Process for fabricating nuclear reactor fuel assemblies for light water nuclear reactors
Assignee: Areva NP SAS
•
Filing: 1982-12-07
•
Granted: 1985-12-17
•
Expires: 2002-12-07
Abstract
Abstract A tool for the manufacture of a fuel assembly, said tool comprising for each end of an assembly an inner metal plate which can be applied to the bottom of an end member, an outer metal plate which can be displaced, under the action of a jack, along sliding columns fixed to the inner plate, in longitudinal translation with respect thereto and threaded ties traversing corresponding openings in the end member and in the inner and outer plates, able to engage with the internal thread of the guide tubes, and each provided with a head on which is supported a spring for compensating the action of the jack. A method for utilizing the tool is set forth, also.
Inventors
- 👤 Jacques Le Pargneux
- 👤 Michel Bonnamour
- 👤 Gerard Filary
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-10-29 17:50
CPC Classifications
B; B25; B25B; B25B27/00; B25B27/02; B25B27/026; G; G21; G21C; G21C3/00; G21C3/30; G21C3/32; G21C3/334; Y; Y02; Y02E; Y02E30/00; Y02E30/30; Y10; Y10S; Y10S29/00; Y10S29/048; Y10T; Y10T29/00; Y10T29/49; Y10T29/49826; Y10T29/49863; Y10T29/49874; Y10T29/49895; Y10T29/53; Y10T29/531; Y10T29/53978
Claims Analysis
Total Claims: 3
Claim 1
Independent Claim
91 words
A process for the production of a fuel assembly of a light water nuclear reactor, said fuel assembly having a pair of end pieces, said process comprising the steps of first provisionally fixing guide tubes on the end pieces; placing the guide tubes under longitudinal tension without torsion; rigidly fixing grids on said guide tubes; relaxing the longitudinal tension on the guide tubes; disconnecting at least one of the end pieces from the guide tubes; introducing fuel rods into the grids; and then screwing the guide tubes on the end pieces.
Claim 2
Dependent Claim
91 words
A process for the production of a fuel assembly of a light water nuclear reactor, said fuel assembly having a pair of end pieces, said process comprising the steps of first provisionally fixing guide tubes on the end pieces; placing the guide tubes under longitudinal tension without torsion; rigidly fixing grids on said guide tubes; relaxing the longitudinal tension on the guide tubes; disconnecting at least one of the end pieces from the guide tubes; introducing fuel rods into the grids; and then screwing the guide tubes on the end pieces.
Claim 3
Dependent Claim
40 words
The process according to claim 1, further including torsion free screwing the guide tubes between the two end pieces, and thereafter placing the guide tubes under longitudinal tension from at least one of the two ends of the guide tubes.
References Cited (Backward Citations)
US3352003A
Cited
GB1101142A
Cited
US3590247A
Cited
US3791466A
Cited
US3577885A
Cited
US3647184A
Cited
US3844023A
Cited
FR2171279A1
Cited
US4030975A
Cited
US4124443A
Cited
US4172117A
Cited
US3971575A
Cited
US4208248A
Cited
US4376092A
Cited
US4326921A
Cited
US4416848A
Cited
US4405114A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1988-12-16 | 1989-06-17 | 1989-12-17 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1992-12-16 | 1993-06-17 | 1993-12-17 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1996-12-16 | 1997-06-17 | 1997-12-17 | $7700.00 | Window Closed / Lapsed |