US3975476A Expired / Lapsed US ⏱️ 0.0 years remaining

Method for building a cable-stayed girder bridge

Assignee: Walter Bau AG
•
Filing: 1975-03-18
•
Granted: 1976-08-17
•
Expires: 1995-03-18
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A cable-stayed girder bridge having a concrete deck girder which includes longitudinally extending stiffening girders having cables embedded therein and a laterally extending deck portion is constructed by sequential formation of said deck girder in successive adjacent sections. The longitudinally extending stiffening girder portions of said deck girder are first formed, support cables are embedded therein and subsequently tensioned. After hardening of the stiffening girders, the laterally extending deck portion of the duck girder is formed. A form carrier movable along the bridge during its construction extends in a cantilevered arrangement from a previously formed deck girder section to provide support for a successive deck girder section during formation thereof.

Inventors

  • 👤 Klemens Finsterwalder

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-26 20:27
CPC Classifications
E; E01; E01D; E01D21/00; E01D11/00; E01D11/04; E01D2101/00; E01D2101/20; E01D2101/24; E01D2101/26; E01D2101/28

Claims Analysis

Total Claims: 2
Claim 1
Independent Claim 215 words
A process for the construction of a deck structure in a cable-stayed girder bridge, by sequential formation in successive adjacent sections of a plurality of concrete deck girders each of which include longitudinally extending stiffening girders and a laterally extending deck portion, said bridge including pylons anchored in the earth to support said concrete deck girders from cables extending between said pylons and said longitudinal stiffening girders, comprising the steps of providing a form carrier adaptable to have concrete poured thereinto to form said deck girders, arranging said form carrier to be cantilevered longitudinally from and below a previously formed deck girder section to provide support for a successive deck girder section during formation thereof, first forming said longitudinal stiffening girders for said successive deck girder section with cables embedded therein, subsequently tensioning said embedded cables between said pylons and said formed longitudinal stiffening girders to provide support therefor, thereafter connecting said form carrier to said formed stiffening girders to thereby provide further support therefor from said previously tensioned cables, thereafter forming said laterally extending deck portion of said successive girder section, subsequently moving said form carrier to be cantilevered longitudinally from said deck girder section thus formed, and thereafter repeating said steps to form said deck structure from said successive adjacent deck girder sections.
Claim 2
Dependent Claim 215 words
A process for the construction of a deck structure in a cable-stayed girder bridge, by sequential formation in successive adjacent sections of a plurality of concrete deck girders each of which include longitudinally extending stiffening girders and a laterally extending deck portion, said bridge including pylons anchored in the earth to support said concrete deck girders from cables extending between said pylons and said longitudinal stiffening girders, comprising the steps of providing a form carrier adaptable to have concrete poured thereinto to form said deck girders, arranging said form carrier to be cantilevered longitudinally from and below a previously formed deck girder section to provide support for a successive deck girder section during formation thereof, first forming said longitudinal stiffening girders for said successive deck girder section with cables embedded therein, subsequently tensioning said embedded cables between said pylons and said formed longitudinal stiffening girders to provide support therefor, thereafter connecting said form carrier to said formed stiffening girders to thereby provide further support therefor from said previously tensioned cables, thereafter forming said laterally extending deck portion of said successive girder section, subsequently moving said form carrier to be cantilevered longitudinally from said deck girder section thus formed, and thereafter repeating said steps to form said deck structure from said successive adjacent deck girder sections.

References Cited (Backward Citations)

US746679A Cited
US965358A Cited
US2059693A Cited
US3003219A Cited
US3425076A Cited
US3259932A Cited
DE1658582B1 Cited
US3571835A Cited
DE2036924A1 Cited
US3845515A Cited
US3832748A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1979-08-17 1980-02-16 1980-08-17 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1983-08-17 1984-02-16 1984-08-17 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1987-08-17 1988-02-16 1988-08-17 $7700.00 Window Closed / Lapsed