Claim 1
Independent Claim
93 words
A rockbolt for installation in a bore in the roof of an underground excavation to support the roof, comprising: a sleeve insertable into the bore having an upper and a lower end and means for defining at least one port in the sleeve near the upper end; a plunger in the sleeve sealingly engaging the sleeve but slideable in response to applied fluid pressure; hardenable binder material in the sleeve between the port and the plunger and; means for applying fluid pressure to the plunger to extrude the binder material from the port.
Claim 2
Dependent Claim
93 words
A rockbolt for installation in a bore in the roof of an underground excavation to support the roof, comprising: a sleeve insertable into the bore having an upper and a lower end and means for defining at least one port in the sleeve near the upper end; a plunger in the sleeve sealingly engaging the sleeve but slideable in response to applied fluid pressure; hardenable binder material in the sleeve between the port and the plunger and; means for applying fluid pressure to the plunger to extrude the binder material from the port.
Claim 3
Dependent Claim
30 words
The rockbolt of claim 1 wherein the means for applying fluid pressure comprises means for connecting the portion of the sleeve below the plunger to a source of pressurized fluid.
Claim 4
Dependent Claim
20 words
The rockbolt of claim 1 further comprising means for engaging the sleeve, near the lower end, to the roof face.
Claim 5
Dependent Claim
34 words
The rockbolt of claim 3 wherein the means for engaging the sleeve to the roof face comprises means near the lower end of the sleeve for engaging a face plate engaging the roof face.
Claim 6
Dependent Claim
48 words
The rockbolt of claim 3 wherein the means for engaging the sleeve to the roof face comprises the threaded collar on the sleeve near the lower end and a nut threadingly engaged on the threaded collar and projecting sufficiently to engage a face plate engaging the roof face.
Claim 7
Dependent Claim
22 words
The rockbolt of claim 3 further comprising means for engaging the sleeve near the upper end, to the rock surrounding the bore.
Claim 8
Dependent Claim
28 words
The rockbolt of claim 6 wherein the means for engaging the sleeve to the rock surrounding the bore comprises an expandable anchor on the top of the sleeve.
Claim 9
Dependent Claim
41 words
The rockbolt of claim 6 further comprising means for tensioning the sleeve between the means for engaging the sleeve to the roof face and the means for engaging the sleeve to the rock surrounding the bore, to compress the rock therebetween.
Claim 10
Dependent Claim
41 words
The rockbolt of claim 1 further comprising a seal above the port, said seal engaging the surrounding rock when the rockbolt is installed in the bore and preventing upward travel of the binder material upon the binder extrusion from the sleeve.
Claim 11
Dependent Claim
18 words
The rockbolt of claim 1 wherein the hardenable binder materials is contained in at least one burstable cartridge.
Claim 12
Dependent Claim
35 words
The rockbolt of claim 9 wherein the hardenable binder comprises at least two components which form the hardenable binder material when mixed, and wherein the components are separately encapsulated in at least one burstable cartridge.
Claim 13
Dependent Claim
21 words
The rockbolt of claim 11 further comprising means for cutting the burstable cartridge and mixing the binder components in the sleeve.
Claim 14
Dependent Claim
42 words
The rockbolt of claim 12 wherein the means for cutting the burstable cartridge and mixing the components comprises a generally cylindrical tube with a chamfered bottom edge for cutting and a plurality of ports on the side of the tube for mixing.
Claim 15
Dependent Claim
78 words
The rockbolt of claim 1 wherein the hardenable binder material includes some binder material of appreciably faster setting time than the balance of the binder material, and wherein this faster setting binder material is below the balance of the binder material in the sleeve so that it is extruded last and remains near the upper end of the sleeve to secure the upper end of the sleeve in the bore before the balance of the binder material sets.
Claim 16
Dependent Claim
146 words
A rockbolt for installation in a bore in the roof of an underground excavation to support the roof, comprising: a sleeve insertable into the bore having an upper end and a lower end and means for defining at least one port in the sleeve near the upper end; a plunger in the sleeve sealingly engaging the sleeve but slideable in response to applied fluid pressure; hardenable binder material comprised of at least two components which form a hardenable binder material when mixed, separately encapsulated in at least one burstable cartridge, in the sleeve between the port and the plunger; means for connecting the portion of the sleeve below the plunger to a source of pressurized fluid to operate the plunger to extrude the binder material and encase the sleeve in the bore; and, means for engaging the sleeve, near the lower end, to the roof face.
Claim 17
Dependent Claim
146 words
A rockbolt for installation in a bore in the roof of an underground excavation to support the roof, comprising: a sleeve insertable into the bore having an upper end and a lower end and means for defining at least one port in the sleeve near the upper end; a plunger in the sleeve sealingly engaging the sleeve but slideable in response to applied fluid pressure; hardenable binder material comprised of at least two components which form a hardenable binder material when mixed, separately encapsulated in at least one burstable cartridge, in the sleeve between the port and the plunger; means for connecting the portion of the sleeve below the plunger to a source of pressurized fluid to operate the plunger to extrude the binder material and encase the sleeve in the bore; and, means for engaging the sleeve, near the lower end, to the roof face.
Claim 18
Dependent Claim
51 words
The rockbolt of claim 15 further comprising means for engaging the sleeve, near the upper end, to the rock surrounding the bore and means for tensioning the sleeve between the means for engaging the rock surrounding the bore and the means for engaging the roof face to compress the rock therebetween.
Claim 19
Independent Claim
97 words
A method for supporting the roof of an underground excavation, comprising: making a bore in the roof of the excavation; inserting into the bore a sleeve having an upper and a lower end and means for defining at least one port in the sleeve near the upper end, the sleeve containing a plunger sealingly engaging the sleeve but slideable in response to applied fluid pressure, the sleeve further containing hardenable binder material between the port and the plunger; and, apply fluid pressure to the plunger to extrude the binder material to encase the sleeve in the bore.
Claim 20
Independent Claim
97 words
A method for supporting the roof of an underground excavation, comprising: making a bore in the roof of the excavation; inserting into the bore a sleeve having an upper and a lower end and means for defining at least one port in the sleeve near the upper end, the sleeve containing a plunger sealingly engaging the sleeve but slideable in response to applied fluid pressure, the sleeve further containing hardenable binder material between the port and the plunger; and, apply fluid pressure to the plunger to extrude the binder material to encase the sleeve in the bore.
Claim 21
Dependent Claim
39 words
The method of claim 17 wherein the step of applying fluid pressure to the plunger comprises connecting the portion of the sleeve below the plunger to a source of pressurized fluid to operate the plunger to extrude binder material.
Claim 22
Dependent Claim
28 words
The method of claim 18 further including the step of tensioning the sleeve to compress the rock between the upper and lower ends before extruding the binder material.
Claim 23
Dependent Claim
28 words
The method of claim 17 further including the step of tensioning the sleeve to compress the rock between its upper end lower ends after extruding the binder material.
Claim 24
Dependent Claim
98 words
The method of claim 17 wherein a portion of the hardenable binder material in the sleeve has an appreciably faster setting time than the balance of the binder material and wherein the faster setting binder material is below the balance of the binder material in the sleeve so that it is extruded last and remains near the top of the sleeve, the method further comprising the step of tensioning the sleeve to compress the rock between its upper and lower ends after the fast setting binder material has set but before the rest of the binder material sets.
Claim 25
Independent Claim
175 words
A method for supporting the roof of an underground excavation, comprising: making a bore in the roof of the excavation; inserting into the bore a sleeve having an upper and an lower end, and means for defining at least one port in the sleeve near the upper end, the sleeve containing a plunger sealingly engaging the sleeve but slideable in response to applied fluid pressure, the sleeve further containing hardenable binder material between the port and the plunger, means for engaging the sleeve near the lower end to the roof face, and means for engaging the sleeve near the upper end to the rock surrounding the bore; engaging the upper end of the sleeve to the rock surrounding the bore and the lower end of the sleeve to the roof face; tensioning the sleeve to compress the rock between the upper and lower ends of the sleeve; connecting the portion of the sleeve below the plunger to a source of pressurized fluid to operate the plunger to extrude the binder material to encase the sleeve.
Claim 26
Independent Claim
175 words
A method for supporting the roof of an underground excavation, comprising: making a bore in the roof of the excavation; inserting into the bore a sleeve having an upper and an lower end, and means for defining at least one port in the sleeve near the upper end, the sleeve containing a plunger sealingly engaging the sleeve but slideable in response to applied fluid pressure, the sleeve further containing hardenable binder material between the port and the plunger, means for engaging the sleeve near the lower end to the roof face, and means for engaging the sleeve near the upper end to the rock surrounding the bore; engaging the upper end of the sleeve to the rock surrounding the bore and the lower end of the sleeve to the roof face; tensioning the sleeve to compress the rock between the upper and lower ends of the sleeve; connecting the portion of the sleeve below the plunger to a source of pressurized fluid to operate the plunger to extrude the binder material to encase the sleeve.
Claim 27
Independent Claim
198 words
A method for supporting the roof of an underground excavation, comprising: making a bore in the roof of the excavation; inserting into the bore a sleeve having an upper and a lower end and a means for defining at least one port in the sleeve near the upper end, the sleeve containing a plunger sealingly engaging the sleeve but slideable in response to applied fluid pressure, the sleeve further containing hardenable binder material between the port and the plunger, a portion of this binder material being of appreciably faster setting time than the balance of the binder material, the faster setting binder material being below the balance of the binder material in the sleeve so that it would be extruded last and would remain near the top of the sleeve, and means for engaging the sleeve, near the lower end, to the roof face; connecting the portion of the sleeve below the plunger to a source of pressurized fluid to operate the plunger to extrude the binder material; tensioning the sleeve after the faster setting binder material has set but before the balance of the binder material sets, to compress the rock between the upper and lower ends.
Claim 28
Independent Claim
198 words
A method for supporting the roof of an underground excavation, comprising: making a bore in the roof of the excavation; inserting into the bore a sleeve having an upper and a lower end and a means for defining at least one port in the sleeve near the upper end, the sleeve containing a plunger sealingly engaging the sleeve but slideable in response to applied fluid pressure, the sleeve further containing hardenable binder material between the port and the plunger, a portion of this binder material being of appreciably faster setting time than the balance of the binder material, the faster setting binder material being below the balance of the binder material in the sleeve so that it would be extruded last and would remain near the top of the sleeve, and means for engaging the sleeve, near the lower end, to the roof face; connecting the portion of the sleeve below the plunger to a source of pressurized fluid to operate the plunger to extrude the binder material; tensioning the sleeve after the faster setting binder material has set but before the balance of the binder material sets, to compress the rock between the upper and lower ends.