US5291397A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Method for resource allocation and project control for the production of a product
Assignee: Individual
•
Filing: 1991-12-20
•
Granted: 1994-03-01
•
Expires: 2011-12-20
Abstract
Abstract A control system for the manufacture of a product is disclosed. A network of events and activities and a baseline schedule is constructed. Actual and predicted deviations to the baseline schedule, which are called slack variables, are used to predict the actual final completion date, using parallel processing. These slack variables are also used to selectively allocate resources to elements of the manufacturing process. Critical elements and critical dates are readily determined. The incremental cost of incremental schedule improvement can be readily determined. The current status of a project can be described in a single variable.
Inventors
- 👤 Roger A. Powell
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-03 17:34
CPC Classifications
G; G06; G06Q; G06Q10/00; G06Q10/06
Claims Analysis
Total Claims: 10
Claim 1
Independent Claim
462 words
A method for the manufacture of a product, comprising: generating a network of activities required to manufacture a product, estimating a time duration for each activity, choosing a desired final completion date for completion of manufacturing, calculating a baseline schedule date for the start of each activity, said baseline schedule date for the start of each prior activity being equal to the baseline schedule date for the start of the following activity in said network minus said estimated time duration of said prior activity, said desired final completion date being the last baseline schedule date in said network, entering said baseline schedule date corresponding to each said activity into a memory bank of a digital computer, identifying external components required to support each activity and entering external component identification and corresponding activity into said memory bank of said computer, determining an availability date for each said component and entering said availability date into said memory bank of said computer, calculating a external component slack value for each said component internally in said computer following programmed instructions, said component slack value being equal to the baseline schedule date for the start of the activity requiring said component minus the availability date of said component, said computer retrieving from said memory bank previously entered said baseline schedule date and said availability date for each said component, said computer storing said component slack values in said memory bank, determining said external component slack value that is most late, determining dates of actual start of said activities and entering said date of actual start into said memory bank of said computer, calculating an internal slack value for each activity having an actual start date internally in said computer following programmed instructions, said internal slack value being equal to said baseline schedule date for the start of said activity minus the actual start date of said activity, said computer retrieving from said memory bank previously entered said baseline schedule date and actual start date for each said activity, said computer storing said internal slack values in said memory bank, determining said internal slack value that is most late, determining the project most late slack value by comparing said most late component slack value and said most late internal slack value, determining a projected final completion date by subtracting the project most late slack value from said desired final completion date on said network, displaying said projected final completion date on an output device of said computer, manufacturing said product, said manufacturing applying resources to transform an article from an initial state into a different final state, allocating said resources in said manufacturing based on said external component slack values and said internal slack values, increasing resources allocated to external components and activities having most late slack values.
Claim 2
Independent Claim
462 words
A method for the manufacture of a product, comprising: generating a network of activities required to manufacture a product, estimating a time duration for each activity, choosing a desired final completion date for completion of manufacturing, calculating a baseline schedule date for the start of each activity, said baseline schedule date for the start of each prior activity being equal to the baseline schedule date for the start of the following activity in said network minus said estimated time duration of said prior activity, said desired final completion date being the last baseline schedule date in said network, entering said baseline schedule date corresponding to each said activity into a memory bank of a digital computer, identifying external components required to support each activity and entering external component identification and corresponding activity into said memory bank of said computer, determining an availability date for each said component and entering said availability date into said memory bank of said computer, calculating a external component slack value for each said component internally in said computer following programmed instructions, said component slack value being equal to the baseline schedule date for the start of the activity requiring said component minus the availability date of said component, said computer retrieving from said memory bank previously entered said baseline schedule date and said availability date for each said component, said computer storing said component slack values in said memory bank, determining said external component slack value that is most late, determining dates of actual start of said activities and entering said date of actual start into said memory bank of said computer, calculating an internal slack value for each activity having an actual start date internally in said computer following programmed instructions, said internal slack value being equal to said baseline schedule date for the start of said activity minus the actual start date of said activity, said computer retrieving from said memory bank previously entered said baseline schedule date and actual start date for each said activity, said computer storing said internal slack values in said memory bank, determining said internal slack value that is most late, determining the project most late slack value by comparing said most late component slack value and said most late internal slack value, determining a projected final completion date by subtracting the project most late slack value from said desired final completion date on said network, displaying said projected final completion date on an output device of said computer, manufacturing said product, said manufacturing applying resources to transform an article from an initial state into a different final state, allocating said resources in said manufacturing based on said external component slack values and said internal slack values, increasing resources allocated to external components and activities having most late slack values.
Claim 3
Independent Claim
390 words
A method for the manufacture of a product, comprising: generating a network of activities required to manufacture a product, estimating a time duration for each activity, choosing a desired final completion date for completion of manufacturing, calculating a baseline schedule date for the start of each said activity, said baseline schedule date for the start of each prior activity being equal to the baseline schedule date for the start of the following activity in said network minus said estimated time duration of said prior activity, said desired final completion date being the last baseline schedule date in said network, entering said baseline schedule date corresponding to each said activity into a memory bank of a digital computer, identifying external components required to support each activity and entering external component identification and corresponding activity into said memory bank of said computer, determining an availability date for each said component and entering said availability date into said memory bank of said computer, calculating a external component slack value for each said component internally in said computer following programmed instructions, said component slack value being equal to the baseline schedule date for the start of the activity requiring said component minus the availability date of said component, said computer retrieving from said memory bank previously entered said baseline schedule date and said availability date for each said component, said computer storing said component slack values in said memory bank, determining, for each activity, a most late external component slack value from among said component slack values for components required for said activity, determining, for each activity, an internal slack value for a most late internal constraint on beginning said activity, determining, for each activity, an activity most late slack value from among said most late external component slack value and said internal slack value, calculating a projected activity beginning date by subtracting said activity most late slack value from said baseline schedule date for the beginning of said activity, displaying said projected activity beginning date on an output device of said computer, manufacturing said product, said manufacturing applying resources to transform an article from an initial state into a different final state, allocating said resources in said manufacturing based on said external component slack values and said internal slack values, increasing resources allocated to external components and activities having most late slack values.
Claim 4
Independent Claim
390 words
A method for the manufacture of a product, comprising: generating a network of activities required to manufacture a product, estimating a time duration for each activity, choosing a desired final completion date for completion of manufacturing, calculating a baseline schedule date for the start of each said activity, said baseline schedule date for the start of each prior activity being equal to the baseline schedule date for the start of the following activity in said network minus said estimated time duration of said prior activity, said desired final completion date being the last baseline schedule date in said network, entering said baseline schedule date corresponding to each said activity into a memory bank of a digital computer, identifying external components required to support each activity and entering external component identification and corresponding activity into said memory bank of said computer, determining an availability date for each said component and entering said availability date into said memory bank of said computer, calculating a external component slack value for each said component internally in said computer following programmed instructions, said component slack value being equal to the baseline schedule date for the start of the activity requiring said component minus the availability date of said component, said computer retrieving from said memory bank previously entered said baseline schedule date and said availability date for each said component, said computer storing said component slack values in said memory bank, determining, for each activity, a most late external component slack value from among said component slack values for components required for said activity, determining, for each activity, an internal slack value for a most late internal constraint on beginning said activity, determining, for each activity, an activity most late slack value from among said most late external component slack value and said internal slack value, calculating a projected activity beginning date by subtracting said activity most late slack value from said baseline schedule date for the beginning of said activity, displaying said projected activity beginning date on an output device of said computer, manufacturing said product, said manufacturing applying resources to transform an article from an initial state into a different final state, allocating said resources in said manufacturing based on said external component slack values and said internal slack values, increasing resources allocated to external components and activities having most late slack values.
Claim 5
Independent Claim
321 words
A method for the manufacture of a product, comprising: generating a network of activities required to manufacture a product, estimating a time duration for each activity, choosing a desired final completion date for completion of manufacturing, calculating a baseline schedule date for the start of each said activity, said baseline schedule date for the start of each prior activity being equal to the baseline schedule date for the start of the following activity in said network minus said estimated time duration of said prior activity, said desired final completion date being the last baseline schedule date in said network, entering said baseline schedule date corresponding to each said activity into a memory bank of a digital computer, identifying external components required to support each activity and entering external component identification and corresponding activity into said memory bank of said computer, determining an availability date for each said component and entering said availability date into said memory bank of said computer, calculating an external component slack value for each said component internally in said computer following programmed instructions, said component slack value being equal to the baseline schedule date for the start of the activity requiring said component minus the availability date of said component, said computer retrieving from said memory bank previously entered said baseline schedule date and said availability date for each said component, said computer storing said component slack values in said memory bank, determining a most late external component slack value, calculating a projected final completion date by subtracting said most late component slack value from said desired final completion date, displaying said projected final completion date on an output device of said computer, manufacturing said product, said manufacturing applying resources to transform an article from an initial state into a different final state, allocating said resources in said manufacturing based on said external component slack values, increasing resources allocated to external components having most late slack values.
Claim 6
Independent Claim
321 words
A method for the manufacture of a product, comprising: generating a network of activities required to manufacture a product, estimating a time duration for each activity, choosing a desired final completion date for completion of manufacturing, calculating a baseline schedule date for the start of each said activity, said baseline schedule date for the start of each prior activity being equal to the baseline schedule date for the start of the following activity in said network minus said estimated time duration of said prior activity, said desired final completion date being the last baseline schedule date in said network, entering said baseline schedule date corresponding to each said activity into a memory bank of a digital computer, identifying external components required to support each activity and entering external component identification and corresponding activity into said memory bank of said computer, determining an availability date for each said component and entering said availability date into said memory bank of said computer, calculating an external component slack value for each said component internally in said computer following programmed instructions, said component slack value being equal to the baseline schedule date for the start of the activity requiring said component minus the availability date of said component, said computer retrieving from said memory bank previously entered said baseline schedule date and said availability date for each said component, said computer storing said component slack values in said memory bank, determining a most late external component slack value, calculating a projected final completion date by subtracting said most late component slack value from said desired final completion date, displaying said projected final completion date on an output device of said computer, manufacturing said product, said manufacturing applying resources to transform an article from an initial state into a different final state, allocating said resources in said manufacturing based on said external component slack values, increasing resources allocated to external components having most late slack values.
Claim 7
Dependent Claim
21 words
A method for the manufacture of a product as recited in claim 3, further comprising: choosing a project external slack goal.
Claim 8
Dependent Claim
52 words
A method for the manufacture of a product as recited in claim 4, further comprising: calculating critical dates for the start of each activity, said critical date for the start of an activity being equal to said baseline schedule date for the start of said activity minus said project external slack goal.
Claim 9
Independent Claim
298 words
A method for the manufacture of a product, comprising: generating a network of activities required to manufacture a product, estimating a time duration for each activity, choosing a desired final completion date for completion of manufacturing, calculating a baseline schedule date for the start of each said activity, said baseline schedule date for the start of each prior activity being equal to the baseline schedule date for the start of the following activity in said network minus said estimated time duration of said prior activity, said desired final completion date being the last baseline schedule date in said network, entering said baseline schedule date corresponding to each said activity into a memory bank of a digital computer, determining dates of actual start of said activities and entering said date of actual start into said memory bank of said computer, calculating an internal slack value for each activity having an actual start date internally in said computer following programmed instructions, said internal slack value being equal to said baseline schedule date for the start of said activity minus the actual start date of said activity, said computer retrieving from said memory bank previously entered said baseline schedule date and actual start date for each said activity, said computer storing said internal slack values in said memory bank, determining a most late internal slack value, calculating a projected final completion date by subtracting said most late internal slack value from said desired final completion date, displaying said projected final completion date on an output device of said computer, manufacturing said product, said manufacturing applying resources to transform an article from an initial state into a different final state, allocating said resources in said manufacturing based on said internal slack values, increasing resources allocated to activities having most late slack values.
Claim 10
Independent Claim
298 words
A method for the manufacture of a product, comprising: generating a network of activities required to manufacture a product, estimating a time duration for each activity, choosing a desired final completion date for completion of manufacturing, calculating a baseline schedule date for the start of each said activity, said baseline schedule date for the start of each prior activity being equal to the baseline schedule date for the start of the following activity in said network minus said estimated time duration of said prior activity, said desired final completion date being the last baseline schedule date in said network, entering said baseline schedule date corresponding to each said activity into a memory bank of a digital computer, determining dates of actual start of said activities and entering said date of actual start into said memory bank of said computer, calculating an internal slack value for each activity having an actual start date internally in said computer following programmed instructions, said internal slack value being equal to said baseline schedule date for the start of said activity minus the actual start date of said activity, said computer retrieving from said memory bank previously entered said baseline schedule date and actual start date for each said activity, said computer storing said internal slack values in said memory bank, determining a most late internal slack value, calculating a projected final completion date by subtracting said most late internal slack value from said desired final completion date, displaying said projected final completion date on an output device of said computer, manufacturing said product, said manufacturing applying resources to transform an article from an initial state into a different final state, allocating said resources in said manufacturing based on said internal slack values, increasing resources allocated to activities having most late slack values.
References Cited (Backward Citations)
US4208712A
Cited
US3703725A
Cited
US3845286A
Cited
US4089056A
Cited
US4027246A
Cited
US4648023A
Cited
US4827423A
Cited
US5128860A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1997-02-28 | 1997-08-30 | 1998-03-01 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 2001-02-28 | 2001-08-30 | 2002-03-01 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 2005-02-28 | 2005-08-30 | 2006-03-01 | $7700.00 | Window Closed / Lapsed |