Abstract
Abstract A fluidized bed calciner cooperating with a pulverized coal boiler includes a two tier fluidized lime cooling bed arrangement. Control of the combustion air flow through the fluidized bed calciner by means of a bypass achieves flexible operation and economy. The cooling beds transfer heat from the hot lime to the combustion air, and a bypass controls the temperature of the air flowing to the combustion chamber. The two tier arrangement is compact and adaptable to the retrofitting of a standardized pulverized coal boiler.
Inventors
- 👤 Melvin E. Murphy
- 👤 Wadie F. Gohara
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-04 07:50
CPC Classifications
B; B01; B01J; B01J8/00; B01J8/18; B01J8/1836; B01J8/24; B01J8/26; B01J8/28; C; C04; C04B; C04B2/00; C04B2/10; C04B2/106; F; F23; F23C; F23C10/00; F23C10/002; F23L; F23L15/00; B01J2208/00; B01J2208/00008; B01J2208/00017; B01J2208/00106; B01J2208/00168; B01J2208/00176; B01J2208/00265; B01J2208/00274; B01J2208/0053; Y; Y02; Y02E; Y02E20/00; Y02E20/34
Claims Analysis
Total Claims: 8
Claim 1
Independent Claim
198 words
A fluidized bed calciner operating with a coal fired boiler comprising: a fluidized bed combustion chamber wherein coal is burned and hot flue gases and lime are produced; a first fluidized lime cooler bed adjacent said combustion chamber including means for receiving lime produced in said combustion chamber and means for supplying air to fluidize said fluidized bed combustion chamber; a second fluidized lime cooler bed adjacent said first fluidized lime cooler bed including means for receiving lime from said first fluidized lime cooler bed and means for supplying air to fluidize said first fluidized lime cooler bed; a windbox adjacent said second fluidized lime cooler bed for supplying air to fluidize said second fluidized lime cooler bed; air suply means for supplying air to said windbox; bypass means for selectively circulating a portion of said air from said air supply means to fluidize said first fluidized lime cooler bed, said bypass means having steam coil heating means for selectively heating said air supplied to said first fluidized lime cooler bed; first-removal means for removing lime from said second fluidized lime cooler bed; and, second removal means for separately removing combustion by-products from said fluidized bed combustion chamber.
Claim 2
Dependent Claim
198 words
A fluidized bed calciner operating with a coal fired boiler comprising: a fluidized bed combustion chamber wherein coal is burned and hot flue gases and lime are produced; a first fluidized lime cooler bed adjacent said combustion chamber including means for receiving lime produced in said combustion chamber and means for supplying air to fluidize said fluidized bed combustion chamber; a second fluidized lime cooler bed adjacent said first fluidized lime cooler bed including means for receiving lime from said first fluidized lime cooler bed and means for supplying air to fluidize said first fluidized lime cooler bed; a windbox adjacent said second fluidized lime cooler bed for supplying air to fluidize said second fluidized lime cooler bed; air suply means for supplying air to said windbox; bypass means for selectively circulating a portion of said air from said air supply means to fluidize said first fluidized lime cooler bed, said bypass means having steam coil heating means for selectively heating said air supplied to said first fluidized lime cooler bed; first-removal means for removing lime from said second fluidized lime cooler bed; and, second removal means for separately removing combustion by-products from said fluidized bed combustion chamber.
Claim 3
Dependent Claim
36 words
A fluidized bed calciner as set forth in claim 1 wherein said windbox, said first and second fluidized lime cooler beds, and said combustion chamber all lay in a vertically stacked arrangement relative to each other.
Claim 4
Dependent Claim
226 words
A fluidized bed calciner operating with a coal fired boiler comprising: a fluidized bed combustion chamber wherein coal is burned and hot flue gases and lime are produced; a first fluidized lime cooler bed adjacent said combustion chamber including means for receiving lime produced in said combustion chamber and means for supplying air to fluidize said fluidized bed combustion chamber; a second fluidized lime cooler bed adjacent said first fluidized lime cooler bed including means for receiving lime from said first fluidized lime cooler bed and means for supplying air to fluidize said first fluidized lime cooler bed; a windbox adjacent said second fluidized lime cooler bed for supplying air to fluidize said second fluidized lime cooler bed, said windbox, said first and second fluidized lime cooler beds, and said combustion chamber all lying in a vertically stacked arrangement relative to each other; air supply means for supplying air to said windbox; bypass means for selectively circulating a portion of said air from said air supply means to fluidize said first fluidized lime cooler bed, said bypass means having heating means comprising a steam coil air heater for heating said air supplied to said first fluidized lime cooler bed; first removal means for removing lime from said second fluidized lime cooler bed; and, second removal means for removing combustion by-products from said fluidized bed combustion chamber.
Claim 5
Dependent Claim
226 words
A fluidized bed calciner operating with a coal fired boiler comprising: a fluidized bed combustion chamber wherein coal is burned and hot flue gases and lime are produced; a first fluidized lime cooler bed adjacent said combustion chamber including means for receiving lime produced in said combustion chamber and means for supplying air to fluidize said fluidized bed combustion chamber; a second fluidized lime cooler bed adjacent said first fluidized lime cooler bed including means for receiving lime from said first fluidized lime cooler bed and means for supplying air to fluidize said first fluidized lime cooler bed; a windbox adjacent said second fluidized lime cooler bed for supplying air to fluidize said second fluidized lime cooler bed, said windbox, said first and second fluidized lime cooler beds, and said combustion chamber all lying in a vertically stacked arrangement relative to each other; air supply means for supplying air to said windbox; bypass means for selectively circulating a portion of said air from said air supply means to fluidize said first fluidized lime cooler bed, said bypass means having heating means comprising a steam coil air heater for heating said air supplied to said first fluidized lime cooler bed; first removal means for removing lime from said second fluidized lime cooler bed; and, second removal means for removing combustion by-products from said fluidized bed combustion chamber.
Claim 6
Dependent Claim
76 words
A fluidized bed calciner as set forth in claim 3 further comprising: first bubble caps in said first lime cooler bed; second bubble caps in said second fluidized lime cooler bed; and, third bubble caps in said fluidized bed combustion chamber wherein said second fluidized lime cooler bed acts as a manifold for said first fluidized lime cooler bed, and said first fluidized lime cooler bed acts as a manifold for said fluidized bed combustion chamber.
Claim 7
Dependent Claim
82 words
A fluidized bed calciner as set forth in claim 4 further comprising: a first lime drain for draining lime from said fluidized bed combustion chamber to said first fluidized lime cooler bed; a second lime drain for draining lime from said first fluidized lime cooler bed to said second fluidized lime cooler bed; a third lime drain for draining lime from said second fluidized lime cooler bed; and, a combustion by-products drain for draining combustion by-products from said fluidized bed combustion chamber.
Claim 8
Dependent Claim
50 words
A fluidized bed calciner as set forth in claim 5 further comprising a hot dust collector for collecting lime dust in said flue gases from said fluidized bed combustion chamber and directing said collected lime dust to storage and directing said flue gases and uncollected lime dust to said boiler.
References Cited (Backward Citations)
US3009513A
Cited
US3814176A
Cited
US4250839A
Cited
US4303023A
Cited
US4343246A
Cited
US4427053A
Cited
US4476816A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1989-11-17 | 1990-05-19 | 1990-11-18 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1993-11-17 | 1994-05-19 | 1994-11-18 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1997-11-17 | 1998-05-19 | 1998-11-18 | $7700.00 | Window Closed / Lapsed |