subterranean fluid permeation control layer in a area of ground for controlling fluid passage therethrough, comprising: a chassis having a front and a rear end; earth digging means mounted on said chassis and associated with means for removing the dug-out earth from the ground to form a trench; conveying means mounted on said chassis for conveying said dug-out earth to a location laterally displaced from said earth digging means; and an applicator mounted on said chassis and arranged to apply a fluid permeation control layer substantially along the bottom surface of an initially formed or widened trench, laterally displaced from said earth digging means; said conveying means being constructed and arranged such that the dug-out earth from an adjacent trench covers only a part of said layer leaving an edge thereof uncovered; and wherein said means for conveying said dug-out earth is an endless belt conveyor mounted across said chassis.
Claim 15
Independent Claim 155 words
A device for forming a subterranean fluid permeation control layer in a area of ground for controlling fluid passage therethrough, comprising: a chassis having a front and a rear end; earth digging means mounted on said chassis and associated with means for removing the dug-out earth from the ground to form a trench; conveying means mounted on said chassis for conveying said dug-out earth to a location laterally displaced from said earth digging means; and an applicator mounted on said chassis and arranged to apply a fluid permeation control layer substantially along the bottom surface of an initially formed or widened trench, laterally displaced from said earth digging means; said conveying means being constructed and arranged such that the dug-out earth from an adjacent trench covers only a part of said layer leaving an edge thereof uncovered; and wherein said means for conveying said dug-out earth is an endless belt conveyor mounted across said chassis.
Claim 16
Dependent Claim 29 words
The device as claimed in claim 12 wherein the lateral extension of the output end of said conveyor with respect to the major axis of the excavator, is adjustable.
Claim 17
Dependent Claim 37 words
The device as claimed in claim 8 wherein said applicator is a sheet strip applicator including a support for a supply roll and a framework for guiding and spreading said strip along the bottom of the trench.
Claim 18
Dependent Claim 20 words
The device as claimed in claim 14 further comprising means for effecting the joining of overlapping edges of said strips.
Claim 19
Dependent Claim 26 words
The device as claimed in claim 15 further comprising means for securing at least portions of one of the sheet strip longitudinal edges in the ground.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1992-06-12 1992-12-12 1993-06-13 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1996-06-12 1996-12-12 1997-06-13 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2000-06-12 2000-12-12 2001-06-13 $7700.00 Window Closed / Lapsed