Abstract A method of laying generally horizontal wellpoint/drainage tubing, comprising excavating a trench by mechanically digging out spoil which is then directed away from said trench, laying wellpoint/drainage tubing at the bottom of said trench, and backfilling the trench wholly or partially with water-pervious material other than said spoil, so as to promote a flow of ground water to the tubing. A mobile machine for digging and backfilling trenches comprises digging means for excavating spoil to form a trench along a predetermined route at a predetermined depth, directing means arranged to direct the spoil excavated by said digging means away from the trench, and backfilling means associated with the digging means for backfilling the trench with material different from the spoil.

Inventors

  • 👤 Ernest William Potter
  • 👤 William Ratcliffe
  • 👤 Ronald Noel Allen

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-03 20:07
CPC Classifications
E; E02; E02F; E02F5/00; E02F5/02; E02F5/06; E02F5/12

Claims Analysis

Total Claims: 3
Claim 1
Independent Claim 499 words
A method of laying generally horizontal wellpoint/drainage tubing for use in the dewatering of ground, comprising progressively excavating a slot-like trench having a width which is small in comparison with the depth of said trench by advancing a digging mechanism along a predetermined route to mechanically dig out spoil, said digging mechanism including a substantially vertically oriented endless chain having a series of cutters thereon, said endless chain and its cutters being driven along a closed path while said digging mechanism is advanced along said predetermined route thereby to bring said spoil to the top of said trench, said closed path having a length aloNg said trench which is substantially smaller than the depth of said trench, supporting the sides of said trench as said excavating step proceeds by positioning a pair of vertically oriented horizontally spaced plates adjacent the sides of said trench and by advancing said plates along said trench together with said digging mechanism, directing the spoil brought to the top of said trench in a lateral direction away from and to one side of the trench being dug to prevent at least the majority of the spoil removed from the trench from being returned to the trench, laying a continuous length of flexible, perforated tubing along the bottom of the trench by advancing a coil of said tubing along said predetermined route together with said digging mechanism and supporting plates and by progressively feeding said continuous length off said coil and through a substantially vertically oriented guide structure which is located between said supporting plates at a position rearward of said digging mechanism, said guide structure extending into said trench to a position adjacent to but spaced from the bottom of said trench and said guide structure being advanced along said trench together with said supporting plates to direct said tubing in a substantially vertical direction toward the bottom of said trench whereafter, at a location between said supporting plates and adjacent the bottom of said trench, the tubing bends to lie along the bottom of said trench, thereafter immediately and substantially completely backfilling the region of the trench between said supporting plates with a water-pervious material different from the spoil, said backfilling step being effected concurrent with the laying of said tubing by advancing a hopper containing said water-pervious material along said predetermined route together with said digging mechanism, supporting plates, coil of tubing, and guide structure and by discharging said water-pervious material from said hopper, into said trench and over and around the length of tubing emerging from said guide structure, through a discharge chute which extends from the hopper into the trench at a location between said supporting plates and rearward of said guide structure, and connecting the flexible tubing to suction pumping means, said digging mechanism, supporting plates, coil of tubing, guide structure, hopper, and discharge chute all being mounted in fixed position relative to one another on a common structure which is advanced as a unit along said predetermined route.
Claim 2
Independent Claim 499 words
A method of laying generally horizontal wellpoint/drainage tubing for use in the dewatering of ground, comprising progressively excavating a slot-like trench having a width which is small in comparison with the depth of said trench by advancing a digging mechanism along a predetermined route to mechanically dig out spoil, said digging mechanism including a substantially vertically oriented endless chain having a series of cutters thereon, said endless chain and its cutters being driven along a closed path while said digging mechanism is advanced along said predetermined route thereby to bring said spoil to the top of said trench, said closed path having a length aloNg said trench which is substantially smaller than the depth of said trench, supporting the sides of said trench as said excavating step proceeds by positioning a pair of vertically oriented horizontally spaced plates adjacent the sides of said trench and by advancing said plates along said trench together with said digging mechanism, directing the spoil brought to the top of said trench in a lateral direction away from and to one side of the trench being dug to prevent at least the majority of the spoil removed from the trench from being returned to the trench, laying a continuous length of flexible, perforated tubing along the bottom of the trench by advancing a coil of said tubing along said predetermined route together with said digging mechanism and supporting plates and by progressively feeding said continuous length off said coil and through a substantially vertically oriented guide structure which is located between said supporting plates at a position rearward of said digging mechanism, said guide structure extending into said trench to a position adjacent to but spaced from the bottom of said trench and said guide structure being advanced along said trench together with said supporting plates to direct said tubing in a substantially vertical direction toward the bottom of said trench whereafter, at a location between said supporting plates and adjacent the bottom of said trench, the tubing bends to lie along the bottom of said trench, thereafter immediately and substantially completely backfilling the region of the trench between said supporting plates with a water-pervious material different from the spoil, said backfilling step being effected concurrent with the laying of said tubing by advancing a hopper containing said water-pervious material along said predetermined route together with said digging mechanism, supporting plates, coil of tubing, and guide structure and by discharging said water-pervious material from said hopper, into said trench and over and around the length of tubing emerging from said guide structure, through a discharge chute which extends from the hopper into the trench at a location between said supporting plates and rearward of said guide structure, and connecting the flexible tubing to suction pumping means, said digging mechanism, supporting plates, coil of tubing, guide structure, hopper, and discharge chute all being mounted in fixed position relative to one another on a common structure which is advanced as a unit along said predetermined route.
Claim 3
Dependent Claim 23 words
The method of claim 1, wherein the water-pervious material is selected from the group comprising gravel, aggregate and other materials with similar properties.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1978-03-31 1978-09-30 1979-04-01 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1982-03-31 1982-09-30 1983-04-01 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1986-03-31 1986-09-30 1987-04-01 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag