Improved liquefied natural gas fueled combined cycle power plant

Assignee: Engie Gas and LNG LLC
•
Filing: 1995-02-14
•
Granted: 1995-10-17
•
Expires: 2015-02-14
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A process and system which improves the capacity and efficiency of a combined cycle power plant. A LNG supply system fuels the combined cycle plant. Gasified LNG in a combustor mixes with the air from the air compressor to provide the hot combustion gas for the gas turbine. The expanding LNG is used to chill a primary heat exchange fluid, e.g. water, which primary heat exchange fluid cools and densifies the intake air for the air compressor. Subsequently, the primary heat exchange fluid is used to condense the spent steam discharged from the steam turbine. The primary heat exchange fluid is then re-chilled and recycled to cool and densify the intake air.

Inventors

  • 👤 Paul C. Johnson
  • 👤 A. Edwin Toombs

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-31 13:03
CPC Classifications
F; F17; F17C; F17C9/00; F17C9/02; F17C9/04; F01; F01K; F01K23/00; F01K23/02; F01K23/06; F01K23/10; F17C2221/00; F17C2221/03; F17C2221/032; F17C2221/033; F17C2223/00; F17C2223/01; F17C2223/0146; F17C2223/0153; F17C2223/0161; F17C2223/03; F17C2223/033; F17C2225/00; F17C2225/01; F17C2225/0107; F17C2225/0123; F17C2225/03; F17C2225/036; F17C2227/00; F17C2227/03; F17C2227/0302; F17C2227/0309; F17C2227/0316; F17C2265/00; F17C2265/05; F17C2265/07; F17C2270/00; F17C2270/05; F17C2270/0581; Y; Y02; Y02E; Y02E20/00; Y02E20/14; Y02E20/16

Claims Analysis

Total Claims: 20
Claim 1
Independent Claim 131 words
A method for enhancing the capacity and the efficiency of a combined cycle plant which comprises: regasifying LNG to convert to natural gas; chilling a primary heat exchange fluid by placing said primary heat exchange fluid in heat exchange relationship with a secondary heat exchange fluid which secondary heat exchange fluid is cooled by the conversion of the LNG to the natural gas; flowing the chilled primary heat exchange fluid through a heat exchange zone through which zone flows the intake air for an air compressor to cool and densify the intake air; flowing subsequently the primary heat exchange fluid through a condenser to condense the spent steam from a high-pressure steam turbine; and placing subsequently the primary heat exchange fluid in heat exchange relationship with the secondary heat exchange fluid.
Claim 2
Independent Claim 131 words
A method for enhancing the capacity and the efficiency of a combined cycle plant which comprises: regasifying LNG to convert to natural gas; chilling a primary heat exchange fluid by placing said primary heat exchange fluid in heat exchange relationship with a secondary heat exchange fluid which secondary heat exchange fluid is cooled by the conversion of the LNG to the natural gas; flowing the chilled primary heat exchange fluid through a heat exchange zone through which zone flows the intake air for an air compressor to cool and densify the intake air; flowing subsequently the primary heat exchange fluid through a condenser to condense the spent steam from a high-pressure steam turbine; and placing subsequently the primary heat exchange fluid in heat exchange relationship with the secondary heat exchange fluid.
Claim 3
Dependent Claim 53 words
The method of claim 1, which comprises: compressing the cooled densified air in the air compressor; mixing the regasified LNG with the compressed air in a combustor to form hot combustion gases; delivering the hot combustion gases to a gas turbine to drive the turbine; and discharging the exhaust gas from the turbine.
Claim 4
Dependent Claim 55 words
The method of claim 2, which comprises: flowing the exhaust gas from the gas turbine to a waste-heat boiler; flowing a liquid through the waste-heat boiler; placing the exhaust gas in heat exchange relationship with the liquid to convert the liquid to high pressure steam; and discharging the high pressure steam from the waste-heat boiler.
Claim 5
Dependent Claim 59 words
The method of claim 3, which comprises: flowing the high pressure steam to the steam turbine; discharging spent steam from the steam turbine; condensing the spent steam to form condensed water with the primary heat exchange fluid; chilling subsequently the primary heat exchange fluid by placing the primary heat exchange fluid in heat exchange relationship with the secondary fluid.
Claim 6
Dependent Claim 22 words
The method of claim 1 which comprises: improving the capacity of the combined cycle plant in an amount of up to 9%.
Claim 7
Independent Claim 21 words
The method of claims 1 or 5 which comprises: enhancing the efficiency of the combined cycle plant up to about 2%.
Claim 8
Independent Claim 295 words
A method for enhancing the capacity and efficiency of a combined cycle plant which combined cycle plant comprises a gas turbine plant, a waste-heat boiler, a steam turbine plant and a LNG supply system, the LNG supply system comprising a regasifier and a chiller in heat exchange relationship with one another which method comprises: regasifying the LNG in the regasifier to convert the same to natural gas; flowing a primary heat exchange fluid through the chiller; flowing a secondary heat exchange fluid between the regasifier and the chiller both to control the gasification of the LNG and the chilling of the primary heat exchange fluid; flowing the gasified LNG to a combustor in the gas turbine plant; flowing the chilled primary heat exchange fluid through a heat exchange zone through which zone flows the intake air for an air compressor in the gas turbine plant, the primary heat exchange fluid cooling and densifying the intake air; discharging the air from the air compressor and mixing the same with the gasified LNG in the combustor to generate hot combustion gases; flowing the hot combustion gases to a turbine in the gas turbine plant to drive the same; discharging hot exhaust gases from the turbine and flowing the same to the waste-heat boiler; convening liquid flowing through the waste-heat boiler to steam and discharging said steam; flowing the discharged stream to a steam turbine in the steam turbine plant to drive the same and to form spent steam; flowing the spent steam through a condenser; flowing the primary heat exchange fluid from the heat exchange zone upstream of the air compressor through the condenser to condense the spent steam; and flowing the primary heat exchange fluid from the condenser to the chiller in the LNG supply system.
Claim 9
Independent Claim 295 words
A method for enhancing the capacity and efficiency of a combined cycle plant which combined cycle plant comprises a gas turbine plant, a waste-heat boiler, a steam turbine plant and a LNG supply system, the LNG supply system comprising a regasifier and a chiller in heat exchange relationship with one another which method comprises: regasifying the LNG in the regasifier to convert the same to natural gas; flowing a primary heat exchange fluid through the chiller; flowing a secondary heat exchange fluid between the regasifier and the chiller both to control the gasification of the LNG and the chilling of the primary heat exchange fluid; flowing the gasified LNG to a combustor in the gas turbine plant; flowing the chilled primary heat exchange fluid through a heat exchange zone through which zone flows the intake air for an air compressor in the gas turbine plant, the primary heat exchange fluid cooling and densifying the intake air; discharging the air from the air compressor and mixing the same with the gasified LNG in the combustor to generate hot combustion gases; flowing the hot combustion gases to a turbine in the gas turbine plant to drive the same; discharging hot exhaust gases from the turbine and flowing the same to the waste-heat boiler; convening liquid flowing through the waste-heat boiler to steam and discharging said steam; flowing the discharged stream to a steam turbine in the steam turbine plant to drive the same and to form spent steam; flowing the spent steam through a condenser; flowing the primary heat exchange fluid from the heat exchange zone upstream of the air compressor through the condenser to condense the spent steam; and flowing the primary heat exchange fluid from the condenser to the chiller in the LNG supply system.
Claim 10
Dependent Claim 22 words
The method of claim 7 which comprises: placing the primary heat exchange fluid in indirect heat exchange relationship with the intake air.
Claim 11
Dependent Claim 13 words
The method of claim 7 wherein the primary heat exchange fluid is water.
Claim 12
Dependent Claim 30 words
The method of claim 9 wherein-the temperature of the water entering the chiller is approximately 95° F. and the temperature of the water exiting the chiller is about 35° F.
Claim 13
Dependent Claim 15 words
The method of claim 7 wherein the secondary heat exchange fluid is a water/glycol mixture.
Claim 14
Dependent Claim 24 words
The method of claim 11 wherein the water/glycol mixture enters the regasifier at about 70° F. and exits the gasifier at about 10° F.
Claim 15
Dependent Claim 39 words
The method of claim 11 wherein the temperature of the water/glycol entering the regasifier is about 70° F., the water/glycol mixture exiting the regasifier is about 10° F. and the natural gas exiting the regasifier is about 45° F.
Claim 16
Dependent Claim 22 words
The method of claim 7 which comprises: improving the capacity of the combined cycle plant in an amount of up to 9%.
Claim 17
Dependent Claim 19 words
The method of claim 7 which comprises: enhancing the efficiency of the combined cycle plant up to about 2%.
Claim 18
Dependent Claim 284 words
A LNG combined cycle plant system which comprises: a LNG fuel supply system which system includes: a source of LNG; a regasifier for the LNG in fluid flow communication with source of LNG; a chiller in heat exchange relationship with the regasifier; means to flow a secondary heat exchange fluid between the regasifier and the chiller to chill a primary heat exchange fluid; a gas turbine plant which comprises: an air compressor; an air intake duct upstream of said air compressor; a second heat exchanger disposed in heat exchange relationship with the air intake system; means to flow the primary heat exchange fluid through the heat exchanger to cool and densify the intake air flowing through the air duct and into the compressor; a gas turbine; a combuster interposed between the air compressor and the gas turbine, the combuster providing the energy to drive the gas turbine; a generator coupled to the gas turbine; and means to exhaust the gas from the gas turbine; a waste-heat boiler downstream of the gas turbine which comprises; means to introduce the exhaust gas from the gas turbine into the waste-gas boiler; means to create high pressure steam and means to discharge the high pressure steam from the waste-heat boiler; a steam turbine plant which comprises: a steam turbine downstream of and adapted to receive the high pressure steam from the waste-heat boiler; a generator coupled to and driven by the steam turbine; a condenser to condense the spent steam discharged from the steam turbine the primary heat exchange fluid flowing through the condenser; means to recycle the condensate to the waste-heat boiler; and means to flow the primary heat exchange fluid from the condenser to the chiller.
Claim 19
Dependent Claim 284 words
A LNG combined cycle plant system which comprises: a LNG fuel supply system which system includes: a source of LNG; a regasifier for the LNG in fluid flow communication with source of LNG; a chiller in heat exchange relationship with the regasifier; means to flow a secondary heat exchange fluid between the regasifier and the chiller to chill a primary heat exchange fluid; a gas turbine plant which comprises: an air compressor; an air intake duct upstream of said air compressor; a second heat exchanger disposed in heat exchange relationship with the air intake system; means to flow the primary heat exchange fluid through the heat exchanger to cool and densify the intake air flowing through the air duct and into the compressor; a gas turbine; a combuster interposed between the air compressor and the gas turbine, the combuster providing the energy to drive the gas turbine; a generator coupled to the gas turbine; and means to exhaust the gas from the gas turbine; a waste-heat boiler downstream of the gas turbine which comprises; means to introduce the exhaust gas from the gas turbine into the waste-gas boiler; means to create high pressure steam and means to discharge the high pressure steam from the waste-heat boiler; a steam turbine plant which comprises: a steam turbine downstream of and adapted to receive the high pressure steam from the waste-heat boiler; a generator coupled to and driven by the steam turbine; a condenser to condense the spent steam discharged from the steam turbine the primary heat exchange fluid flowing through the condenser; means to recycle the condensate to the waste-heat boiler; and means to flow the primary heat exchange fluid from the condenser to the chiller.
Claim 20
Dependent Claim 24 words
The system of claim 16 which includes: means to place the primary heat exchange fluid in indirect heat transfer relationship with the intake air.

References Cited (Backward Citations)

US3183666A Cited
US3726085A Cited
US3978663A Cited
US4036028A Cited
US4330998A Cited
US4422298A Cited
US4429536A Cited
US4953479A Cited
US4995234A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1998-10-16 1999-04-17 1999-10-17 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2002-10-16 2003-04-17 2003-10-17 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2006-10-16 2007-04-17 2007-10-17 $7700.00 Window Closed / Lapsed