Patent US3948497A successfully refreshed from Google Patents.
Patent US4150910A successfully refreshed from Google Patents.
US4150910A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Construction of underground galleries
Assignee: PROMON ENGENHARIA SA
•
Filing: 1977-09-23
•
Granted: 1979-04-24
•
Expires: 1997-09-23
Abstract
Abstract A method of constructing a gallery in which a trench is excavated and the gallery is either constructed in or lowered into the excavation. The gallery is braced internally to withstand external loads applied. Thereafter a controlled backfill is applied around and over the gallery in such manner that with removal of the bracing the backfill acts effectively to form an arch above the gallery which together with the gallery is sufficient to support the overlying covering material up to the ground surface.
Inventors
- 👤 Carlos E. M. Maffei
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-08 17:15
CPC Classifications
E; E02; E02D; E02D29/00; E02D29/045; E02D29/05
Claims Analysis
Total Claims: 27
Claim 1
Independent Claim
115 words
A method of constructing an underground gallery comprising excavating to form a pit having a depth greater than the overall height of the gallery, locating the gallery within the pit, internally bracing the structure of said gallery to withstand loads exerted by ground material upon refilling of the pit, covering the gallery and filling the pit with ground material, said covering being effected initially by applying and compacting backfill material in incremental steps around and over the gallery, removing said bracing from within the gallery and thereby causing said initially applied backfill material to adopt an internal arching structure which together with said gallery will support applied loads, and completing the filling of the pit.
Claim 2
Independent Claim
115 words
A method of constructing an underground gallery comprising excavating to form a pit having a depth greater than the overall height of the gallery, locating the gallery within the pit, internally bracing the structure of said gallery to withstand loads exerted by ground material upon refilling of the pit, covering the gallery and filling the pit with ground material, said covering being effected initially by applying and compacting backfill material in incremental steps around and over the gallery, removing said bracing from within the gallery and thereby causing said initially applied backfill material to adopt an internal arching structure which together with said gallery will support applied loads, and completing the filling of the pit.
Claim 3
Dependent Claim
14 words
A method according to claim 1, wherein the initially applied backfill is applied layer-by-layer.
Claim 4
Dependent Claim
26 words
A method according to claim 1, wherein the initially applied backfill and subsequently applied final backfill are the same material and are of the same consistency.
Claim 5
Dependent Claim
20 words
A method according to claim 1, wherein the initially applied backfill and subsequently applied final backfill have a different composition.
Claim 6
Dependent Claim
22 words
A method according to claim 4, wherein the initial backfill comprises a mixture of the material of the backfill and stabilizing material.
Claim 7
Dependent Claim
69 words
A method according to claim 5, wherein the ground material is a coarse-grained soil, having a grain size of which more than 50% will not pass through a standard No. 200 sieve and wherein the initially applied backfill comprises such ground material mixed with from 3% to 9% by weight of portland cement to provide a mixture with a controlled water content of from 7% to 12% by weight.
Claim 8
Dependent Claim
68 words
A method according to claim 5, wherein the ground material is a fine-grained soil having a grain size of which more than 50% will pass through a standard No. 200 sieve and wherein the initially applied backfill comprises such ground material mixed with from 5% to 14% by weight of portland cement to provide a mixture with a controlled water content of from 10% to 14% by weight.
Claim 9
Dependent Claim
17 words
A method according to claim 1, wherein the gallery is positioned on a cradle within the pit.
Claim 10
Dependent Claim
33 words
A method according to claim 7 wherein the gallery is a composite structure comprising a plurality of prefabricated sections which are lowered into the pit and assembed therein to form said composite structure.
Claim 11
Dependent Claim
14 words
A method according to claim 1, wherein the gallery is constructed in the pit.
Claim 12
Dependent Claim
20 words
A method according to claim 1, wherein the internal braces are arranged inside the gallery structure in a grid formation.
Claim 13
Dependent Claim
42 words
A method according to claim 1, wherein the gallery is of substantially circular configuration and wherein each brace comprises four quadrant sectors assembled within said gallery to mate with the internal surface of the gallery shell substantially around the entire periphery thereof.
Claim 14
Dependent Claim
22 words
A method according to claim 1, wherein the braces are applied inside the gallery before the gallery is lowered into the pit.
Claim 15
Dependent Claim
36 words
A method according to claim 1, wherein the braces are applied inside the gallery after said gallery has been positioned within the pit and before initially applied backfill can exert any substantial load on said gallery.
Claim 16
Dependent Claim
18 words
A method according to claim 1, wherein the braces are removed when the pit has been completely filled.
Claim 17
Dependent Claim
12 words
A method according to claim 1, wherein the pit is a trench.
Claim 18
Dependent Claim
12 words
A method according to claim 18, wherein the gallery is a tunnel.
Claim 19
Independent Claim
141 words
A method of constructing an underground gallery comprising the steps of excavating a trench having a depth greater than the overall height of the gallery, laying the gallery along the trench bottom, inserting braces inside the gallery to brace the peripheral shell thereof against external pressure, beginning to fill the trench with ground material to embed the gallery, said filling comprising the steps of initially applying and compacting backfill material layer-by-layer in incremental steps to cover the gallery to a depth at which upon removal of the bracing from within the gallery the initially applied backfill will adopt an internal structure which together with said gallery will support applied loads, removing said bracing from within the gallery to permit some shifting of the initially applied backfill to adopt an internal load supporting arching structure and completing the filling of the trench.
Claim 20
Independent Claim
141 words
A method of constructing an underground gallery comprising the steps of excavating a trench having a depth greater than the overall height of the gallery, laying the gallery along the trench bottom, inserting braces inside the gallery to brace the peripheral shell thereof against external pressure, beginning to fill the trench with ground material to embed the gallery, said filling comprising the steps of initially applying and compacting backfill material layer-by-layer in incremental steps to cover the gallery to a depth at which upon removal of the bracing from within the gallery the initially applied backfill will adopt an internal structure which together with said gallery will support applied loads, removing said bracing from within the gallery to permit some shifting of the initially applied backfill to adopt an internal load supporting arching structure and completing the filling of the trench.
Claim 21
Dependent Claim
30 words
A method according to claim 18, wherein the gallery comprises a plurality of prefabricated segments sequentially lowered into the trench and then joined end-to-end to lie along the trench bottom.
Claim 22
Dependent Claim
26 words
A method according to claim 18, wherein the initially applied backfill and subsequently applied final backfill are the same material and are of the same consistency.
Claim 23
Dependent Claim
20 words
A method according to claim 18, wherein the initially applied backfill and subsequently applied final backfill have a different composition.
Claim 24
Dependent Claim
22 words
A method according to claim 21, wherein the initial backfill comprises a mixture of the material of the backfill and stabilizing material.
Claim 25
Dependent Claim
69 words
A method according to claim 22, wherein the ground material is a coarse-grained soil having a grain size of which more than 50% will not pass through a standard No. 200 sieve and wherein the initially applied backfill comprises such ground material mixed with from 3% to 9% by weight of portland cement to provide a mixture with a controlled water content of from 7% to 12% by weight.
Claim 26
Independent Claim
204 words
A method of constructing a tunnel comprising the steps of excavating a trench, locating supporting cradles along the bottom of said trench, sequentially lowering a plurality of prefabricated annular tunnel sections into said trench and aligning said sections on said cradles in end-to-end relationship, joining said aligned sections to form an elongated annular tunnel shell, positioning braces within the shell to reinforce said shell to resist the load exerted by ground material when the trench is filled, applying initial backfilling material layer-by-layer and compacting each applied layer before proceeding with the next subsequent layer, said initially applied backfill comprising a mixture of the excavated ground material and portland cement in a proportion of from 3% to 9% by weight, said mixture having a moisture content of from 7% to 12% by weight, continuing incrementally to apply said initial backfill around, over and above the tunnel shell up to a depth at which said mixture will adopt an arching effect upon removal of the braces, completing filling of the trench to the ground surface with final backfilling material comprising the excavated ground material without any additions and compacting the final backfill material during application thereof and finally removing said braces from within the embedded tunnel.
Claim 27
Independent Claim
204 words
A method of constructing a tunnel comprising the steps of excavating a trench, locating supporting cradles along the bottom of said trench, sequentially lowering a plurality of prefabricated annular tunnel sections into said trench and aligning said sections on said cradles in end-to-end relationship, joining said aligned sections to form an elongated annular tunnel shell, positioning braces within the shell to reinforce said shell to resist the load exerted by ground material when the trench is filled, applying initial backfilling material layer-by-layer and compacting each applied layer before proceeding with the next subsequent layer, said initially applied backfill comprising a mixture of the excavated ground material and portland cement in a proportion of from 3% to 9% by weight, said mixture having a moisture content of from 7% to 12% by weight, continuing incrementally to apply said initial backfill around, over and above the tunnel shell up to a depth at which said mixture will adopt an arching effect upon removal of the braces, completing filling of the trench to the ground surface with final backfilling material comprising the excavated ground material without any additions and compacting the final backfill material during application thereof and finally removing said braces from within the embedded tunnel.
References Cited (Backward Citations)
US986068A
Cited
US1644476A
Cited
US1722038A
Cited
DE1143155B
Cited
US3508406A
Cited
US3774683A
Cited
GB1434096A
Cited
US3891186A
Cited
US4050255A
Cited
US4068488A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1982-04-23 | 1982-10-23 | 1983-04-24 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1986-04-23 | 1986-10-23 | 1987-04-24 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1990-04-23 | 1990-10-23 | 1991-04-24 | $7700.00 | Window Closed / Lapsed |