← Back to Patent Explorer
US6128588A Expired / Lapsed US ⏱️ 0.0 years remaining

Integrated wafer fab time standard (machine tact) database

Assignee: Sony Corp
•
Filing: 1997-10-01
•
Granted: 2000-10-03
•
Expires: 2017-10-01
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract An integrated wafer fab production characterization and scheduling system incorporates a manufacturing execution system with a scheduling system based on simulation. The integrated characterization/scheduling system provides manufacturing with a simulation tool integrated with the manufacturing execution system to evaluate proposed production control logic as a practical alternative to expensive experimentation on actual production system. Furthermore, simulation models are used to create short term dispatch schedules to steer daily manufacturing operations towards planned performance goals. Innovative features include integration of preventive maintenance scheduling, Kanban based WIP control, an integrated time standard database, a, and real time lot move updates.

Inventors

  • 👤 Guillermo Rudolfo Chacon

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-02 05:39
CPC Classifications
G; G03; G03F; G03F7/00; G03F7/70; G03F7/708; G03F7/70991; G03F7/70483; G03F7/70491; G03F7/705; G03F7/70525; G05; G05B; G05B19/00; G05B19/02; G05B19/418; G05B19/41865; G05B19/41885; G06; G06Q; G06Q10/00; G06Q10/06; Y; Y02; Y02P; Y02P90/00; Y02P90/02; Y02P90/80

Claims Analysis

Total Claims: 12
Claim 1
Independent Claim 194 words
A modeling and manufacturing execution system comprising: said manufacturing execution system for automatically controlling routing of product lots and production inputs in said manufacturing production line based on a production scheduling model, wherein feedback data from said production line is provided to said manufacturing execution system, said feedback data comprising operating parameters for equipment in said production line and identification of said equipment by type; a database for storing said model, said feedback data and formulae for calculating a production capacity for each piece of said equipment based on said identified type of that piece of equipment and said operating parameters of that piece of equipment; and a simulating system for simulating operation of said production line according to said model, said simulating system using said formulae from said database to calculate said production capacities for said equipment in said production line; wherein each formula in said database is associated with a flag having at least two values; a first of said values indicating that an associated formula is based on actual operation of equipment production of said production line; a second of said values indicating that an associated formula is new and unproven.
Claim 2
Dependent Claim 194 words
A modeling and manufacturing execution system comprising: said manufacturing execution system for automatically controlling routing of product lots and production inputs in said manufacturing production line based on a production scheduling model, wherein feedback data from said production line is provided to said manufacturing execution system, said feedback data comprising operating parameters for equipment in said production line and identification of said equipment by type; a database for storing said model, said feedback data and formulae for calculating a production capacity for each piece of said equipment based on said identified type of that piece of equipment and said operating parameters of that piece of equipment; and a simulating system for simulating operation of said production line according to said model, said simulating system using said formulae from said database to calculate said production capacities for said equipment in said production line; wherein each formula in said database is associated with a flag having at least two values; a first of said values indicating that an associated formula is based on actual operation of equipment production of said production line; a second of said values indicating that an associated formula is new and unproven.
Claim 3
Dependent Claim 34 words
The system of claim 1, wherein said flag has a third value indicating that said simulating system should retain an associated formula in said database, but should ignore said associated formula in performing simulations.
Claim 4
Dependent Claim 197 words
A modeling and manufacturing execution system comprising: said manufacturing execution system for automatically controlling routing of product lots and production inputs in said manufacturing production line based on a production scheduling model, wherein feedback data from said production line is provided to said manufacturing execution system, said feedback data comprising operating parameters for equipment in said production line and identification of said equipment by type; a database for storing said model, said feedback data and formulae for calculating a production capacity for each piece of said equipment based on said identified type of that piece of equipment and said operating parameters of that piece of equipment; and a simulating system for simulating operation of said production line according to said model, said simulating system using said formulae from said database to calculate said production capacities for said equipment in said production line; wherein said manufacturing execution system uses said production capacities generated by said simulating system to create a routing schedule for said production inputs and said product lots; wherein said manufacturing execution system scans generated routes for equipment in said production line without a determined production capacity to determine potential problem areas in said generated routes.
Claim 5
Dependent Claim 197 words
A modeling and manufacturing execution system comprising: said manufacturing execution system for automatically controlling routing of product lots and production inputs in said manufacturing production line based on a production scheduling model, wherein feedback data from said production line is provided to said manufacturing execution system, said feedback data comprising operating parameters for equipment in said production line and identification of said equipment by type; a database for storing said model, said feedback data and formulae for calculating a production capacity for each piece of said equipment based on said identified type of that piece of equipment and said operating parameters of that piece of equipment; and a simulating system for simulating operation of said production line according to said model, said simulating system using said formulae from said database to calculate said production capacities for said equipment in said production line; wherein said manufacturing execution system uses said production capacities generated by said simulating system to create a routing schedule for said production inputs and said product lots; wherein said manufacturing execution system scans generated routes for equipment in said production line without a determined production capacity to determine potential problem areas in said generated routes.
Claim 6
Dependent Claim 59 words
The system of claim 1, wherein a safeguard system prevents a first formula with a flag of said first value and a second formula with a flag of said second value from being retained in said database where both said first and second formulas would be indicated for use in response to a given set of said feedback data.
Claim 7
Dependent Claim 185 words
A modeling and manufacturing execution method comprising: automatically controlling routing of product lots and production inputs in a manufacturing production line with a manufacturing execution system based on a production scheduling model; providing feedback data from said production line to said manufacturing execution system, said feedback data comprising operating parameters for equipment in said production line and identification of said equipment by type; storing in a database said model, said feedback data and formulae for calculating a production capacity for each piece of said equipment based on said identified type of that piece of equipment and said operating parameters of that piece of equipment; simulating operation of said production line with a simulation system according to said model and using said formulae to calculate said production capacities for said equipment in said production line; and associating each formula in said database with a flag having at least two values; a first of said values indicating that an associated formula is based on actual operation of equipment production of said production line; a second of said values indicating that an associated formula is new and unproven.
Claim 8
Dependent Claim 185 words
A modeling and manufacturing execution method comprising: automatically controlling routing of product lots and production inputs in a manufacturing production line with a manufacturing execution system based on a production scheduling model; providing feedback data from said production line to said manufacturing execution system, said feedback data comprising operating parameters for equipment in said production line and identification of said equipment by type; storing in a database said model, said feedback data and formulae for calculating a production capacity for each piece of said equipment based on said identified type of that piece of equipment and said operating parameters of that piece of equipment; simulating operation of said production line with a simulation system according to said model and using said formulae to calculate said production capacities for said equipment in said production line; and associating each formula in said database with a flag having at least two values; a first of said values indicating that an associated formula is based on actual operation of equipment production of said production line; a second of said values indicating that an associated formula is new and unproven.
Claim 9
Dependent Claim 34 words
The method of claim 5, wherein said flag has a third value indicating that said simulating system should retain an associated formula in said database, but should ignore said associated formula in performing simulations.
Claim 10
Dependent Claim 184 words
A modeling and manufacturing execution method comprising: automatically controlling routing of product lots and production inputs in a manufacturing production line with a manufacturing execution system based on a production scheduling model; providing feedback data from said production line to said manufacturing execution system, said feedback data comprising operating parameters for equipment in said production line and identification of said equipment by type; storing in a database said model, said feedback data and formulae for calculating a production capacity for each piece of said equipment based on said identified type of that piece of equipment and said operating parameters of that piece of equipment; simulating operation of said production line with a simulation system according to said model and using said formulae to calculate said production capacities for said equipment in said production line; generating a routing schedule for said production inputs and said product lots with said manufacturing execution system using said production capacities generated by said simulation system; and scanning generated routes for equipment in said production line without a determined production capacity to determine potential problem areas in said generated routes.
Claim 11
Dependent Claim 184 words
A modeling and manufacturing execution method comprising: automatically controlling routing of product lots and production inputs in a manufacturing production line with a manufacturing execution system based on a production scheduling model; providing feedback data from said production line to said manufacturing execution system, said feedback data comprising operating parameters for equipment in said production line and identification of said equipment by type; storing in a database said model, said feedback data and formulae for calculating a production capacity for each piece of said equipment based on said identified type of that piece of equipment and said operating parameters of that piece of equipment; simulating operation of said production line with a simulation system according to said model and using said formulae to calculate said production capacities for said equipment in said production line; generating a routing schedule for said production inputs and said product lots with said manufacturing execution system using said production capacities generated by said simulation system; and scanning generated routes for equipment in said production line without a determined production capacity to determine potential problem areas in said generated routes.
Claim 12
Dependent Claim 55 words
The method of claim 5, preventing a first formula with a flag of said first value and a second formula with a flag of said second value from being retained in said database where both said first and second formulas would be indicated for use in response to a given set of said feedback data.

References Cited (Backward Citations)

US5479343A Cited
US5396432A Cited
US5751580A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 2003-10-03 2004-04-03 2004-10-03 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2007-10-03 2008-04-03 2008-10-03 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2011-10-03 2012-04-03 2012-10-03 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag