Patent US4487166A successfully refreshed from Google Patents.
US4487166A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Start-up system for once-through boilers
Assignee: Babcock and Wilcox Co
•
Filing: 1983-09-12
•
Granted: 1984-12-11
•
Expires: 2003-09-12
Abstract
Abstract A start-up system for once-through boilers including the reduction of minimum flow during start-up to 15% full load by the use of multi-lead internal ribbed tubing to the enclosure tubes in the high heat input zones, the use of a variable pressure by-pass stop valve in the main flow path, a pressure reducing means in the by-pass system and two steam spray attemperators from the flash tank or separators. The first steam attemperation is to the outlet of the secondary superheater and the second to the outlet of the reheater.
Inventors
- 👤 Kurt H. Haller
- 👤 Carl Lieb
- 👤 Pete G. Todoroff
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-05 07:44
CPC Classifications
F; F22; F22B; F22B35/00; F22B35/06; F22B35/14
Claims Analysis
Total Claims: 2
Claim 1
Independent Claim
141 words
In combination with a power plant system having a main once-through fluid flow path connected in series with furnace enclosure tubular means, primary and secondary superheaters, high and low pressure turbine means with a reheater connected therebetween, the improvement comprising utilization of multi-lead ribbed tubing as the tubular means whereby minimum start-up flow is reduced to approximately 15 percent of full load flow, a start-up system including a flash tank, valve means interposed between the primary and secondary superheater and in parallel with the main flow path whereby the transition from operation through the start-up system to flow through the main flow path is accomplished without fluctuation in steam temperature and wherein the valve means provide supercritical pressure upstream of the primary superheater outlet and variable pressure downstream of the secondary superheater inlet over the greater portion of the load range.
Claim 2
Dependent Claim
141 words
In combination with a power plant system having a main once-through fluid flow path connected in series with furnace enclosure tubular means, primary and secondary superheaters, high and low pressure turbine means with a reheater connected therebetween, the improvement comprising utilization of multi-lead ribbed tubing as the tubular means whereby minimum start-up flow is reduced to approximately 15 percent of full load flow, a start-up system including a flash tank, valve means interposed between the primary and secondary superheater and in parallel with the main flow path whereby the transition from operation through the start-up system to flow through the main flow path is accomplished without fluctuation in steam temperature and wherein the valve means provide supercritical pressure upstream of the primary superheater outlet and variable pressure downstream of the secondary superheater inlet over the greater portion of the load range.
References Cited (Backward Citations)
US3255735A
Cited
US3304716A
Cited
US3362164A
Cited
US3882680A
Cited
US3789805A
Cited
US4344338A
Cited
US4262636A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1987-12-11 | 1988-06-11 | 1988-12-11 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1991-12-11 | 1992-06-11 | 1992-12-11 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1995-12-11 | 1996-06-11 | 1996-12-11 | $7700.00 | Window Closed / Lapsed |