Patent US4886399A successfully refreshed from Google Patents.
← Back to Patent Explorer
US4886399A Expired / Lapsed US ⏱️ 0.0 years remaining

Method of constructing a foundation for buildings

Assignee: Individual
•
Filing: 1988-02-10
•
Granted: 1989-12-12
•
Expires: 2008-02-10
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method of constructing a foundation 10 for a building includes forming in the ground a grid 12 of intersecting foundation trenches 14, 16. The grid 12 is made up of two sets of substantially parallel trenches, the trenches of the sets being respectively designated 14 and 16, each trench 14, 16 of each set intersecting at least one trench of the other set. Settable material, eg concrete, is continuously cast within the trenches 14, 16 to obtain an integral grid 18 of two sets of intersecting foundation between 20 (in the trenches 16) and 22 (in the trenches (14). The spacing A between adjacent pairs of trenches 14 or 16 and between adjacent pairs of parallel beams 20 or 22 of the grid 18 is 1,5 meters. A covering of concrete is continuously cast over the beams 20 and 22 and integral therewith, to obtain a slab 24 (FIG. 3) covering the beams and the ground 26 between the beams 20 and 22, the slabs having a flat upper surface 28 (FIG. 3).

Inventors

  • 👤 John T. Pidgeon

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 08:39
CPC Classifications
E; E02; E02D; E02D27/00; E02D27/01; E02D27/02; E02D27/08

Claims Analysis

Total Claims: 16
Claim 1
Independent Claim 130 words
In a method of constructing a stiffened raft foundation for a building which includes forming in the ground a grid of intersecting foundation trenches, the grid being made up of two sets of substantially parallel trenches, each trench of each set intersecting at least one trench of the other set; continuously casting settable material within the trenches to obtain an integral grid of intersecting foundation beams; and continuously casting a covering of settable material over the beams and integral therewith, to obtain a slab covering the ground between the beams and having a flat upper surface, the improvement of forming the trenches such that the spacing between adjacent parallel beams of the grid is 1 to 2 meters, and the width of each foundation beam is 100 to 170 mm.
Claim 2
Dependent Claim 130 words
In a method of constructing a stiffened raft foundation for a building which includes forming in the ground a grid of intersecting foundation trenches, the grid being made up of two sets of substantially parallel trenches, each trench of each set intersecting at least one trench of the other set; continuously casting settable material within the trenches to obtain an integral grid of intersecting foundation beams; and continuously casting a covering of settable material over the beams and integral therewith, to obtain a slab covering the ground between the beams and having a flat upper surface, the improvement of forming the trenches such that the spacing between adjacent parallel beams of the grid is 1 to 2 meters, and the width of each foundation beam is 100 to 170 mm.
Claim 3
Dependent Claim 22 words
A method as claimed in claim 1 wherein the spacing between adjacent parallel trenches and beams of the grids is 1.3-1.7 meters.
Claim 4
Dependent Claim 30 words
A method as claimed in claim 2 wherein the vertical spacing from the bottom of each trench to the flat upper surface of the slab is 300 to 1500 mm.
Claim 5
Dependent Claim 17 words
A method as claimed in claim 3 wherein the thickness of the covering slab is 75-125 mm.
Claim 6
Dependent Claim 148 words
A method as claimed in claim 1 wherein forming the grid of intersecting foundation trenches is such that they are substantially rectangular in cross-section so that the cast beams each have a pair of laterally spaced vertical side faces and a horizontal lower face, the method including the step of reinforcing each foundation beam by embedding a reinforcing bar therein and by embedding a reinforcing bar in the slab above the beam at a position centrally above the beam, the bar in the beam extending parallel to the beam in the interior thereof along the length of the beam midway between the side faces of the beam, and the bar in the slab above the beam extending along the length of the beam parallel to the bar embedded in the beam, each bar being spaced by at least 50 mm from the outer surface of the cast foundation.
Claim 7
Dependent Claim 50 words
A method as claimed in claim 5 wherein each of the bars has a cross-section which has an area which is from 0.1-0.25% of the cross-sectional area of the beam below a level which is midway between the lower face of the beam and the upper surface of the slab.
Claim 8
Dependent Claim 72 words
A method as claimed in claim 1 which includes forming a boundary trench which defines the outer periphery of the foundation in plan view, each of the trenches of the grid of the foundation intersecting the boundary trench, the method including continuously casting settable material in the boundary trench to obtain a boundary beam in the boundary trench which is integral with the beams of the grid and integral with the slab.
Claim 9
Dependent Claim 56 words
A method as claimed in claim 7 wherein forming the boundary trench is such that a boundary beam made up of a plurality of straight portions at right angles to one another is obtained, which portions intercept one another in series at their ends to provide corners for the foundation when seen in plan view outline.
Claim 10
Dependent Claim 36 words
A method as claimed in claim 8 wherein forming the boundary trench is such that the portions of the boundary beam obtained are each parallel to one of the sets of parallel trenches of the grid.
Claim 11
Dependent Claim 34 words
A method as claimed in claim 8 wherein forming the boundary trench is such that none of said portions is obtained which is parallel to either of the sets of trenches of the grid.
Claim 12
Dependent Claim 62 words
A method as claimed in claim 10 wherein forming the boundary trench is such that each of said portions is inclined at an angle of 45° to the foundation trenches of the grid, and wherein forming the grid of intersecting foundation trenches is such that at least some of the foundation trenches intersect the boundary trench at the corners of the foundation.
Claim 13
Dependent Claim 25 words
A method as claimed in claim 1 wherein forming the grid of intersecting foundation trenches is effected by a means of a cable trenching machine.
Claim 14
Dependent Claim 119 words
In a stiffened raft foundation for a building, which foundation includes an integral grid of intersecting foundation beams of set settable material located within a grid of intersecting foundation trenches in the ground, the grid of foundation beams being made up of two sets of substantially parallel foundation beams, each beam of each set intersecting at least one beam of the other set; and a covering of settable material over the beams and integral therewith forming a slab covering the ground between the beams and having a flat upper surface, the improvement whereby the spacing between adjacent parallel beams of the grid is 1 to 2 meters, and the width of each foundation beam is 100 to 170 mm.
Claim 15
Dependent Claim 119 words
In a stiffened raft foundation for a building, which foundation includes an integral grid of intersecting foundation beams of set settable material located within a grid of intersecting foundation trenches in the ground, the grid of foundation beams being made up of two sets of substantially parallel foundation beams, each beam of each set intersecting at least one beam of the other set; and a covering of settable material over the beams and integral therewith forming a slab covering the ground between the beams and having a flat upper surface, the improvement whereby the spacing between adjacent parallel beams of the grid is 1 to 2 meters, and the width of each foundation beam is 100 to 170 mm.
Claim 16
Dependent Claim 11 words
A foundation when constructed by the method claimed in claim 1.

References Cited (Backward Citations)

FR1080764A Cited
US4089183A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1992-12-11 1993-06-12 1993-12-12 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1996-12-11 1997-06-12 1997-12-12 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2000-12-11 2001-06-12 2001-12-12 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag