Applying a tapered electrode on a porous ceramic support tube by masking a band inside the tube and drawing in electrode material from the outside of the tube by suction
Assignee: Westinghouse Electric Corp
•
Filing: 1991-01-15
•
Granted: 1991-12-17
•
Expires: 2011-01-15
Abstract
Abstract An electrode is deposited on a support by providing a porous ceramic support tube (10) having an open end (14) and closed end (16); masking at least one circumferential interior band (18 and 18') inside the tube; evacuating air from the tube by an evacuation system (30), to provide a permeability gradient between the masked part (18 and 18') and unmasked part (20) of the tube; applying a liquid dispersion of solid electrode particles to the outside surface of the support tube, where liquid flows through the wall, forming a uniform coating (42) over the unmasked support part (20) and a tapered coating over the masked part (18 and 18').
Inventors
- 👤 Theodore R. Vasilow
- 👤 Gregory E. Zymboly
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-07 18:12
CPC Classifications
G; G01; G01N; G01N27/00; G01N27/26; G01N27/403; G01N27/406; G01N27/407; G01N27/4075; H; H01; H01M; H01M8/00; H01M8/04; B; B05; B05C; B05C3/00; B05C3/20; C; C04; C04B; C04B41/00; C04B41/45; C04B41/50; C04B41/5025; C04B41/80; C04B41/81; C04B41/85; C04B41/87; H01M4/00; H01M4/86; H01M4/8605; H01M4/8621; H01M4/88; H01M4/8825; H01M4/8846; H01M4/8878; H01M4/8882; H01M4/8885; H01M4/90; H01M4/9016; H01M8/02; H01M8/10; H01M8/12; H01M8/1213; H01M8/1226; H01M2004/8678; H01M2004/8684; H01M2008/1293; H01M2300/00; H01M2300/0017; H01M2300/0065; H01M2300/0068; H01M2300/0071; H01M2300/0074; H01M4/9025; H01M4/9033; Y; Y02; Y02E; Y02E60/00; Y02E60/30; Y02E60/50
Claims Analysis
Total Claims: 15
Claim 1
Independent Claim
187 words
A method of depositing a tapered electrode on a support tube comprising the steps: (1) providing a ceramic support tube, having a porous wall and two ends; (2) masking at least one circumferential band inside of the tube, where at least the inside of one end of the tube is masked, leaving at least one unmasked band inside of the tube; (3) evacuating air from inside of the tube, to provide a permeability gradation in the tube wall between masked and unmasked circumferential bands; (4) applying a liquid dispersion of solid electrode material particles to the outside surface of the evacuated tube, wherein liquid flows through the support tube wall, the particles coat a uniform deposit thickness on the outside surface over the unmasked inner bands of the tube where there is unrestricted liquid flow, and coat a tapered deposit thickness on the outside surface over at least part of the masked inner bands of the tube where there is restricted liquid flow, with the thinnest part of the taper near the ends of the support tube; and (5) sintering the applied deposit on the support tube.
Claim 2
Independent Claim
187 words
A method of depositing a tapered electrode on a support tube comprising the steps: (1) providing a ceramic support tube, having a porous wall and two ends; (2) masking at least one circumferential band inside of the tube, where at least the inside of one end of the tube is masked, leaving at least one unmasked band inside of the tube; (3) evacuating air from inside of the tube, to provide a permeability gradation in the tube wall between masked and unmasked circumferential bands; (4) applying a liquid dispersion of solid electrode material particles to the outside surface of the evacuated tube, wherein liquid flows through the support tube wall, the particles coat a uniform deposit thickness on the outside surface over the unmasked inner bands of the tube where there is unrestricted liquid flow, and coat a tapered deposit thickness on the outside surface over at least part of the masked inner bands of the tube where there is restricted liquid flow, with the thinnest part of the taper near the ends of the support tube; and (5) sintering the applied deposit on the support tube.
Claim 3
Dependent Claim
45 words
The method of claim 1, where the support tube comprises stabilized zirconia, the electrode particles comprise doped LaMnO 3 having a particle size of from 0.2 micrometer to 75 micrometers, and the dispersion is applied in step (4) by immersing the tube in the dispersion.
Claim 4
Dependent Claim
62 words
The method of claim 1, where the support tube has one closed end, is from 20% porous to 40% porous with an average pore size of from 1 micrometer to 3 micrometers, the electrode particles are ball milled with water and then added to water to form the dispersion, and where the inside masking in step (2) is near the closed end.
Claim 5
Dependent Claim
29 words
The method of claim 1, where the dispersion has a pH of from 7 to 8.5, and comprises from 1 wt. % to 20 wt. % electrode particle solids.
Claim 6
Dependent Claim
35 words
The method of claim 1, where the masking in step (2) is by applying to the circumferential band to be masked, a film of organic material which will burn off at temperatures below 900° C.
Claim 7
Dependent Claim
25 words
The method of claim 1, where the masking in step (2) is by sealingly engaging an inflated bladder to the circumferential band to be masked.
Claim 8
Dependent Claim
66 words
The method of claim 1, where the electrode particles are dispersed in water, and in step (4), liquid entering the evacuated support tube over the circumferential masking band will have restricted passage and travel substantially parallel to the support wall surface in order to flow through the porous support wall and will deposit less particles than liquid entering over the unmasked band which allows unrestricted flow.
Claim 9
Dependent Claim
31 words
The method of claim 1, including as final steps, application of a solid oxide electrolyte over most of the electrode deposit and then applying an outer cermet electrode over the electrolyte.
Claim 10
Dependent Claim
14 words
A support tube having a tapered electrode applied by the method of claim 1.
Claim 11
Independent Claim
215 words
A method of depositing a tapered electrode on a support tube comprising the steps: (1) providing a stabilized zirconia support tube, having a 20% porous to 40% porous wall, an open end and a closed end; (2) masking at least one circumferential band inside of the tube, where at least the inside of the closed end is masked, by sealingly engaging an inflated bladder to the circumferential band to be masked, leaving at least one unmasked band inside of the tube; (3) evacuating air from inside of the tube, to provide a permeability gradation in the tube wall between masked and unmasked circumferential bands; (4) applying an aqueous dispersion of solid, doped LaMnO 3 particles to the outside surface of the evacuated tube by immersing the tube in the dispersion, wherein water flows through the support tube wall, the particles coat a uniform deposit thickness on the outside surface over the unmasked inner bands of the tube where there is unrestricted liquid flow, and coat a tapered deposit thickness on the outside surface over at least part of the masked inner bands of the tube where there is restricted liquid flow, with the thinnest part of the taper near the ends of the support tube; and (5) sintering the applied deposit on the support tube.
Claim 12
Independent Claim
215 words
A method of depositing a tapered electrode on a support tube comprising the steps: (1) providing a stabilized zirconia support tube, having a 20% porous to 40% porous wall, an open end and a closed end; (2) masking at least one circumferential band inside of the tube, where at least the inside of the closed end is masked, by sealingly engaging an inflated bladder to the circumferential band to be masked, leaving at least one unmasked band inside of the tube; (3) evacuating air from inside of the tube, to provide a permeability gradation in the tube wall between masked and unmasked circumferential bands; (4) applying an aqueous dispersion of solid, doped LaMnO 3 particles to the outside surface of the evacuated tube by immersing the tube in the dispersion, wherein water flows through the support tube wall, the particles coat a uniform deposit thickness on the outside surface over the unmasked inner bands of the tube where there is unrestricted liquid flow, and coat a tapered deposit thickness on the outside surface over at least part of the masked inner bands of the tube where there is restricted liquid flow, with the thinnest part of the taper near the ends of the support tube; and (5) sintering the applied deposit on the support tube.
Claim 13
Dependent Claim
59 words
The method of claim 10, where the support tube has an average pore size of from 1 micrometer to 3 micrometers, the doped LaMnO 3 particles have a particle size from 0.2 micrometer to 75 micrometers, the dispersion has a pH of from 7 to 8.5, and the dispersion comprises from 1 wt. % to 20 wt. % solids
Claim 14
Dependent Claim
58 words
The method of claim 10, where in step (4), water entering the evacuated support tube over the circumferential masking band will have restricted passage and travel substantially parallel to the support wall surface in order to flow through the porous support wall and will deposit less particles than water entering over the unmasked band which allows unrestricted flow.
Claim 15
Dependent Claim
31 words
The method of claim 10, including as final steps, application of a solid oxide electrolyte over most of the electrode deposit and then applying an outer cermet electrode over the electrolyte.
References Cited (Backward Citations)
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1994-12-16 | 1995-06-17 | 1995-12-17 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1998-12-16 | 1999-06-17 | 1999-12-17 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 2002-12-16 | 2003-06-17 | 2003-12-17 | $7700.00 | Window Closed / Lapsed |