Claims Analysis
Total Claims: 8
Claim 1
Independent Claim
210 words
A computer implemented decision support method which intelligently matches assets with demand to create a material requirements planning (MRP) match to determine what work needs to be accomplished to meet demand comprising the steps of: accessing a bill of materials in computer memory to identify parts by part numbers of a product to be manufactured; classifying each part by part number as MRP, Linear Programming (LP) MRP, or non-critical, LPMRP parts being identified from binning data and data related to permissible substitutions and build options as those parts which may be substituted for or by another part number that does not result as output from the same binning process, non-critical parts being identified by a planner using the method as those which can be run with MRP as can components and sub-components of the non-critical parts, and MRP parts being those not classified as LPMRP parts or non-critical parts; accessing a build options file, a bill of materials file, binning data and permissible substitutions data in computer memory and processing LPMRP parts using a series of integrated LP and MRP methods; processing MRP parts and non-critical parts using a heuristic method; and consolidating output from the processing steps using linear programming and heuristic methods and providing a single output file.
Claim 2
Dependent Claim
210 words
A computer implemented decision support method which intelligently matches assets with demand to create a material requirements planning (MRP) match to determine what work needs to be accomplished to meet demand comprising the steps of: accessing a bill of materials in computer memory to identify parts by part numbers of a product to be manufactured; classifying each part by part number as MRP, Linear Programming (LP) MRP, or non-critical, LPMRP parts being identified from binning data and data related to permissible substitutions and build options as those parts which may be substituted for or by another part number that does not result as output from the same binning process, non-critical parts being identified by a planner using the method as those which can be run with MRP as can components and sub-components of the non-critical parts, and MRP parts being those not classified as LPMRP parts or non-critical parts; accessing a build options file, a bill of materials file, binning data and permissible substitutions data in computer memory and processing LPMRP parts using a series of integrated LP and MRP methods; processing MRP parts and non-critical parts using a heuristic method; and consolidating output from the processing steps using linear programming and heuristic methods and providing a single output file.
Claim 3
Dependent Claim
98 words
The computer implemented decision support method recited in claim 1 wherein the step of classifying each part by part number comprises the steps of: identifying an initial set of non-critical parts; identifying all non-critical parts by exploding through the accessed bill of material; identifying an initial set of LPMRP parts by examining situations with alternate processes and/or substitutions outside of binned processes; identifying a complete set of LPMRP parts by iteratively exploding down and imploding up through the accessed bill of material; and identifying as MRP parts all parts not previously identified as non-critical parts or LPMRP parts.
Claim 4
Dependent Claim
31 words
The computer implemented decision support method recited in claim 1 further comprising the step of transforming a multiple process per part number representation into a single process per part number representation.
Claim 5
Dependent Claim
62 words
The computer implemented decision support method recited in claim 1 further comprising the step of determining low-level codes such that each part number has a same low-level code as all parts for which it may substitute, and each part number resulting as output of a binning process has a same low-level code as all other part numbers output from that binning process.
Claim 6
Dependent Claim
36 words
The computer implemented decision support method recited in claim 4 wherein the processing of LPMRP parts component comprises the step of running an integrated LP and MRP process at each level of the bill of material.
Claim 7
Dependent Claim
79 words
The computer implemented decision support method recited in claim 5 wherein the LPMRP processing further comprises the steps of: determining whether an LP method is required at each low level code; invoking an LP method at each required low level code; taking an output of the LP run and feeding its resulting substitutions (and implicitly alternate processes) into an MRP method for that low level code; and invoking an MRP method which considers LP substitutions as demands and receipts.
Claim 8
Dependent Claim
44 words
The computer implemented decision support method recited in claim 1 wherein the processing of any non-critical parts comprises the steps of: gathering dependent demand for non-critical parts stemming from the MRP and LPMRP methods; and executing an MRP run for the non-critical part numbers.