US7309188B2
Expired / Lapsed
US
⏱️ 0.0 years remaining
Drainable base course for a landfill and method of forming the same
Assignee: Advanced Geotech Systems LLC
•
Filing: 2004-09-01
•
Granted: 2007-12-18
•
Expires: 2024-09-01
Abstract
Abstract Numerous embodiments of one or more layers of void-maintaining synthetic drainable base courses (“VMSDBC's”) are provided as incorporated into landfills and other waste containment facilities.
Inventors
- 👤 Peter J. Ianniello
- 👤 Aigen Zhao
- 👤 Gary L. Shaffer
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-06 19:26
CPC Classifications
E; E01; E01C; E01C3/00; E01C3/06; E01F; E01F5/00; E02; E02B; E02B11/00; E02D; E02D31/00; E02D31/02; E02D31/10; E02D31/14; E02D2300/00; E02D2300/0085; E02D2450/00; E02D2450/10; E02D2450/108
Claims Analysis
Total Claims: 78
Claim 1
Independent Claim
242 words
A synthetic drainable base course composite element suitable for providing drainage when positioned within a landfill, said base course element comprising a void-maintaining geocomposite, said geocomposite including a) a geocomposite core element having a plurality of ribs constructed and arranged to form a plurality of interconnected voids, said core element having an upper surface and a lower surface, a no-load thickness and a thickness under load, wherein said thicknesses are measured substantially perpendicular to said surfaces, and b) at least one fluid-transmissible layer attached adjacent said upper surface, wherein said layers and said core element are constructed and arranged so that, under a load of at least 1,000 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 19 gallons/minute/foot at a slope gradient of 33% and at least 33 gallons/minute at a slope gradient of 10%, and wherein said geocomposite is constructed and arranged so that said transmissivity is maintained within said landfill when, fill comprising one or more layers, sections or quantities of waste or refuse materials, or waste or materials to be processed at least partially within said landfill, is disposed above said geocomposite, wherein at least a portion of said synthetic drainable base course is sloped downwardly in a gradient from a first portion to a second portion of said landfill.
Claim 2
Dependent Claim
242 words
A synthetic drainable base course composite element suitable for providing drainage when positioned within a landfill, said base course element comprising a void-maintaining geocomposite, said geocomposite including a) a geocomposite core element having a plurality of ribs constructed and arranged to form a plurality of interconnected voids, said core element having an upper surface and a lower surface, a no-load thickness and a thickness under load, wherein said thicknesses are measured substantially perpendicular to said surfaces, and b) at least one fluid-transmissible layer attached adjacent said upper surface, wherein said layers and said core element are constructed and arranged so that, under a load of at least 1,000 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 19 gallons/minute/foot at a slope gradient of 33% and at least 33 gallons/minute at a slope gradient of 10%, and wherein said geocomposite is constructed and arranged so that said transmissivity is maintained within said landfill when, fill comprising one or more layers, sections or quantities of waste or refuse materials, or waste or materials to be processed at least partially within said landfill, is disposed above said geocomposite, wherein at least a portion of said synthetic drainable base course is sloped downwardly in a gradient from a first portion to a second portion of said landfill.
Claim 3
Dependent Claim
251 words
A drainable landfill comprising I. a base layer formed at least partially of one or more of native soil components and non-native soil components, II. a synthetic drainable base course element disposed above said base layer, said drainable base course element comprising A) a void-maintaining geocomposite, said geocomposite including i) a geocomposite core element having a plurality of ribs constructed and arranged to form a plurality of interconnected voids, said core element having an upper surface and a lower surface, a no-load thickness and a thickness under load, wherein said thicknesses are measured substantially perpendicular to said surfaces, and ii) at least one fluid-transmissible layer attached adjacent said upper surface, wherein said layers and said core element are constructed and arranged so that, under a load of at least 500 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 19 gallons/minute/foot at a slope gradient of 33% and at least 33 gallons/minute at a slope gradient of 10%, and III. above said synthetic drainable base course, fill suitable to be drained, said fill comprising one or more layers, sections or quantities of refuse materials, or materials to be processed at least partially within said landfill, wherein at least a portion of said synthetic drainable base course is sloped downwardly in a gradient from a first portion to a second portion of said landfill.
Claim 4
Dependent Claim
251 words
A drainable landfill comprising I. a base layer formed at least partially of one or more of native soil components and non-native soil components, II. a synthetic drainable base course element disposed above said base layer, said drainable base course element comprising A) a void-maintaining geocomposite, said geocomposite including i) a geocomposite core element having a plurality of ribs constructed and arranged to form a plurality of interconnected voids, said core element having an upper surface and a lower surface, a no-load thickness and a thickness under load, wherein said thicknesses are measured substantially perpendicular to said surfaces, and ii) at least one fluid-transmissible layer attached adjacent said upper surface, wherein said layers and said core element are constructed and arranged so that, under a load of at least 500 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 19 gallons/minute/foot at a slope gradient of 33% and at least 33 gallons/minute at a slope gradient of 10%, and III. above said synthetic drainable base course, fill suitable to be drained, said fill comprising one or more layers, sections or quantities of refuse materials, or materials to be processed at least partially within said landfill, wherein at least a portion of said synthetic drainable base course is sloped downwardly in a gradient from a first portion to a second portion of said landfill.
Claim 5
Dependent Claim
83 words
The drainable landfill of claim 2 , wherein said layers and said core element are constructed and arranged so that, under a load of at least 1,000 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 19 gallons/minute/foot at a slope gradient of 33% and at least 33 gallons/minute at a slope gradient of 10%.
Claim 6
Dependent Claim
72 words
The drainable landfill of claim 2 , wherein said layers and said core element are constructed and arranged so that, under a load of at least 15,000 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 8.5 gallons/minute/foot at a slope gradient of 10%.
Claim 7
Dependent Claim
72 words
The drainable landfill of claim 2 , wherein said layers and said core element are constructed and arranged so that, under a load of at least 25,000 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 3.5 gallons/minute/foot at a slope gradient of 10%.
Claim 8
Dependent Claim
20 words
The drainable landfill of claim 2 , wherein said core element comprises ribs constructed and arranged in a bi-planar configuration.
Claim 9
Dependent Claim
20 words
The drainable landfill of claim 2 , wherein said core element comprises ribs constructed and arranged in a tri-planar configuration.
Claim 10
Dependent Claim
20 words
The drainable landfill of claim 2 , wherein said core element comprises ribs constructed and arranged in a uniplanar configuration.
Claim 11
Dependent Claim
50 words
The drainable landfill of claim 2 , wherein said non-native soil components are one or more selected from the group consisting of refuse from highway excavations, refuse from building foundation excavations, mining refuse, manufacturing refuse, geologic refuse, gypsum refuse, quarry refuse, refuse from road-building activities, and refuse from dredging operations.
Claim 12
Dependent Claim
20 words
The drainable landfill of claim 2 , wherein said base layer of said drainable structure comprises at least one slope.
Claim 13
Dependent Claim
21 words
The drainable landfill of claim 2 , wherein said base layer of said drainable landfill comprises a plurality of sloping surfaces.
Claim 14
Dependent Claim
17 words
The drainable landfill of claim 2 , wherein said plurality of surfaces form at least one container.
Claim 15
Dependent Claim
15 words
The drainable landfill of claim 2 , wherein said landfill comprises a plurality of containers.
Claim 16
Dependent Claim
41 words
The drainable landfill of claim 13 , wherein said plurality of containers are constructed and arranged such that at least portions of one container can drain via gravitational means into one or more of other containers of said plurality of containers.
Claim 17
Dependent Claim
27 words
The drainable landfill of claim 2 , wherein said drainage element further comprises iii) at least one frictional layer attached adjacent said lower surface of said geocomposite.
Claim 18
Dependent Claim
26 words
The drainable landfill of claim 2 , wherein said drainage element further comprises iii) at least one cushion layer adjacent said lower surface of said geocomposite.
Claim 19
Dependent Claim
12 words
The drainable landfill of claim 2 , wherein said landfill is layered.
Claim 20
Dependent Claim
80 words
The synthetic drainable base course (SDBC) of claim 2 , wherein said ribs of said core are provided in a first set and a second set, and a) said ribs of said first set are disposed substantially parallel to one another and substantially in a first plane, and b) said ribs of said second set being disposed substantially parallel to one another and substantially in a second plane, and wherein said first and second planes are disposed adjacent one another.
Claim 21
Dependent Claim
58 words
The synthetic drainable base course of claim 18 , wherein further ribs are provided in at least a third set wherein said ribs of said third set are disposed substantially parallel to one another and said third set of ribs is disposed in a third plane adjacent and non-parallel to the ribs of said first or second sets.
Claim 22
Dependent Claim
42 words
The synthetic drainable base course of claim 18 , wherein the cross-section of any one of said ribs approximates one or more shapes from the group consisting of a square, a rectangle, an oval, a star shape, a crenulation, and a trapezoid.
Claim 23
Dependent Claim
51 words
The synthetic drainable base course of claim 20 , wherein at least one of said ribs has the cross-section of a square and said square has a width and a height approximately equal to one another, and said width and said height have dimensions of from 1.0 mm to 10.0 mm.
Claim 24
Dependent Claim
55 words
The synthetic drainable base course of claim 20 , wherein at least one of said ribs has the cross-section of a rectangle and said rectangle has a width and a height, and said width has dimensions of from 2.0 mm to 15.0 mm and said height has dimensions of from 1.0 mm to 10.0 mm.
Claim 25
Dependent Claim
72 words
The synthetic drainable base course of claim 20 , wherein at least one of said ribs has the cross-section of a trapezoid and said trapezoid has a major width, a minor width and a height, and said major width has dimensions of from 2.0 mm to 15.0 mm, said minor width has dimensions of from 1.0 mm to 10.0 mm and said height has dimensions of from 1.0 mm to 10.0 mm.
Claim 26
Dependent Claim
30 words
The synthetic drainable base course of claim 2 , wherein at least some of said ribs comprise crenulations and said crenulations are disposed longitudinally along the surfaces of said ribs.
Claim 27
Dependent Claim
28 words
The synthetic drainable base course of claim 2 , wherein all of said ribs are crenulated and said crenulations are disposed longitudinally along the surfaces of said ribs.
Claim 28
Dependent Claim
38 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 1,200 kPa for at least 10,000 hours at 20 degrees Celsius, said thickness under load is at least 65% of said no-load thickness.
Claim 29
Dependent Claim
38 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 720 kPa for at least 5,000 hours at 40 degrees Celsius, said thickness under load is at least 65% of said no-load thickness.
Claim 30
Dependent Claim
38 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 1,200 kPa for at least 10,000 hours at 20 degrees Celsius, said thickness under load is at least 60% of said no-load thickness.
Claim 31
Dependent Claim
38 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 720 kPa for at least 5,000 hours at 40 degrees Celsius, said thickness under load is at least 60% of said no-load thickness.
Claim 32
Dependent Claim
38 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 1,200 kPa for at least 10,000 hours at 20 degrees Celsius, said thickness under load is at least 50% of said no-load thickness.
Claim 33
Dependent Claim
38 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 720 kPa for at least 5,000 hours at 40 degrees Celsius, said thickness under load is at least 50% of said no-load thickness.
Claim 34
Dependent Claim
45 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 720 kPa and a shear load of 240 kPa for at least 5,000 hours at 40 degrees Celsius, said thickness under load is at least 50% of said no-load thickness.
Claim 35
Dependent Claim
45 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 720 kPa and a shear load of 240 kPa for at least 5,000 hours at 40 degrees Celsius, said thickness under load is at least 45% of said no-load thickness.
Claim 36
Dependent Claim
45 words
The synthetic drainable base course of claim 2 , wherein under a normal load of 720 kPa and a shear load of 240 kPa for at least 5,000 hours at 40 degrees Celsius, said thickness under load is at least 40% of said no-load thickness.
Claim 37
Dependent Claim
24 words
The synthetic drainable base course of claim 2 , wherein said no-load thickness is in the range of from 0.20 inches to 1.00 inches.
Claim 38
Dependent Claim
24 words
The synthetic drainable base course of claim 2 , wherein said no-load thickness is in the range of from 0.20 inches to 0.75 inches.
Claim 39
Dependent Claim
24 words
The synthetic drainable base course of claim 2 , wherein said no-load thickness is in the range of from 0.25 inches to 0.35 inches.
Claim 40
Dependent Claim
38 words
The synthetic drainable base course of claim 2 , wherein said core element is a machine manufactured network of fibers or filaments and has a tensile strength of at least 400 lbs per foot in the machine direction.
Claim 41
Dependent Claim
38 words
The synthetic drainable base course of claim 2 , wherein said core element is a machine manufactured network of fibers or filaments and has a tensile strength of at least 500 lbs per foot in the machine direction.
Claim 42
Dependent Claim
26 words
The synthetic drainable base course of claim 2 , wherein said gradient is at least 1% in a direction away from said portion of said landfill.
Claim 43
Dependent Claim
18 words
The synthetic drainable base course of claim 2 , wherein said portion of said landfill is the centerline.
Claim 44
Dependent Claim
41 words
The synthetic drainable base course of claim 2 , wherein under a load of 720 kPa for at least 100 hours, said voids maintain an average width of at least 2.0 mm and an average height of at least 10.0 mm.
Claim 45
Dependent Claim
34 words
The synthetic drainable base course of claim 2 , wherein under a load of 720 kPa for at least 100 hours, said voids maintain an average width of from 2.0 mm to 10.0 mm.
Claim 46
Dependent Claim
34 words
The synthetic drainable base course of claim 2 , wherein under a load of 720 kPa for at least 100 hours, said voids maintain an average width of from 3.0 mm to 8.0 mm.
Claim 47
Dependent Claim
34 words
The synthetic drainable base course of claim 2 , wherein under a load of 1,200 kPa for at least 100 hours, said voids maintain an average width of from 2.0 mm to 10.0 mm.
Claim 48
Dependent Claim
34 words
The synthetic drainable base course of claim 2 , wherein under a load of 1,200 kPa for at least 100 hours, said voids maintain an average width of from 3.0 mm to 8.0 mm.
Claim 49
Dependent Claim
34 words
The synthetic drainable base course of claim 2 , wherein under a load of 1,200 kPa for at least 100 hours, said voids maintain an average height of from 2.0 mm to 10.0 mm.
Claim 50
Dependent Claim
34 words
The synthetic drainable base course of claim 2 , wherein under a load of 1,200 kPa for at least 100 hours, said voids maintain an average height of from 3.0 mm to 8.0 mm.
Claim 51
Dependent Claim
41 words
The synthetic drainable base course of claim 2 , wherein under a load of 720 kPa for at least 100 hours, said voids maintain an average width of at least 3.0 mm and an average height of at least 10.0 mm.
Claim 52
Dependent Claim
41 words
The synthetic drainable base course of claim 2 , wherein under a load of 1,200 kPa for at least 100 hours, said voids maintain an average width of at least 2.0 mm and an average height of at least 8.0 mm.
Claim 53
Dependent Claim
41 words
The synthetic drainable base course of claim 2 , wherein under a load of 720 kPa for at least 100 hours, said voids maintain an average width of at least 6.0 mm and an average height of at least 8.0 mm.
Claim 54
Dependent Claim
41 words
The synthetic drainable base course of claim 2 , wherein under a load of 1,200 kPa for at least 1,000 hours, said voids maintain an average width of at least 2.0 mm and an average height of at least 8.0 mm.
Claim 55
Dependent Claim
41 words
The synthetic drainable base course of claim 2 , wherein under a load of 720 kPa for at least 1,000 hours, said voids maintain an average width of at least 6.0 mm and an average height of at least 8.0 mm.
Claim 56
Dependent Claim
32 words
The synthetic drainable base course of claim 2 , wherein said ribs are constructed and arranged to form preferential flow paths and non-preferential flow paths in a sloped portion of said landfill.
Claim 57
Dependent Claim
31 words
The synthetic drainable base course of claim 54 , wherein said preferential flow paths and said non-preferential flow paths are not parallel to one another and are formed by said ribs.
Claim 58
Dependent Claim
28 words
The synthetic drainable base course of claim 54 , disposed in a landfill such that said preferential flow paths are substantially perpendicular to said portion of said landfill.
Claim 59
Dependent Claim
28 words
The synthetic drainable base course of claim 54 , disposed in a landfill such that said preferential flow paths are substantially parallel to said portion of said landfill.
Claim 60
Dependent Claim
31 words
The synthetic drainable base course of claim 54 , wherein at least 35% of the volume of fluid moving through said SDBC does so by way of said preferential flow paths.
Claim 61
Dependent Claim
31 words
The synthetic drainable base course of claim 54 , wherein at least 50% of the volume of fluid moving through said SDBC does so by way of said preferential flow paths.
Claim 62
Dependent Claim
31 words
The synthetic drainable base course of claim 54 , wherein at least 65% of the volume of fluid moving through said SDBC does so by way of said preferential flow paths.
Claim 63
Dependent Claim
33 words
The synthetic drainable base course of claim 54 , wherein said portion of said landfill is the centerline or axis of at least one of said first and second portions of said landfill.
Claim 64
Dependent Claim
32 words
The synthetic drainable base course of claim 1 , wherein said geocomposite core comprises at least one margin constructed and arranged to transmit fluids from said base course away from said landfill.
Claim 65
Dependent Claim
51 words
The synthetic drainable base course of claim 62 , wherein said at least one margin is constructed and arranged to connect with one or more selected from the group consisting of perforated pipes, non-perforated pipes, drainage ditches, sumps, canals, re-circulating manifolds, drainage manifolds and facilities for further processing of said fluid.
Claim 66
Independent Claim
258 words
A method of forming drainable landfill, comprising the steps of I. providing a base layer formed at least partially of one or more of native soil components and non-native soil components, II. providing a synthetic drainable base course element disposed above said base layer, said drainage element comprising A) a void-maintaining geocomposite, said geocomposite including i) a geocomposite core element having a plurality of ribs constructed and arranged to form a plurality of interconnected voids, said core element having an upper surface and a lower surface, a no-load thickness and a thickness under load, wherein said thicknesses are measured substantially perpendicular to said surfaces, and ii) at least one fluid-transmissible layer attached adjacent said upper surface, wherein said layers and said core element are constructed and arranged so that, under a load of at least 500 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 19 gallons/minute/foot at a slope gradient of 33% and at least 33 gallons/minute at a slope gradient of 10%, and III. providing above said synthetic drainable base course, fill suitable to be drained, said fill comprising one or more layers, sections or quantities of refuse materials, or materials to be processed at least partially within said landfill, wherein at least a portion of said synthetic drainable base course is sloped downwardly in a gradient from a first portion to a second portion of said landfill.
Claim 67
Independent Claim
258 words
A method of forming drainable landfill, comprising the steps of I. providing a base layer formed at least partially of one or more of native soil components and non-native soil components, II. providing a synthetic drainable base course element disposed above said base layer, said drainage element comprising A) a void-maintaining geocomposite, said geocomposite including i) a geocomposite core element having a plurality of ribs constructed and arranged to form a plurality of interconnected voids, said core element having an upper surface and a lower surface, a no-load thickness and a thickness under load, wherein said thicknesses are measured substantially perpendicular to said surfaces, and ii) at least one fluid-transmissible layer attached adjacent said upper surface, wherein said layers and said core element are constructed and arranged so that, under a load of at least 500 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 19 gallons/minute/foot at a slope gradient of 33% and at least 33 gallons/minute at a slope gradient of 10%, and III. providing above said synthetic drainable base course, fill suitable to be drained, said fill comprising one or more layers, sections or quantities of refuse materials, or materials to be processed at least partially within said landfill, wherein at least a portion of said synthetic drainable base course is sloped downwardly in a gradient from a first portion to a second portion of said landfill.
Claim 68
Dependent Claim
49 words
The method of claim 64 , wherein said non-native soil components are one or more selected from the group consisting of refuse from highway excavations, refuse from building foundation excavations, mining refuse, manufacturing refuse, geologic refuse, gypsum refuse, quarry refuse, refuse from road-building activities, and refuse from dredging operations.
Claim 69
Dependent Claim
19 words
The method of claim 64 , wherein said base layer of said drainable structure comprises at least one slope.
Claim 70
Dependent Claim
30 words
The method of claim 64 , wherein said drainage element of said drainable landfill further comprises iii) at least one frictional layer attached adjacent said lower surface of said geocomposite.
Claim 71
Dependent Claim
29 words
The method of claim 64 , wherein said drainage element of said drainable landfill further comprises iii) at least one cushion layer adjacent said lower surface of said geocomposite.
Claim 72
Dependent Claim
11 words
The method of claim 64 , wherein said landfill is layered.
Claim 73
Dependent Claim
76 words
The method of claim 64 , wherein said ribs of said core are provided in a first set and a second set, and a) said ribs of said first set are disposed substantially parallel to one another and substantially in a first plane, and b) said ribs of said second set being disposed substantially parallel to one another and substantially in a second plane, and wherein said first and second planes are disposed adjacent one another.
Claim 74
Dependent Claim
55 words
The method of claim 64 , wherein further ribs are provided in at least a third set wherein said ribs of said third set are disposed substantially parallel to one another and said third set of ribs is disposed in a third plane adjacent and non-parallel to the ribs of said first or second sets.
Claim 75
Dependent Claim
33 words
The method of claim 64 , wherein the cross-section of any one of said ribs approximates one or more shapes from the group consisting of squares, rectangles, ovals, star shapes, crenulations, and trapezoids.
Claim 76
Dependent Claim
82 words
The method of claim 64 , wherein said layers and said core element are constructed and arranged so that, under a load of at least 1,000 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 19 gallons/minute/foot at a slope gradient of 33% and at least 33 gallons/minute at a slope gradient of 10%.
Claim 77
Dependent Claim
71 words
The method of claim 64 , wherein said layers and said core element are constructed and arranged so that, under a load of at least 15,000 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 8.5 gallons/minute/foot at a slope gradient of 10%.
Claim 78
Dependent Claim
71 words
The method of claim 64 , wherein said layers and said core element are constructed and arranged so that, under a load of at least 25,000 lbs/foot 2 for a period of at least 100 hours, said geocomposite maintains voids of sufficient dimension that fluid from said landfill can move freely through portions of said drainage element at a transmissivity of at least 3.5 gallons/minute/foot at a slope gradient of 10%.
References Cited (Backward Citations)
US4397899A
Cited
US4749306A
Cited
US4815892A
Cited
US4815892B1
Cited
US4992003A
Cited
US5183355A
Cited
US5190406A
Cited
US5823706A
Cited
US5980155A
Cited
US5735640A
Cited
US6481934B1
Cited
US20010002497A1
Cited
US6648549B1
Cited
US20030118404A1
Cited
US6558081B2
Cited
US6599058B1
Cited
US20030223826A1
Cited
US20030215287A1
Cited
US20030199217A1
Cited
US20040022583A1
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 2010-12-17 | 2011-06-18 | 2011-12-18 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 2014-12-17 | 2015-06-18 | 2015-12-18 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 2018-12-17 | 2019-06-18 | 2019-12-18 | $7700.00 | Window Closed / Lapsed |