Claims Analysis
Total Claims: 16
Claim 1
Independent Claim
98 words
An arrangement for entrapping asbestos contaminated particles within a portion of a building, which comprises: a crawl space in the building having side walls, a ceiling, and an earthen floor with said ceiling being spaced from said earthen floor, a layer of asbestos contaminated particles located on top of said earthen floor and within said crawl space, and sealing means located on top of said layer of asbestos contaminated particles for sealing said layer of asbestos contaminated particles between said sealing means and said earthen floor, said sealing means including an impermeable membrane sealed to said side walls.
Claim 2
Dependent Claim
98 words
An arrangement for entrapping asbestos contaminated particles within a portion of a building, which comprises: a crawl space in the building having side walls, a ceiling, and an earthen floor with said ceiling being spaced from said earthen floor, a layer of asbestos contaminated particles located on top of said earthen floor and within said crawl space, and sealing means located on top of said layer of asbestos contaminated particles for sealing said layer of asbestos contaminated particles between said sealing means and said earthen floor, said sealing means including an impermeable membrane sealed to said side walls.
Claim 3
Dependent Claim
35 words
An arrangement for encapsulating asbestos contaminated particles as claimed in claim 1, wherein a layer of cementatious material is located with said layer of asbestos contaminated particles between said sealing means and said earthen floor.
Claim 4
Dependent Claim
38 words
An arrangement for encapsulating asbestos contaminated particles as claimed in claim 1, wherein a tube communicates with an area below said sealing means and the outside of said building for passage of gas trapped below said sealing means.
Claim 5
Dependent Claim
33 words
An arrangement for encapsulating asbestos contaminated particles as claimed in claim 1, wherein said impermeable membrane is stretchable so that workmen may walk on said impermeable layer without tearing of said impermeable layer.
Claim 6
Independent Claim
109 words
A method of encapsulating asbestos contaminated particles, said method comprising: providing an enclosed space of a building defined by side walls, a ceiling and an earthen floor, said ceiling being spaced from said earthen floor, said enclosed space including utility lines having asbestos contaminated particles, removing said asbestos contaminated particles from said utility lines with some of said asbestos contaminated particles settling in a layer on said earthen floor, and sealing said layer and said earthen floor with an impermeable membrane extending between and sealed to said side walls so as to prevent migration of said asbestos contaminated particles mixed with the earthen floor away from said earthen floor.
Claim 7
Independent Claim
109 words
A method of encapsulating asbestos contaminated particles, said method comprising: providing an enclosed space of a building defined by side walls, a ceiling and an earthen floor, said ceiling being spaced from said earthen floor, said enclosed space including utility lines having asbestos contaminated particles, removing said asbestos contaminated particles from said utility lines with some of said asbestos contaminated particles settling in a layer on said earthen floor, and sealing said layer and said earthen floor with an impermeable membrane extending between and sealed to said side walls so as to prevent migration of said asbestos contaminated particles mixed with the earthen floor away from said earthen floor.
Claim 8
Dependent Claim
41 words
A method of encapsulating asbestos contaminated particles as claimed in claim 5, wherein a layer of cementatious material is added to said layer of asbestos contaminated particles prior to sealing of said layer of asbestos contaminated particles and said earthen floor.
Claim 9
Dependent Claim
35 words
A method of encapsulating asbestos contaminated particles as claimed in claim 5, further comprising communicating an area which has been sealed with the exterior of said building to vent gas entrapped by said sealing step.
Claim 10
Independent Claim
106 words
A method of sealing asbestos contaminated particles located in a crawl space of a building having an earthen floor, said method comprising: disrupting the asbestos contaminated particles in the crawl space, allowing the asbestos contaminated particles to settle on said earthen floor, and covering said asbestos contaminated particles and said earthen floor with an impermeable membrane sealed to side walls of said crawl space at its periphery to prevent migration of said asbestos contaminated particles through or around said membrane so as to seal said asbestos contaminated particles and said earthen floor from said crawl space and thereby forming a new floor of said crawl space.
Claim 11
Independent Claim
106 words
A method of sealing asbestos contaminated particles located in a crawl space of a building having an earthen floor, said method comprising: disrupting the asbestos contaminated particles in the crawl space, allowing the asbestos contaminated particles to settle on said earthen floor, and covering said asbestos contaminated particles and said earthen floor with an impermeable membrane sealed to side walls of said crawl space at its periphery to prevent migration of said asbestos contaminated particles through or around said membrane so as to seal said asbestos contaminated particles and said earthen floor from said crawl space and thereby forming a new floor of said crawl space.
Claim 12
Dependent Claim
17 words
A method of sealing asbestos contaminated particles as claimed in claim 8, wherein said membrane is stretchable.
Claim 13
Dependent Claim
107 words
An arrangement for entrapping asbestos contaminated particles within a portion of a building which comprises: a crawl space in the building having side walls, and a ceiling, and an earthen floor with said ceiling being spaced from said earthen floor, a layer of asbestos contaminated particles located on top of said earthen and within said crawl space, and sealing means located on top of said layer of asbestos contaminated particles for sealing said layer of asbestos contaminated particles between said sealing means and said earthen floor, said sealing means including a stretchable, impermeable membrane of substantially uniform thickness sealed to said side walls by a sealing material.
Claim 14
Dependent Claim
107 words
An arrangement for entrapping asbestos contaminated particles within a portion of a building which comprises: a crawl space in the building having side walls, and a ceiling, and an earthen floor with said ceiling being spaced from said earthen floor, a layer of asbestos contaminated particles located on top of said earthen and within said crawl space, and sealing means located on top of said layer of asbestos contaminated particles for sealing said layer of asbestos contaminated particles between said sealing means and said earthen floor, said sealing means including a stretchable, impermeable membrane of substantially uniform thickness sealed to said side walls by a sealing material.
Claim 15
Independent Claim
119 words
A method of encapsulating asbestos contaminated particles, said method comprising: providing an enclosed space of a building defined by side walls, a ceiling and an earthen floor, said ceiling being spaced from said earthen floor, said enclosed space including utility lines covered by asbestos contaminated particles, removing said asbestos contaminated particles from said utility lines with some of said asbestos contaminated particles settling in a layer on said earthen floor, and covering said layer and said earthen floor with at least one section of an impermeable membrane of substantially uniform thickness extending between and sealed to said side walls so as to prevent migration of said asbestos contaminated particles mixed with the earthen floor away from said earthen floor.
Claim 16
Independent Claim
119 words
A method of encapsulating asbestos contaminated particles, said method comprising: providing an enclosed space of a building defined by side walls, a ceiling and an earthen floor, said ceiling being spaced from said earthen floor, said enclosed space including utility lines covered by asbestos contaminated particles, removing said asbestos contaminated particles from said utility lines with some of said asbestos contaminated particles settling in a layer on said earthen floor, and covering said layer and said earthen floor with at least one section of an impermeable membrane of substantially uniform thickness extending between and sealed to said side walls so as to prevent migration of said asbestos contaminated particles mixed with the earthen floor away from said earthen floor.