US5940370A Expired / Lapsed US ⏱️ 0.0 years remaining

ABR traffic management in ATM networks

Assignee: Fujitsu Ltd
•
Filing: 1996-06-05
•
Granted: 1999-08-17
•
Expires: 2016-06-05
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract Connection control apparatus is provided for use in an ATM network to control ABR connections provided by the network, each such ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network. The apparatus includes: congestion detection circuitry (32, 33) for determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; and a rate control circuit (30) connected to the said congestion detection circuitry for detecting, based on the determined end-to-end delay, when one of the ABR channels is congested. When congestion in one of the ABR channels is detected the rate control circuit imposes on the ABR connection concerned a maximum transmission rate that is higher than and dependent upon the said agreed minimum transmission rate for the connection concerned. Such apparatus can assist in achieving a fair allocation of bandwidth when congestion occurs in the network, and provides an effective way of detecting congestion without requiring processing at each intermediate node within the ATM network.

Inventors

  • 👤 Marc Simon Curtis
  • 👤 Ana Ferrandiz Roca

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 13:19
CPC Classifications
H; H04; H04L; H04L12/00; H04L12/54; H04L12/56; H04L12/5601; H04L12/5602; H04Q; H04Q11/00; H04Q11/04; H04Q11/0428; H04Q11/0478; H04Q3/00; H04Q3/0016; H04Q3/0062; H04Q3/0066; H04L2012/5619; H04L2012/5629; H04L2012/5631; H04L2012/5632; H04L2012/5636; H04L2012/5638; H04L2012/5646; H04L2012/5649; H04Q2213/00; H04Q2213/13523; H04Q2213/13561

Claims Analysis

Total Claims: 41
Claim 1
Independent Claim 165 words
Connection control apparatus, for use in an ATM network to control ABR connections provided by the network, each said ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which apparatus includes: maximum transmission rate calculation means for calculating for each said ABR connection a maximum transmission rate that is higher than and dependent upon said agreed minimum transmission rate for the connection concerned; congestion detection means for determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; and rate control means connected to said congestion detection means for detecting, based on the determined end-to-end delay, when one of the ABR connections is congested, and operative, upon such detection, to impose on the ABR connection concerned its said maximum transmission rate, and, when no such congestion of the ABR connection concerned is detected, to permit the ABR connection concerned to exceed that maximum transmission rate.
Claim 2
Dependent Claim 165 words
Connection control apparatus, for use in an ATM network to control ABR connections provided by the network, each said ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which apparatus includes: maximum transmission rate calculation means for calculating for each said ABR connection a maximum transmission rate that is higher than and dependent upon said agreed minimum transmission rate for the connection concerned; congestion detection means for determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; and rate control means connected to said congestion detection means for detecting, based on the determined end-to-end delay, when one of the ABR connections is congested, and operative, upon such detection, to impose on the ABR connection concerned its said maximum transmission rate, and, when no such congestion of the ABR connection concerned is detected, to permit the ABR connection concerned to exceed that maximum transmission rate.
Claim 3
Dependent Claim 25 words
Apparatus as claimed in claim 1, wherein the imposed maximum transmission rate is increased when said agreed minimum transmission rate increases for the connection concerned.
Claim 4
Dependent Claim 26 words
Apparatus as claimed in claim 2, wherein said imposed maximum transmission rate is also dependent upon the agreed minimum transmission rates of other such ABR connections.
Claim 5
Dependent Claim 48 words
Apparatus as claimed in claim 1, wherein said rate control means are arranged at an ingress node of the network that is linked to other parts of the network by an access link, the imposed maximum transmission rate being dependent upon the available capacity of the access link.
Claim 6
Dependent Claim 38 words
Apparatus as claimed in claim 4, wherein said available capacity of the access link is determined by subtracting from the full capacity of the access link the sum of the agreed minimum transmission rates of the ABR connections.
Claim 7
Dependent Claim 63 words
Apparatus as claimed in claim 5, wherein the imposed maximum transmission rate MAXR VCj is made equal to: ##EQU5## where: VC1 to VCn denote the different ABR connections, VC j being the ABR connection in which congestion has been detected; SCR VCx is the agreed minimum transmission rate of the ABR connection VCx; and AB is said available bandwidth of the access link.
Claim 8
Dependent Claim 51 words
Apparatus as claimed in claim 1, further including bandwidth allocation means operable, when a request is received by the apparatus for establishment of a new ABR connection, to determine the maximum transmission rate for the new connection and to recalculate the respective maximum transmission rates of all the existing ABR connections.
Claim 9
Dependent Claim 144 words
Apparatus as claimed in claim 7, wherein: said rate control means are arranged at an ingress node of the network that is linked to other parts of the network by an access link, the imposed maximum transmission rate being dependent upon the available capacity of the access link, said available capacity of the access link being determined by subtracting from the full capacity of the access link the sum of the agreed minimum transmission rates of the ABR connections; and said bandwidth allocation means are also operable, when the apparatus is in use, to determine an instantaneous available bandwidth of said access link by subtracting from said full capacity of the access link the sum of the actual transmission rates of the ABR connections, and are operable to calculate the maximum transmission rate of each ABR connection based on the determined instantaneous available bandwidth.
Claim 10
Dependent Claim 60 words
Apparatus as claimed in claim 8, wherein said maximum transmission rate MAXR VCj is made equal to: ##EQU6## where: VC1 to VCn denote the different ABR connections, VC j being the ABR connection in which congestion has been detected; SCR VCx is the agreed minimum transmission rate of the ABR connection VCx; and IAB is the determined instantaneous available bandwidth.
Claim 11
Dependent Claim 57 words
Apparatus as claimed in claim 1, wherein said rate control means send a feedback message to the data source of the congested ABR connection if it is exceeding its said maximum transmission rate when that rate is imposed, which feedback message requests the data source concerned to reduce its transmission rate to the imposed maximum transmission rate.
Claim 12
Dependent Claim 44 words
Apparatus as claimed in claim 10, wherein said rate control means impose further restrictions progressively on the transmission rate of the congested ABR connection, if the congestion persists, until the transmission rate is reduced to the agreed minimum transmission rate for the connection concerned.
Claim 13
Dependent Claim 35 words
Apparatus as claimed in claim 1, wherein said rate control means detect that congestion is occurring in one of the ABR connections when the determined end-to-end delay for that connection exceeds a predetermined threshold value.
Claim 14
Dependent Claim 32 words
Apparatus as claimed in claim 1, wherein the rate control means are operative to impose said maximum transmission rate on the ABR connection concerned immediately when congestion of that connection is detected.
Claim 15
Dependent Claim 247 words
Connection control apparatus, for use in an ATM network to control ABR connections provided by the network, each said ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which apparatus includes: congestion detection means for determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; and rate control means connected to the said congestion detection means for detecting, based on the determined end-to-end delay, when one of the ABR connections is congested, and operative, upon such detection, to impose on the ABR connection concerned a maximum transmission rate that is higher than and dependent upon said agreed minimum transmission rate for the connection concerned; said rate control means being operable to detect that congestion is occurring in one of the ABR connections when the determined end-to-end delay for that connection exceeds a predetermined threshold value; and said congestion detection means comprising first and second circuits arranged respectively at ingress and egress nodes of the network, one of said first and second circuits being operative to transmit a timing cell to the other of those circuits via the network, and said other circuit being operative to determine the time of receipt of the timing cell concerned; the congestion detection means being operative to calculate said end-to-end delay in dependence upon the time taken for said timing cell to travel from said one circuit to said other circuit.
Claim 16
Dependent Claim 247 words
Connection control apparatus, for use in an ATM network to control ABR connections provided by the network, each said ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which apparatus includes: congestion detection means for determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; and rate control means connected to the said congestion detection means for detecting, based on the determined end-to-end delay, when one of the ABR connections is congested, and operative, upon such detection, to impose on the ABR connection concerned a maximum transmission rate that is higher than and dependent upon said agreed minimum transmission rate for the connection concerned; said rate control means being operable to detect that congestion is occurring in one of the ABR connections when the determined end-to-end delay for that connection exceeds a predetermined threshold value; and said congestion detection means comprising first and second circuits arranged respectively at ingress and egress nodes of the network, one of said first and second circuits being operative to transmit a timing cell to the other of those circuits via the network, and said other circuit being operative to determine the time of receipt of the timing cell concerned; the congestion detection means being operative to calculate said end-to-end delay in dependence upon the time taken for said timing cell to travel from said one circuit to said other circuit.
Claim 17
Dependent Claim 73 words
Apparatus as claimed in claim 14, wherein said timing cell transmitted from said one circuit to said other circuit carries timing information indicating the time of transmission of the cell concerned by said one circuit, and said other circuit includes relative delay calculation means operative to determine a relative delay value by calculating the difference between said time of transmission of the timing cell and its time of receipt by said other circuit.
Claim 18
Dependent Claim 107 words
Apparatus as claimed in claim 15, wherein said other circuit is operative, following receipt of such a timing cell from said one circuit, to transmit a corresponding timing cell back to said one circuit via the network, and said one circuit is operative to determine the time of receipt of said corresponding timing cell; said congestion detection means being operative to calculate said end-to-end delay in dependence upon the average of the time taken for the timing cell to travel from said one circuit to said other circuit and the time taken for said corresponding timing cell to travel from said other circuit to said one circuit.
Claim 19
Dependent Claim 91 words
Apparatus as claimed in claim 16, wherein said corresponding timing cell transmitted from said other circuit back to said one circuit carries timing information indicating the time of transmission of the cell concerned by said other circuit and also indicating said relative delay value, and said one circuit includes round-trip-delay calculating means operative to determine a round-trip delay value by calculating the difference between said time of transmission of the corresponding timing cell and its time of receipt by said one circuit and subtracting from that difference said relative delay value.
Claim 20
Independent Claim 140 words
A method of controlling ABR connections in an ATM network, each such ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which method includes the steps of: calculating for each said ABR connection a maximum transmission rate that is hither than and dependent upon said agreed minimum transmission rate for the ABR connection concerned; determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; detecting, based on the determined end-to-end delay, when one of the ABR connections is congested; and when such congestion is detected, imposing on the ABR connection concerned its said maximum transmission rate and, when no such congestion of the ABR connection concerned is detected, permitting the ABR connection concerned to exceed that maximum transmission rate.
Claim 21
Independent Claim 140 words
A method of controlling ABR connections in an ATM network, each such ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which method includes the steps of: calculating for each said ABR connection a maximum transmission rate that is hither than and dependent upon said agreed minimum transmission rate for the ABR connection concerned; determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; detecting, based on the determined end-to-end delay, when one of the ABR connections is congested; and when such congestion is detected, imposing on the ABR connection concerned its said maximum transmission rate and, when no such congestion of the ABR connection concerned is detected, permitting the ABR connection concerned to exceed that maximum transmission rate.
Claim 22
Dependent Claim 184 words
Congestion detection apparatus for use in an ATM network, including end-to-end delay determining means operable to determine the end-to-end delay experienced by ATM cells of a virtual channel of the network as they pass through the network; and congestion detection means connected to the end-to-end delay determining means for detecting congestion in the concerned virtual channel based on the determined end-to-end delay; said congestion detection means being operable to detect that congestion is occurring in a virtual channel when the determined end-to-end delay for that channel exceeds a predetermined threshold value; and said end-to-end delay determining means comprising first and second circuits arranged respectively at ingress and egress nodes of the network, one of said first and second circuits being operative to transmit a timing cell to the other of those circuits via the network, and said other circuit being operative to determine the time of receipt of the timing cell concerned; said end-to-end delay determining means being operative to calculate said end-to-end delay in dependence upon the time taken for said timing cell to travel from said one circuit to said other circuit.
Claim 23
Dependent Claim 184 words
Congestion detection apparatus for use in an ATM network, including end-to-end delay determining means operable to determine the end-to-end delay experienced by ATM cells of a virtual channel of the network as they pass through the network; and congestion detection means connected to the end-to-end delay determining means for detecting congestion in the concerned virtual channel based on the determined end-to-end delay; said congestion detection means being operable to detect that congestion is occurring in a virtual channel when the determined end-to-end delay for that channel exceeds a predetermined threshold value; and said end-to-end delay determining means comprising first and second circuits arranged respectively at ingress and egress nodes of the network, one of said first and second circuits being operative to transmit a timing cell to the other of those circuits via the network, and said other circuit being operative to determine the time of receipt of the timing cell concerned; said end-to-end delay determining means being operative to calculate said end-to-end delay in dependence upon the time taken for said timing cell to travel from said one circuit to said other circuit.
Claim 24
Dependent Claim 73 words
Apparatus as claimed in claim 19, wherein said timing cell transmitted from said one circuit to said other circuit carries timing information indicating the time of transmission of the cell concerned by said one circuit, and said other circuit includes relative delay calculation means operative to determine a relative delay value by calculating the difference between said time of transmission of the timing cell and its time of receipt by said other circuit.
Claim 25
Dependent Claim 106 words
Apparatus as claimed in claim 20, wherein said other circuit is operative, following receipt of such a timing cell from said one circuit, to transmit a corresponding timing cell back to said one circuit via the network, and said one circuit is operative to determine the time of receipt of said corresponding said end-to-end delay determining means being operative to calculate said end-to-end delay in dependence upon the average of the time taken for the timing cell to travel from said one circuit to said other circuit and the time taken for said corresponding timing cell to travel from said other circuit to said one circuit.
Claim 26
Dependent Claim 91 words
Apparatus as claimed in claim 21, wherein said corresponding timing cell transmitted from said other circuit back to said one circuit carries timing information indicating the time of transmission of the cell concerned by said other circuit and also indicating said relative delay value, and said one circuit includes round-trip-delay calculating means operative to determine a round-trip delay value by calculating the difference between said time of transmission of the corresponding timing cell and its time of receipt by said one circuit and subtracting from that difference said relative delay value.
Claim 27
Independent Claim 135 words
A method of detecting congestion in an ATM network, including the steps of: determining the end-to-end delay experienced by ATM cells of a virtual channel of the network as they pass through the network by: employing one of first and second circuits, arranged respectively at ingress and egress nodes of the network, to transmit a timing cell to the other of those circuits via the network; employing the other of said first and second circuits to determine the time of receipt of the timing cell concerned; and calculating said end-to-end delay in dependence upon the time taken for said timing cell to travel from said one circuit to said other circuit; and detecting that congestion is occurring in the virtual channel concerned when the determined end-to-end delay for that channel exceeds a predetermined threshold value.
Claim 28
Independent Claim 135 words
A method of detecting congestion in an ATM network, including the steps of: determining the end-to-end delay experienced by ATM cells of a virtual channel of the network as they pass through the network by: employing one of first and second circuits, arranged respectively at ingress and egress nodes of the network, to transmit a timing cell to the other of those circuits via the network; employing the other of said first and second circuits to determine the time of receipt of the timing cell concerned; and calculating said end-to-end delay in dependence upon the time taken for said timing cell to travel from said one circuit to said other circuit; and detecting that congestion is occurring in the virtual channel concerned when the determined end-to-end delay for that channel exceeds a predetermined threshold value.
Claim 29
Dependent Claim 257 words
Connection control apparatus, for use in an ATM network to control ABR connections provided by the network, each said ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which apparatus includes: maximum transmission rate calculation means for calculating for each said ABR connection a maximum transmission rate that is higher than and dependent upon said agreed minimum transmission rate for the connection concerned; congestion detection means for determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; and rate control means connected to the said congestion detection means for detecting, based on the determined end-to-end delay, when one of the ABR connections is congested, and operative, upon such detection, to impose on the ABR connection concerned its said maximum transmission rate, and, when no such congestion of the ABR connection concerned is detected, to permit the ABR connection concerned to exceed that maximum transmission rate; said rate control means being operable to send a feedback message to the data source of the congested ABR connection if it is exceeding its said maximum transmission rate when that rate is imposed, which feedback message requests the data source concerned to reduce its transmission rate to the imposed maximum transmission rate, and also being operable to impose further restrictions progressively on the transmission rate of the congested ABR connection, if the congestion persists, until the transmission rate is reduced to the agreed minimum transmission rate for the connection concerned.
Claim 30
Dependent Claim 257 words
Connection control apparatus, for use in an ATM network to control ABR connections provided by the network, each said ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which apparatus includes: maximum transmission rate calculation means for calculating for each said ABR connection a maximum transmission rate that is higher than and dependent upon said agreed minimum transmission rate for the connection concerned; congestion detection means for determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; and rate control means connected to the said congestion detection means for detecting, based on the determined end-to-end delay, when one of the ABR connections is congested, and operative, upon such detection, to impose on the ABR connection concerned its said maximum transmission rate, and, when no such congestion of the ABR connection concerned is detected, to permit the ABR connection concerned to exceed that maximum transmission rate; said rate control means being operable to send a feedback message to the data source of the congested ABR connection if it is exceeding its said maximum transmission rate when that rate is imposed, which feedback message requests the data source concerned to reduce its transmission rate to the imposed maximum transmission rate, and also being operable to impose further restrictions progressively on the transmission rate of the congested ABR connection, if the congestion persists, until the transmission rate is reduced to the agreed minimum transmission rate for the connection concerned.
Claim 31
Dependent Claim 25 words
Apparatus as claimed in claim 24, wherein the imposed maximum transmission rate is increased when said agreed minimum transmission rate increases for the connection concerned.
Claim 32
Dependent Claim 26 words
Apparatus as claimed in claim 25, wherein said imposed maximum transmission rate is also dependent upon the agreed minimum transmission rates of other such ABR connections.
Claim 33
Dependent Claim 48 words
Apparatus as claimed in claim 24, wherein said rate control means are arranged at an ingress node of the network that is linked to other parts of the network by an access link, the imposed maximum transmission rate being dependent upon the available capacity of the access link.
Claim 34
Dependent Claim 38 words
Apparatus as claimed in claim 27, wherein said available capacity of the access link is determined by subtracting from the full capacity of the access link the sum of the agreed minimum transmission rates of the ABR connections.
Claim 35
Dependent Claim 63 words
Apparatus as claimed in claim 28, wherein the imposed maximum transmission rate MAXR VCj is made equal to: ##EQU7## where: VC1 to VCn denote the different ABR connections, VC j being the ABR connection in which congestion has been detected; SCR VCx is the agreed minimum transmission rate of the ABR connection VCx; and AB is said available bandwidth of the access link.
Claim 36
Dependent Claim 51 words
Apparatus as claimed in claim 24, further including bandwidth allocation means operable, when a request is received by the apparatus for establishment of a new ABR connection, to determine the maximum transmission rate for the new connection and to recalculate the respective maximum transmission rates of all the existing ABR connections.
Claim 37
Dependent Claim 144 words
Apparatus as claimed in claim 30, wherein: said rate control means are arranged at an ingress node of the network that is linked to other parts of the network by an access link, the imposed maximum transmission rate being dependent upon the available capacity of the access link, said available capacity of the access link being determined by subtracting from the full capacity of the access link the sum of the agreed minimum transmission rates of the ABR connections; and said bandwidth allocation means are also operable, when the apparatus is in use, to determine an instantaneous available bandwidth of said access link by subtracting from said full capacity of the access link the sum of the actual transmission rates of the ABR connections, and are operable to calculate the maximum transmission rate of each ABR connection based on the determined instantaneous available bandwidth.
Claim 38
Dependent Claim 60 words
Apparatus as claimed in claim 31, wherein said maximum transmission rate MAXR VCj is made equal to: ##EQU8## where: VC1 to VCn denote the different ABR connections, VC j being the ABR connection in which congestion has been detected; SCR VCx is the agreed minimum transmission rate of the ABR connection VCx; and IAB is the determined instantaneous available bandwidth.
Claim 39
Dependent Claim 35 words
Apparatus as claimed in claim 24, wherein said rate control means detect that congestion is occurring in one of the ABR connections when the determined end-to-end delay for that connection exceeds a predetermined threshold value.
Claim 40
Independent Claim 220 words
A method of controlling ABR connections in an ATM network, each such ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which method includes the steps of: calculating for each said ABR connection a maximum transmission rate that is higher than and dependent upon said agreed minimum transmission rate for the ABR connection concerned; determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; detecting, based on the determined end-to-end delay, when one of the ABR connections is congested and when such congestion is detected, imposing on the ABR connection concerned its said maximum transmission rate and, when no such congestion of the ABR connection concerned is detected, permitting the ABR connection concerned to exceed that maximum transmission rate; sending a feedback message to the data source of the congested ABR connection if it is exceeding its said maximum transmission rate when that rate is imposed, which feedback message requests the data source concerned to reduce its transmission rate to the imposed maximum transmission rate; and imposing further restrictions progressively on the transmission rate of the congested ABR connection, if the congestion persists, until the transmission rate is reduced to the agreed minimum transmission rate for the connection concerned.
Claim 41
Independent Claim 220 words
A method of controlling ABR connections in an ATM network, each such ABR connection having an agreed minimum transmission rate which it is permitted to exceed when there is spare capacity in the network, which method includes the steps of: calculating for each said ABR connection a maximum transmission rate that is higher than and dependent upon said agreed minimum transmission rate for the ABR connection concerned; determining the end-to-end delay experienced by ATM cells of each ABR connection as they pass through the network; detecting, based on the determined end-to-end delay, when one of the ABR connections is congested and when such congestion is detected, imposing on the ABR connection concerned its said maximum transmission rate and, when no such congestion of the ABR connection concerned is detected, permitting the ABR connection concerned to exceed that maximum transmission rate; sending a feedback message to the data source of the congested ABR connection if it is exceeding its said maximum transmission rate when that rate is imposed, which feedback message requests the data source concerned to reduce its transmission rate to the imposed maximum transmission rate; and imposing further restrictions progressively on the transmission rate of the congested ABR connection, if the congestion persists, until the transmission rate is reduced to the agreed minimum transmission rate for the connection concerned.

References Cited (Backward Citations)

US4551833A Cited
US5070498A Cited
US5193151A Cited
US5241534A Cited
US5335222A Cited
US5400329A Cited
GB2267200A Cited
EP0587522A2 Cited
GB2281005A Cited
US5497375A Cited
US5633859A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 2002-08-16 2003-02-15 2003-08-17 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2006-08-16 2007-02-15 2007-08-17 $3760.00 Window Closed / Lapsed