US4291537A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Thermal energy storage for covering peak loads
Assignee: BBC BROWN BOVERI and Co Ltd
•
Filing: 1979-05-03
•
Granted: 1981-09-29
•
Expires: 1999-05-03
Abstract
Abstract To cover peak loads an auxiliary circuit having a water store which can be charged from the main circuit is connected to the main circuit of a thermal power station. The stored energy carrier is expanded by throttling, whereupon the vaporous part performs work in a peak-load turbine or in part of the main turbine, which is designed for this purpose, while the unvaporized part is returned to the main circuit in such a way that the low-pressure bleed points of the main turbine are relieved and the output of the main turbine is thus increased. The water store is preferably fed with condensate from the reheater.
Inventors
- 👤 George Oplatka
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-10-30 09:45
CPC Classifications
F; F01; F01K; F01K3/00; F01K3/18; F01K3/26; F01K3/262; F01K3/265; F01K3/004; F01K3/02; F01K3/04; F01K7/00; F01K7/34; F01K7/40
Claims Analysis
Total Claims: 8
Claim 1
Independent Claim
154 words
A method of evening load fluctuations in an electrical supply network, comprising the steps of: connecting a thermal store to a main circuit of a thermal power station; supplying condensate from a reheater of the main circuit to the thermal store; throttling the working medium of the thermal store to vaporize a portion of the working medium; supplying the vaporized portion of the working medium from the thermal store to a turbine; returning a portion of the throttled working medium in liquid form directly to a feedwater tank of the main circuit; expanding the vaporized portion of the working medium and the steam of the main circuit; precipitating the expanded steam in a condensor and supplying it to a condensate vessel; and interrupting a flow of working medium from the condensate vessel to a low-pressure feed-heater during the supply of the vaporized portion of the working medium from the thermal store to the turbine.
Claim 2
Independent Claim
154 words
A method of evening load fluctuations in an electrical supply network, comprising the steps of: connecting a thermal store to a main circuit of a thermal power station; supplying condensate from a reheater of the main circuit to the thermal store; throttling the working medium of the thermal store to vaporize a portion of the working medium; supplying the vaporized portion of the working medium from the thermal store to a turbine; returning a portion of the throttled working medium in liquid form directly to a feedwater tank of the main circuit; expanding the vaporized portion of the working medium and the steam of the main circuit; precipitating the expanded steam in a condensor and supplying it to a condensate vessel; and interrupting a flow of working medium from the condensate vessel to a low-pressure feed-heater during the supply of the vaporized portion of the working medium from the thermal store to the turbine.
Claim 3
Dependent Claim
40 words
The method of claim 1 wherein the vaporized portion of the throttled working medium is supplied to a low pressure turbine of the main circuit of the thermal power station where it expands together with fluid of the main circuit.
Claim 4
Dependent Claim
45 words
The method of claim 1 wherein the vaporized portion of the throttled working medium expands in a peak-load turbine separate from the main circuit, is precipitated in a separate condenser and is joined to the condensate of the main circuit in the common condensate vessel.
Claim 5
Dependent Claim
123 words
Apparatus for evening load fluctuations in an electrical supply network, comprising: storage means for storing as working medium a condensate of a reheater of a main circuit of a thermal power station; expansion means for throttling the working medium of the storage means; first means for supplying liquid from the expansion means to a feedwater tank of the main circuit of the thermal power plant; second means for supplying vapor from the expansion means to a turbine; cold condensate storage means for supplying fluid to a low-pressure feed-heater of the main circuit and for receiving condensate from the turbine; and means for selectively interrupting a flow of working medium from the cold condensate storage means of the main circuit to a low-pressure feed-heater.
Claim 6
Dependent Claim
123 words
Apparatus for evening load fluctuations in an electrical supply network, comprising: storage means for storing as working medium a condensate of a reheater of a main circuit of a thermal power station; expansion means for throttling the working medium of the storage means; first means for supplying liquid from the expansion means to a feedwater tank of the main circuit of the thermal power plant; second means for supplying vapor from the expansion means to a turbine; cold condensate storage means for supplying fluid to a low-pressure feed-heater of the main circuit and for receiving condensate from the turbine; and means for selectively interrupting a flow of working medium from the cold condensate storage means of the main circuit to a low-pressure feed-heater.
Claim 7
Dependent Claim
17 words
The apparatus of claim 4 wherein the turbine is a peak-load turbine separate from the main circuit.
Claim 8
Dependent Claim
16 words
The apparatus of claim 4 wherein the turbine is a low-pressure turbine of the main circuit.
References Cited (Backward Citations)
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1984-09-28 | 1985-03-30 | 1985-09-29 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1988-09-28 | 1989-03-30 | 1989-09-29 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1992-09-28 | 1993-03-30 | 1993-09-29 | $7700.00 | Window Closed / Lapsed |