A computerized method for remotely storing power plant data in a database and for calculating a reserve time for which a power plant can provide power to consumer equipment, the method comprising the steps of: (1) identifying a site associated with the power plant; (2) searching a site facility planner database for the site; (3) prompting a user to identify a power plant associated with the site if the site is located in a site facility planner database; (4) searching a temporary database for the site if the site is not located in a site facility planner database; (5) prompting the user to identify a power plant associated with the site and permitting the user to edit data associated with the power plant if the site is not located in a site facility planner database but is located in a temporary database; (6) generating a new site entry in the temporary database and prompting the user to enter power plant data associated with the new site if the site is not located in a site facility planner database and is not located in the temporary database; (7) prompting the user to identify a consumer equipment load value associated with the power plant; and (8) calculating a reserve time for which the power plant can supply power to the consumer equipment.
Claim 2
Dependent Claim
220 words
A computerized method for remotely storing power plant data in a database and for calculating a reserve time for which a power plant can provide power to consumer equipment, the method comprising the steps of: (1) identifying a site associated with the power plant; (2) searching a site facility planner database for the site; (3) prompting a user to identify a power plant associated with the site if the site is located in a site facility planner database; (4) searching a temporary database for the site if the site is not located in a site facility planner database; (5) prompting the user to identify a power plant associated with the site and permitting the user to edit data associated with the power plant if the site is not located in a site facility planner database but is located in a temporary database; (6) generating a new site entry in the temporary database and prompting the user to enter power plant data associated with the new site if the site is not located in a site facility planner database and is not located in the temporary database; (7) prompting the user to identify a consumer equipment load value associated with the power plant; and (8) calculating a reserve time for which the power plant can supply power to the consumer equipment.
Claim 3
Dependent Claim
101 words
The method of claim 1, wherein step (8) further comprises the steps of: (a) retrieving battery data associated with the power plant from the site facility planner database if the site was located in a site facility planner database; (b) retrieving battery data associated with the power plant from the temporary database if the site was not located in a site facility planner database; (c) calculating a stored potential value of the power plant based on the retrieved battery data associated with the power plant; (d) calculating a time for which the power plant can supply power to the consumer equipment.
Claim 4
Dependent Claim
44 words
The method of claim 2, wherein step (d) further comprises the step of: calculating a time for which the power plant can supply power to the consumer equipment based upon the consumer equipment load value and the stored potential value of the power plant.
Claim 5
Dependent Claim
115 words
The method of claim 2, wherein step (d) further comprises the steps of: (a) generating a corrected load value of the consumer equipment by multiplying the consumer equipment load value by a load correction factor which exaggerates the consumer equipment load value; (b) generating a corrected stored potential value for the power plant by multiplying the stored potential value for the power plant by a power plant correction factor which understates the stored potential value for the power plant; and (c) calculating a time for which the power plant can supply power to the consumer equipment based upon the corrected load value of the consumer equipment and the corrected stored potential of the power plant.
Claim 6
Dependent Claim
84 words
A computerized method for remotely calculating a reserve time for which a power plant can provide power to consumer equipment, the method comprising the steps of: (1) retrieving a consumer equipment load value from a relational database; (2) retrieving UPS batter data associated with the power plant from a relational database; (3) calculating a stored potential value of the power plant based on the retrieved UPS data; and (4) calculating a time for which the power plant can supply power to the consumer equipment.
Claim 7
Dependent Claim
84 words
A computerized method for remotely calculating a reserve time for which a power plant can provide power to consumer equipment, the method comprising the steps of: (1) retrieving a consumer equipment load value from a relational database; (2) retrieving UPS batter data associated with the power plant from a relational database; (3) calculating a stored potential value of the power plant based on the retrieved UPS data; and (4) calculating a time for which the power plant can supply power to the consumer equipment.
Claim 8
Dependent Claim
44 words
The method of claim 5, wherein step (4) further comprises the step of: calculating a time for which the power plant can supply power to the consumer equipment based upon the consumer equipment load value and the stored potential value of the power plant.
Claim 9
Dependent Claim
136 words
The method of claim 5, wherein step (4) further comprises the steps of: (a) generating a corrected load value of the consumer equipment by multiplying a consumer equipment load value by a load correction factor which exaggerates the consumer equipment load value; (b) calculating a stored potential value of the power plant based on battery data associated with the power plant; (c) generating a corrected deliverable stored potential value for the power plant by multiplying the stored potential of the power plant by a power plant correction factor which understates the store potential value for the power plant; and (d) calculating a time for which the power plant can supply power to he consumer equipment, based upon the corrected load value of the consumer equipment and the corrected deliverable stored potential value for the power plant.
Claim 10
Dependent Claim
62 words
The method of claim 5, wherein step (1) further comprises the steps of: (a) retrieving the consumer equipment load value from a database; (b) permitting a user to edit the consumer equipment load value; and (c) generating a corrected consumer equipment load value by multiplying the consumer equipment load value by a load correction factor which exaggerates the consumer equipment load value.
Claim 11
Dependent Claim
61 words
The method of claim 5, wherein step (2) further comprises the steps of: (a) retrieving battery data associated with the power plant from a relational database; (b) permitting a user to edit the battery data associated with the power plant; and (c) calculating a stored potential value of the power plant based on battery data the associated with the power plant.
Claim 12
Dependent Claim
62 words
The method of claim 5, wherein step (2) further comprises the steps of: (a) retrieving battery data associated with the power plant from a site facility planner database; (b) denying users access to the battery data associated with the power plant; and (c) calculating a stored potential value of the power plant based on the battery data associated with the power plant.
Claim 13
Dependent Claim
136 words
A web-based general purpose computer system for remotely entering plan data into a database and for calculating a reserve time for which a power plant can provide power to consumer equipment, comprising: (a) a SiteVu power pages (SVPP) module comprising a data input module for receiving power plant data from users at remote workstations and for inputting receiving power plant data into a relational database and a calculation module for calculating reserve time for which a power plant can supply power to consumer equipment; (b) a web browser interface for interfacing users at remote workstations with said data input module and said calculation module; and (c) a power table relational database for receiving power plant data from said data input module and for providing power plant data to said calculation module for calculation of reserve times.
Claim 14
Dependent Claim
136 words
A web-based general purpose computer system for remotely entering plan data into a database and for calculating a reserve time for which a power plant can provide power to consumer equipment, comprising: (a) a SiteVu power pages (SVPP) module comprising a data input module for receiving power plant data from users at remote workstations and for inputting receiving power plant data into a relational database and a calculation module for calculating reserve time for which a power plant can supply power to consumer equipment; (b) a web browser interface for interfacing users at remote workstations with said data input module and said calculation module; and (c) a power table relational database for receiving power plant data from said data input module and for providing power plant data to said calculation module for calculation of reserve times.
Claim 15
Dependent Claim
39 words
The system for claim 11, wherein said data input module comprises means for inputting a consumer equipment load value into a site facility planning database and for inputting plant data and consumer equipment load values into said relational database.
Claim 16
Dependent Claim
39 words
The system of claim 11, wherein said data input module comprises means for editing consumer equipment load values in a site facility planning database and means for editing plant data and consumer equipment load values in said relational database.
Claim 17
Dependent Claim
28 words
The system of claim 11, wherein said power pages module further comprises means for querying a database for an entry associated with a site selected by a user.
Claim 18
Dependent Claim
52 words
The system of claim 14, wherein said means for querying a database includes means for querying a site facility planner database for an entry associated with a site selected by a user and means for querying said power tables relational database for an entry associated with a site selected by a user.
Claim 19
Dependent Claim
27 words
The system of claim 15, wherein said data input module comprises means for generating new entries in said relational database for new sites entered by a user.
Claim 20
Dependent Claim
115 words
The system of claim 11, wherein said relational database comprises: (a) a site table for storing data associated with sites; (b) a power plant table for storing data associated with power plants; (c) means for associating entries in said power plant table with entries in said site table; (d) a battery table for storing battery data associated with power plants; (e) means for associating entries in said battery table with entries in said power plant table; (f) one or more component tables for identifying components associated with power plants and sites; and (g) means for associating entries in said one or more component tables with entries in said power plant table and said site table.
Claim 21
Dependent Claim
101 words
The system of claim 17, wherein said one or more component tables comprise: (a) a rectifier table for storing rectifier data associated with power plants; (b) means for associating entries in said rectifier table with entries in said power plant table; (c) an uninterruptible power supply (UPS) table for storing uninterruptible power supply data associated with power plants; (d) means for associating entries in said UPS table with entries in said power plant table; (e) a generator table for storing generator data associated with sites; and (f) means for associating entries in said generator table with entries in said site table.