Abstract

Abstract A low sulfur coke product is obtained in an integrated fluid coking and gasification process in which an oxygen-containing gas is introduced into the upper portion of the gasification zone and steam is introduced into the lower portion of the gasification zone. The desired degree of coke desulfurization is controlled by controlling the thickness of the gasifier coke layer on the gaseous reactor leaving solids per pass.

Inventors

  • 👤 William J. Metrailer
  • 👤 Walter Weissman

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-02 11:22
CPC Classifications
C; C10; C10B; C10B55/00; C10B55/02; C10B55/04; C10B55/08; C10B55/10

Claims Analysis

Total Claims: 9
Claim 1
Independent Claim 281 words
In an integrated coking and gasification process for the production of a low sulfur coke comprising the steps of: reacting a carbonaceous material containing sulfur contaminants, said carbonaceous material having a Conradson carbon content of at least 5 weight percent in a coking zone containing a bed of fluidized solids maintained at a temperature ranging from about 850° to about 1250° F. to form coke containing sulfur contaminants, said coke depositing on said fluidized solids; introducing a portion of said solids with the coke deposition thereon into a heating zone operated at a temperature greater than said coking zone temperature to heat said portion of solids; recycling a first portion of heated solids from said heating zone to said coking zone and introducing a second portion of said heated solids to a fluid bed gasification zone maintained at a temperature of at least 1600° F., and passing a stream of solids from said gasification zone to said heating zone, the improvement which comprises: controlling the rate of circulation of said solids between each of said zones such as to maintain the thickness of a shell of deposited coke, subjected to treatment within the gasification zone in a single cycle, ranging at the time of exit from the gasification zone to a thickness not greater than 10 microns, while introducing steam into the lower portion of said fluidized bed gasification zone to produce a hydrogen-containing gas and introducing an oxygen-containing gas into the upper portion of said fluid bed gasification zone to convert at least a portion of said hydrogen to steam and thereby produce at least a portion of the heat requirements of said process and recovering a partially desulfurized coke.
Claim 2
Dependent Claim 281 words
In an integrated coking and gasification process for the production of a low sulfur coke comprising the steps of: reacting a carbonaceous material containing sulfur contaminants, said carbonaceous material having a Conradson carbon content of at least 5 weight percent in a coking zone containing a bed of fluidized solids maintained at a temperature ranging from about 850° to about 1250° F. to form coke containing sulfur contaminants, said coke depositing on said fluidized solids; introducing a portion of said solids with the coke deposition thereon into a heating zone operated at a temperature greater than said coking zone temperature to heat said portion of solids; recycling a first portion of heated solids from said heating zone to said coking zone and introducing a second portion of said heated solids to a fluid bed gasification zone maintained at a temperature of at least 1600° F., and passing a stream of solids from said gasification zone to said heating zone, the improvement which comprises: controlling the rate of circulation of said solids between each of said zones such as to maintain the thickness of a shell of deposited coke, subjected to treatment within the gasification zone in a single cycle, ranging at the time of exit from the gasification zone to a thickness not greater than 10 microns, while introducing steam into the lower portion of said fluidized bed gasification zone to produce a hydrogen-containing gas and introducing an oxygen-containing gas into the upper portion of said fluid bed gasification zone to convert at least a portion of said hydrogen to steam and thereby produce at least a portion of the heat requirements of said process and recovering a partially desulfurized coke.
Claim 3
Dependent Claim 42 words
The process of claim 1 wherein the coke formed in said coking zone contains up to 10 weight percent sulfur and wherein said partially desulfurized coke contains about 60 to 85 percent less sulfur than the coke formed in said coking zone.
Claim 4
Dependent Claim 18 words
The process of claim 1 wherein the partially desulfurized coke contains up to about 4 weight percent sulfur.
Claim 5
Dependent Claim 42 words
The process of claim 1 wherein at least 15 percent of said oxygen-containing gas is introduced into said upper portion of said gasification zone and the remaining portion of the oxygen-containing gas is introduced into the lower portion of said gasification zone.
Claim 6
Dependent Claim 24 words
The process of claim 1 wherein the thickness of said coke deposition per pass through the gasification zone is less than about 5 microns.
Claim 7
Dependent Claim 30 words
The process of claim 1 wherein said steam is introduced into said gasification zone at a rate varying from about 0.20 to about 1.00 moles per mole of carbon gasified.
Claim 8
Dependent Claim 21 words
The process of claim 1 wherein the concentration of hydrogen in said gasification zone ranges up to about 40 mol percent.
Claim 9
Dependent Claim 21 words
The process of claim 1 wherein said gasification is maintained at a temperature ranging from about 1700° to about 2000° F.

References Cited (Backward Citations)

US2600430A Cited
GB771743A Cited
US3475323A Cited
US3707462A Cited
US3912465A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1980-02-08 1980-08-09 1981-02-08 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1984-02-08 1984-08-09 1985-02-08 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1988-02-08 1988-08-09 1989-02-08 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag