Claims Analysis
Total Claims: 4
Claim 1
Independent Claim
408 words
The method of making field installed insulated and shrouded pipe joints comprising the steps of: a. providing first and second lengths of insulated and shrouded pipe, each having an end to be joined to an end of the other length with the ends disposed at an angle to one another, the length comprising an inner pipe, an envelope of rigid foamed insulation surrounding the inner pipe and an outer protective shroud surrounding the envelope of insulation, b. projecting the inner pipe beyond the end of the envelope of insulation and beyond an end of the shroud, c. providing an angle pipe fitting having first and second ends disposed at an angle to one another adapted to be connected to the ends of the lengths, d. welding a first end of one of the lengths to a first end of the fitting, e. providing a fitting shroud having first and second ends spaced apart less than the spacing of the ends of said outer shrouds from one another when said lengths are attached to said fitting, said fitting shroud having a shape adapted to receive the fitting interiorly thereof and an inner diameter greater than the outer diameter of the fitting, f. inserting the fitting into the fitting shroud and beyond the weld of the first end to a point where the second end of the fitting projects beyond the fitting shroud, g. welding a first end of the other of the first and second lengths to the second end of the fitting, h. centering the fitting shroud in spaced relation around the fitting with the first and second ends of the fitting shroud spaced from the ends of the envelope of insulation and the end of the shroud of the first and second lengths to provide gaps between the fitting shroud and said ends of said first and second lengths, i. attaching mold members to the fitting shroud and length shrouds spanning and enclosing the gaps, at least one mold member having a filling orifice, j. flowing a settable foaming insulation material in a non-set state through said orifice and into the area between the fitting shroud and fitting and into the gaps, k. setting the foaming material and filling the area and gaps with foamed insulation, l. removing the mold members and exposing the foamed insulation in the gaps, m. and thereafter enclosing the foamed gaps with protective material which overlaps the fitting shroud and length shrouds.
Claim 2
Independent Claim
408 words
The method of making field installed insulated and shrouded pipe joints comprising the steps of: a. providing first and second lengths of insulated and shrouded pipe, each having an end to be joined to an end of the other length with the ends disposed at an angle to one another, the length comprising an inner pipe, an envelope of rigid foamed insulation surrounding the inner pipe and an outer protective shroud surrounding the envelope of insulation, b. projecting the inner pipe beyond the end of the envelope of insulation and beyond an end of the shroud, c. providing an angle pipe fitting having first and second ends disposed at an angle to one another adapted to be connected to the ends of the lengths, d. welding a first end of one of the lengths to a first end of the fitting, e. providing a fitting shroud having first and second ends spaced apart less than the spacing of the ends of said outer shrouds from one another when said lengths are attached to said fitting, said fitting shroud having a shape adapted to receive the fitting interiorly thereof and an inner diameter greater than the outer diameter of the fitting, f. inserting the fitting into the fitting shroud and beyond the weld of the first end to a point where the second end of the fitting projects beyond the fitting shroud, g. welding a first end of the other of the first and second lengths to the second end of the fitting, h. centering the fitting shroud in spaced relation around the fitting with the first and second ends of the fitting shroud spaced from the ends of the envelope of insulation and the end of the shroud of the first and second lengths to provide gaps between the fitting shroud and said ends of said first and second lengths, i. attaching mold members to the fitting shroud and length shrouds spanning and enclosing the gaps, at least one mold member having a filling orifice, j. flowing a settable foaming insulation material in a non-set state through said orifice and into the area between the fitting shroud and fitting and into the gaps, k. setting the foaming material and filling the area and gaps with foamed insulation, l. removing the mold members and exposing the foamed insulation in the gaps, m. and thereafter enclosing the foamed gaps with protective material which overlaps the fitting shroud and length shrouds.
Claim 3
Dependent Claim
209 words
The method of claim 1, including the additional steps of: providing a T-shaped fitting, providing a third length of insulated shrouded pipe, the fitting shroud being provided with an inner diameter greater than the outer diameter of the shroud of at least one of the lengths, sliding the fitting shroud over the shroud of the said one of the lengths subsequent to welding the first end of said one of the lengths to expose an opposite third end of said fitting projecting beyond an end of the fitting shroud, welding the third end of said fitting to an end of said third length, repositioning said fitting shroud over said fitting to project the second end of the fitting beyond the second end of the fitting shroud, welding the second end of the fitting to the first end of said other of the first and second lengths, centering the fitting shroud in spaced relation around the fitting with the first, second and third ends of the fitting shrouds spaced from the end of the envelope of insulation and end of the shroud of the first, second and third lengths to provide three gaps, attaching three mold members to the fitting shroud and length shrouds spanning and enclosing the three gaps.
Claim 4
Dependent Claim
18 words
The method of claim 2, wherein the steps of flowing, setting, removing and enclosing include all three gaps.