Method of backfilling pipeline trenches

Assignee: Beloit Corp
•
Filing: 1975-04-30
•
Granted: 1978-01-17
•
Expires: 1995-04-30
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A trench containing a pipeline is backfilled by temporarily supporting the pipeline at grade in the trench on deflatable airbags spaced along the bottom of the trench. The trench is then backfilled below and around the pipe by pneumatically blowing a granular fill material into the trench first beneath the pipe and then progressively upwardly about its opposite sides to about its spring line so as simultaneously to backfill the trench and uniformly compact the fill material about the pipe without leaving any voids. The fill material is blown into the trench through a pair of opposed air ducts with upturned lower outlet ends extending into the trench on opposite sides of the pipe so that backfilling progresses upwardly on opposite sides of the pipe simultaneously. As backfilling operation progresses along the trench and approaches each support pad, the pad is deflated and removed so that the operation can proceed uninterruptedly. After the trench is pneumatically backfilled to the spring line of the pipe in the aforesaid manner, the upper portion of the trench to the soil surface can be backfilled in a conventional manner.

Inventors

  • 👤 D. Graham Ball

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-05 20:41
CPC Classifications
F; F16; F16L; F16L1/00; F16L1/024; F16L1/028

Claims Analysis

Total Claims: 16
Claim 1
Independent Claim 197 words
A method of backfilling a trench containing a pipeline comprising: temporarily supporting said pipeline at a desired final position and grade within said trench spaced from the opposite sides of said trench and spaced above the bottom of the trench on removable support pads spaced at intervals along the bottom of said trench, at a portion of said pipeline unsupported by said support pads blowing under pneumatic pressure a granular fill material into said trench first below and into the space beneath and about said pipeline and then progressively upwardly about and along the opposite sides of said pipeline to fill the trench spaces about the pipeline to at least about the spring line thereof, said fill material being blown at a velocity sufficient to simultaneously backfill said trench and compact said granular fill material to a substantially uniform desired final density about said pipeline to support the same at its final position and grade within said trench, whereby subsequent compaction of said fill material is not required, and continuing the aforesaid pneumatic filling operation progressively in a given direction along said trench and removing said support pads seriatim as the filling operation approaches each said pad.
Claim 2
Independent Claim 197 words
A method of backfilling a trench containing a pipeline comprising: temporarily supporting said pipeline at a desired final position and grade within said trench spaced from the opposite sides of said trench and spaced above the bottom of the trench on removable support pads spaced at intervals along the bottom of said trench, at a portion of said pipeline unsupported by said support pads blowing under pneumatic pressure a granular fill material into said trench first below and into the space beneath and about said pipeline and then progressively upwardly about and along the opposite sides of said pipeline to fill the trench spaces about the pipeline to at least about the spring line thereof, said fill material being blown at a velocity sufficient to simultaneously backfill said trench and compact said granular fill material to a substantially uniform desired final density about said pipeline to support the same at its final position and grade within said trench, whereby subsequent compaction of said fill material is not required, and continuing the aforesaid pneumatic filling operation progressively in a given direction along said trench and removing said support pads seriatim as the filling operation approaches each said pad.
Claim 3
Independent Claim 158 words
The method of backfilling a trench containing a pipeline supported at final position and grade at intervals therealong spaced above the bottom of said trench and spaced from the opposite sides thereof, said method comprising blowing a granular fill material into said trench under pneumatic pressure first along the bottom of said trench and beneath said pipeline to fill the space between said pipeline and the bottom of said trench and then progressively upwardly along the opposite sides of said pipeline to fill the spaces between the pipeline and opposite sides of said trench, said fill material being blown at a velocity sufficient to simultaneously backfill said trench and compact said fill material about said pipeline to a substantially uniform final desired density to support said pipeline at its final position and grade and to substantially eliminate air pockets between said pipeline and said fill material, and to eliminate the need for subsequent compaction of said fill material.
Claim 4
Independent Claim 158 words
The method of backfilling a trench containing a pipeline supported at final position and grade at intervals therealong spaced above the bottom of said trench and spaced from the opposite sides thereof, said method comprising blowing a granular fill material into said trench under pneumatic pressure first along the bottom of said trench and beneath said pipeline to fill the space between said pipeline and the bottom of said trench and then progressively upwardly along the opposite sides of said pipeline to fill the spaces between the pipeline and opposite sides of said trench, said fill material being blown at a velocity sufficient to simultaneously backfill said trench and compact said fill material about said pipeline to a substantially uniform final desired density to support said pipeline at its final position and grade and to substantially eliminate air pockets between said pipeline and said fill material, and to eliminate the need for subsequent compaction of said fill material.
Claim 5
Dependent Claim 42 words
The method of claim 2 including using deflatable gas-filled support pads for temporary support of said pipeline at grade within said trench and deflating each said pad to facilitate its removal from beneath said pipeline as said filling operation approaches said pad.
Claim 6
Dependent Claim 39 words
The method of claim 2 including pneumatically filling said trench with a granular fill material that is of substantially uniform size composition from the bottom of said trench upwardly to at least about the spring line of said pipe.
Claim 7
Dependent Claim 23 words
The method of claim 2 wherein said granular fill material blown into said trench under pneumatic pressure is three-quarter inch minus mineral aggregate.
Claim 8
Dependent Claim 63 words
The method of claim 2 including pneumatically blowing said granular fill material into said trench from below and along the opposite sides of pipeline through a vertically and longitudinally movable air duct extending into said trench and having an upturned lower outlet end rotatable about a generally upright axis for directing said granular material beneath said pipeline along the bottom of said trench.
Claim 9
Dependent Claim 24 words
The method of claim 2 wherein said material is blow into said trench and below and along pipeline in a generally horizontal air stream.
Claim 10
Dependent Claim 22 words
The method of claim 2 wherein said material is blown into said trench at velocities of at least 88 feet per second.
Claim 11
Independent Claim 161 words
The method of backfilling a trench containing a pipeline comprising: temporarily supporting said pipeline at a desired final position and grade within said trench on removable support pads placed at intervals along the bottom of said trench, at a portion of said pipeline unsupported by said support pads, blowing under pneumatic pressure granular fill material into said trench first beneath said pipeline and then progressively upwardly along the opposite sides of said pipeline to at least about the spring line thereof to simultaneously backfill said trench and compact said granular fill material along said pipeline, blowing said granular fill material into said trench below and about said pipeline simultaneously from opposite sides of said pipeline so that said filling operation progresses simultaneously from below said pipeline upwardly along the opposite sides thereof, and continuing the aforesaid pneumatic filling operation progressively in a given direction along said trench and removing said support pads seriatim as the filling operation approaches each said pad.
Claim 12
Independent Claim 161 words
The method of backfilling a trench containing a pipeline comprising: temporarily supporting said pipeline at a desired final position and grade within said trench on removable support pads placed at intervals along the bottom of said trench, at a portion of said pipeline unsupported by said support pads, blowing under pneumatic pressure granular fill material into said trench first beneath said pipeline and then progressively upwardly along the opposite sides of said pipeline to at least about the spring line thereof to simultaneously backfill said trench and compact said granular fill material along said pipeline, blowing said granular fill material into said trench below and about said pipeline simultaneously from opposite sides of said pipeline so that said filling operation progresses simultaneously from below said pipeline upwardly along the opposite sides thereof, and continuing the aforesaid pneumatic filling operation progressively in a given direction along said trench and removing said support pads seriatim as the filling operation approaches each said pad.
Claim 13
Independent Claim 216 words
The method of backfilling a pipeline trench comprising the steps: supporting a pipeline at a desired final position and grade within said trench at spaced intervals along said pipeline so as to create a substantial air space between said pipeline and the bottom of said trench except at such intervals and air spaces between the opposite sides of said pipeline and opposite sides of said trench, blowing a granular fill material into said trench under pneumatic pressure first along the bottom of said trench below said pipeline and into the space between said pipeline and the bottom of said trench and then progressively upwardly along the opposite sides of said pipeline and trench to fill the spaces between said opposite sides of said pipeline and opposite sides of said trench and simultaneously compact said fill material to a substantially uniform desired final density about the bottom and opposite sides of said pipeline to thereby substantially eliminate air pockets within said fill material and between said fill material and said pipeline, and eliminate the need for subsequent compaction of such fill material, and blowing said fill material in the aforesaid manner simultaneously from opposite sides of said pipeline so that said filling operation progresses simultaneously from beneath and below said pipeline upwardly along the opposite sides thereof.
Claim 14
Independent Claim 216 words
The method of backfilling a pipeline trench comprising the steps: supporting a pipeline at a desired final position and grade within said trench at spaced intervals along said pipeline so as to create a substantial air space between said pipeline and the bottom of said trench except at such intervals and air spaces between the opposite sides of said pipeline and opposite sides of said trench, blowing a granular fill material into said trench under pneumatic pressure first along the bottom of said trench below said pipeline and into the space between said pipeline and the bottom of said trench and then progressively upwardly along the opposite sides of said pipeline and trench to fill the spaces between said opposite sides of said pipeline and opposite sides of said trench and simultaneously compact said fill material to a substantially uniform desired final density about the bottom and opposite sides of said pipeline to thereby substantially eliminate air pockets within said fill material and between said fill material and said pipeline, and eliminate the need for subsequent compaction of such fill material, and blowing said fill material in the aforesaid manner simultaneously from opposite sides of said pipeline so that said filling operation progresses simultaneously from beneath and below said pipeline upwardly along the opposite sides thereof.
Claim 15
Dependent Claim 47 words
The method of claim 10 including backfilling said trench beneath and about said pipeline and compacting said fill material by blowing said granular fill material into said trench simultaneously from opposite sides of said pipeline through a pair of laterally opposed vertically and longitudinally movable air ducts.
Claim 16
Dependent Claim 91 words
The method of claim 10 including pneumatically blowing said granular fill material into said trench progressively from the bottom of said trench below said pipeline progressively upwardly and simultaneously along the opposite sides of said pipeline from the bottom of said trench to at least about the spring line of said pipeline from opposite sides of said pipeline simultaneously under uniform blowing pressures so as to produce a substantially uniform high density compaction of said fill material from the bottom of said trench to approximately the level of said spring line.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1981-01-16 1981-07-18 1982-01-17 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1985-01-16 1985-07-18 1986-01-17 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1989-01-16 1989-07-18 1990-01-17 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag