Patent US5148668A successfully refreshed from Google Patents.
US5148668A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Combined gas/steam turbine power station plant
Assignee: Alstom SA
•
Filing: 1991-01-17
•
Granted: 1992-09-22
•
Expires: 2011-01-17
Abstract
Abstract In a gas/steam power station plant (combined plant) the gas turbine group (1, 2, 3), the steam circuit (8, 9) and the waste heat boiler (4), individually of in combination with one another, are connected, directly or indirectly, operationally to a steam accumulator (12). This operational connection is one wherein a proportion of steam from the constantly charged-up steam accumulator (12) is available for an autonomous start-up of at least one steam turbine (8, 9), coupled to the gas turbine group, of the steam circuit, whereby the start capability of the combined plant can be increased.
Inventors
- 👤 Hansulrich Frutschi
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-10-27 22:44
CPC Classifications
F; F01; F01K; F01K23/00; F01K23/02; F01K23/06; F01K23/10; F01K23/106; F01K21/00; F01K21/04; F01K21/042; F01K3/00; F01K3/02; Y; Y02; Y02E; Y02E20/00; Y02E20/16
Claims Analysis
Total Claims: 5
Claim 1
Independent Claim
193 words
A method for operating a gas/steam power plant wherein at least one steam turbine and at least one gas turbine drive an electrical generator comprising the steps of: supplying throttled steam from a steam reservoir to said at least one steam turbine for start-up of the gas/steam power plant; throttling said stem from said steam reservoir such that a start-up power of said at least one steam turbine is generated that is a fraction of a nominal output power of said at least one steam turbine blocking during start-up a supply of steam to said steam reservoir from a waste heat boiler that is positioned to receive exhaust gas of said at least one gas turbine; blocking at least during start-up a steam supply to a combustion chamber of said at least one gas turbine; gradually delivering and igniting air and fuel in said combustion chamber of said at least one gas turbine; and, switching the supply of steam to said at least one steam turbine from said steam reservoir to an evaporator bank of said waste heat boiler according to the attainment of a nominal rotary speed of said gas/steam power plant.
Claim 2
Independent Claim
193 words
A method for operating a gas/steam power plant wherein at least one steam turbine and at least one gas turbine drive an electrical generator comprising the steps of: supplying throttled steam from a steam reservoir to said at least one steam turbine for start-up of the gas/steam power plant; throttling said stem from said steam reservoir such that a start-up power of said at least one steam turbine is generated that is a fraction of a nominal output power of said at least one steam turbine blocking during start-up a supply of steam to said steam reservoir from a waste heat boiler that is positioned to receive exhaust gas of said at least one gas turbine; blocking at least during start-up a steam supply to a combustion chamber of said at least one gas turbine; gradually delivering and igniting air and fuel in said combustion chamber of said at least one gas turbine; and, switching the supply of steam to said at least one steam turbine from said steam reservoir to an evaporator bank of said waste heat boiler according to the attainment of a nominal rotary speed of said gas/steam power plant.
Claim 3
Dependent Claim
37 words
A method for operating a gas/steam power plant according to claim 1, wherein at least a portion of steam from said at least one steam turbine is supplied as coolant to said at least one gas turbine.
Claim 4
Dependent Claim
26 words
A method for operating a gas/steam power plant according to claim 1, wherein after start-up, the steam reservoir is re-charged with steam from said waste-heat boiler.
Claim 5
Dependent Claim
55 words
A method for operating a gas/steam power plant according to claim 1, wherein during start-up, throttled exhaust steam from said at least one steam turbine is supplied to an additional steam turbine section disposed downstream of said at least one steam turbine such that said throttled exhaust steam serves to cool said additional steam turbine.
References Cited (Backward Citations)
CH211358A
Cited
GB1173923A
Cited
US3747336A
Cited
US4353206A
Cited
JPS58160502A
Cited
DE3331153A1
Cited
JPS61255244A
Cited
US4893467A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1995-09-22 | 1996-03-23 | 1996-09-22 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1999-09-22 | 2000-03-23 | 2000-09-22 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 2003-09-22 | 2004-03-23 | 2004-09-22 | $7700.00 | Window Closed / Lapsed |