Apparatus for and method of monitoring for breached fuel elements

Assignee: ENERGY United States, Department of
•
Filing: 1981-04-28
•
Granted: 1983-11-15
•
Expires: 2001-04-28
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract This invention teaches improved apparatus for the method of detecting a breach in cladded fuel used in a nuclear reactor. The detector apparatus uses a separate bypass loop for conveying part of the reactor coolant away from the core, and at least three separate delayed-neutron detectors mounted proximate this detector loop. The detectors are spaced apart so that the coolant flow time from the core to each detector is different, and these differences are known. The delayed-neutron activity at the detectors is a function of the dealy time after the reaction in the fuel until the coolant carrying the delayed-neutron emitter passes the respective detector. This time delay is broken down into separate components including an isotopic holdup time required for the emitter to move through the fuel from the reaction to the coolant at the breach, and two transit times required for the emitter now in the coolant to flow from the breach to the detector loop and then via the loop to the detector. At least two of these time components are determined during calibrated operation of the reactor. Thereafter during normal reactor operation, repeated comparisons are made by the method of regression approximation of the third time component for the best-fit line correlating measured delayed-neutron activity against activity that is approximated according to specific equations. The equations use these time-delay components and known parameter values of the fuel and of the part and emitting daughter isotopes.

Inventors

  • 👤 Kenny C. Gross
  • 👤 Robert V. Strain

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 04:16
CPC Classifications
G; G21; G21C; G21C17/00; G21C17/02; G21C17/04; Y; Y02; Y02E; Y02E30/00; Y02E30/30

Claims Analysis

Total Claims: 10
Claim 1
Independent Claim 469 words
In the operation of a nuclear power reactor having a core, cladded fuel in the core, a coolant flowing through the core over the cladded fuel, and heat exchanger means to cool the coolant and obtain useful energy thereby, an improved safety control to detect if any fuel cladding has a breach that allows delayed-neutron emitters to enter the coolant, the combination comprising means for conveying the coolant from the core through a loop flow circuit and back to the core, at least three separate delayed-neutron detectors and means for mounting each detector proximate the flow circuit operable to count the delayed neutrons released by emitters in the coolant when passing the detector, the first detector being located downstream from the core a distance corresponding to coolant flow time therebetween of between fifteen and forty seconds and the second and third detectors being spaced apart and downstream from the first and second detectors, respectively, each corresponding to coolant flow time therebetween of between 1 and 3 seconds, the delayed-neutron activity at the detectors being a function of the delay time after reaction in the fuel until the coolant carrying the delayed-neutron emitter passes the respective detector, where T TOTAL =T h +T t +T d , means for calibrating the detectors during calibration operation of the reactor to determine T d and at least one of T h and T t with respect to measured delayed-neutron counts on the detectors for the calibration fuel, and means for monitoring the detectors during reactor operation and for making repeated comparisons for the best fit line by the method of regression approximation of the delayed-neutron counts measured at the respective detectors and the delayed-neutron counts approximated for each detector according to the equations: ##EQU5## where A dn i =Total delayed neutron activity at each detector attributable to isotope i, in counts/second/cm 3 of coolant; A dn TOTAL =Total count of delayed neutrons at any detector, in counts/cm 3 of coolant; λ P i , λ D i =Decay coefficient of parent and daughter isotopes of species i, in seconds -1 ; S P i , S D i =Fission production rates of parent and daughter isotopes of species i, in fissions/second; P n i =Probability of emission of a delayed neutron for each daughter isotope, dimensionless; and F=Flow rate of primary coolant through the reactor core, in cm 3 /second; T h =Isotopic holdup time of delayed-neutron emitter in moving from reaction in the fuel to the coolant, in seconds; T t =Transit time of the delayed-neutron emitter in the coolant in flowing from breach to the inlet of the detector loop flow circuit, in seconds; and T d =Transit time of the delayed-neutron emitter in the coolant in flowing from the inlet of the detector loop to the detector, in seconds.
Claim 2
Dependent Claim 469 words
In the operation of a nuclear power reactor having a core, cladded fuel in the core, a coolant flowing through the core over the cladded fuel, and heat exchanger means to cool the coolant and obtain useful energy thereby, an improved safety control to detect if any fuel cladding has a breach that allows delayed-neutron emitters to enter the coolant, the combination comprising means for conveying the coolant from the core through a loop flow circuit and back to the core, at least three separate delayed-neutron detectors and means for mounting each detector proximate the flow circuit operable to count the delayed neutrons released by emitters in the coolant when passing the detector, the first detector being located downstream from the core a distance corresponding to coolant flow time therebetween of between fifteen and forty seconds and the second and third detectors being spaced apart and downstream from the first and second detectors, respectively, each corresponding to coolant flow time therebetween of between 1 and 3 seconds, the delayed-neutron activity at the detectors being a function of the delay time after reaction in the fuel until the coolant carrying the delayed-neutron emitter passes the respective detector, where T TOTAL =T h +T t +T d , means for calibrating the detectors during calibration operation of the reactor to determine T d and at least one of T h and T t with respect to measured delayed-neutron counts on the detectors for the calibration fuel, and means for monitoring the detectors during reactor operation and for making repeated comparisons for the best fit line by the method of regression approximation of the delayed-neutron counts measured at the respective detectors and the delayed-neutron counts approximated for each detector according to the equations: ##EQU5## where A dn i =Total delayed neutron activity at each detector attributable to isotope i, in counts/second/cm 3 of coolant; A dn TOTAL =Total count of delayed neutrons at any detector, in counts/cm 3 of coolant; λ P i , λ D i =Decay coefficient of parent and daughter isotopes of species i, in seconds -1 ; S P i , S D i =Fission production rates of parent and daughter isotopes of species i, in fissions/second; P n i =Probability of emission of a delayed neutron for each daughter isotope, dimensionless; and F=Flow rate of primary coolant through the reactor core, in cm 3 /second; T h =Isotopic holdup time of delayed-neutron emitter in moving from reaction in the fuel to the coolant, in seconds; T t =Transit time of the delayed-neutron emitter in the coolant in flowing from breach to the inlet of the detector loop flow circuit, in seconds; and T d =Transit time of the delayed-neutron emitter in the coolant in flowing from the inlet of the detector loop to the detector, in seconds.
Claim 3
Dependent Claim 79 words
The safety control combination according to claim 1, further including means for evaluating the severity of the cladding breach according to the equation: ##EQU6## where ERA=Equivalent recoil area of breached operational fuel, in cm 2 ; C=Slope of best fit line for measured versus predicted delayed-neutron activity, dimensionless; α=Fission rate of fuel, in fissions/gram/second; ρ=Density of fuel, in g/cm 3 ; W=Recoil distance in the fuel, in cm; and S rc =Area of calibration fuel, in cm 2 .
Claim 4
Dependent Claim 40 words
The safety control combination according to claim 1, wherein the calculations are made according to Eqs. (1) and (2) for the parent isotope of tellurium 137 ( 137 Te), selenium 88 ( 88 Se), and selenium 89 ( 89 Se).
Claim 5
Dependent Claim 386 words
In the operation of a nuclear power reactor having a core, cladded fuel in the core, a coolant flowing through the core over the cladded fuel, and heat exchanger means to cool the coolant and obtain useful energy thereby, an improved method of detecting if any fuel cladding has a breach that allows delayed-neutron emitters to enter the coolant, comprising the steps of locating at least three separate delayed-neutron detectors proximate a coolant loop flow circuit downstream of the core, the first detector being located downstream from the core a distance to correspond to coolant flow time therebetween of between fifteen and forty seconds and the second and third detectors being spaced apart and downstream from the first and second detectors respectively, each corresponding to coolant flow time therebetween of between 1 and 3 seconds; calibrating the detectors with respect to calibration operation of the reactor to determine T d and at least one of T h and T t with respect to measured delayed-neutron counts on the detectors, and monitoring the detector counts and repeatedly comparing for best-fit line by the method of regression approximation of the delayed-neutron counts measured at the respective detectors and the delayed-neutron counts approximated for each detector according to the equations: ##EQU7## where A dn i =Total delayed neutron activity at each detector attributable to isotope i, in counts/second/cm 3 of coolant; A dn TOTAL =Total count of delayed neutrons at any detector, in counts/cm 3 of coolant; λ P i , λ D i =Decay coefficient of parent and daughter isotopes of species i, in seconds -1 ; S P i , S D i =Fission production rates of parent and daugher isotopes of species i, in fissions/second; P n i =Probability of emission of a delayed neutron for each daughter isotope, dimensionless; and F=Flow rate of primary coolant through the reactor core, in cm 3 /second; T h =Isotopic holdup time of delayed-neutron emitter in moving from reaction in the fuel to the coolant, in seconds; T t =Transit time of the delayed-neutron emitter in the coolant in flowing from breach to the inlet of the detector loop flow circuit, in seconds; and T d =Transit time of the delayed-neutron emitter in the coolant in flowing from the inlet of the detector loop to the detector, in seconds.
Claim 6
Dependent Claim 386 words
In the operation of a nuclear power reactor having a core, cladded fuel in the core, a coolant flowing through the core over the cladded fuel, and heat exchanger means to cool the coolant and obtain useful energy thereby, an improved method of detecting if any fuel cladding has a breach that allows delayed-neutron emitters to enter the coolant, comprising the steps of locating at least three separate delayed-neutron detectors proximate a coolant loop flow circuit downstream of the core, the first detector being located downstream from the core a distance to correspond to coolant flow time therebetween of between fifteen and forty seconds and the second and third detectors being spaced apart and downstream from the first and second detectors respectively, each corresponding to coolant flow time therebetween of between 1 and 3 seconds; calibrating the detectors with respect to calibration operation of the reactor to determine T d and at least one of T h and T t with respect to measured delayed-neutron counts on the detectors, and monitoring the detector counts and repeatedly comparing for best-fit line by the method of regression approximation of the delayed-neutron counts measured at the respective detectors and the delayed-neutron counts approximated for each detector according to the equations: ##EQU7## where A dn i =Total delayed neutron activity at each detector attributable to isotope i, in counts/second/cm 3 of coolant; A dn TOTAL =Total count of delayed neutrons at any detector, in counts/cm 3 of coolant; λ P i , λ D i =Decay coefficient of parent and daughter isotopes of species i, in seconds -1 ; S P i , S D i =Fission production rates of parent and daugher isotopes of species i, in fissions/second; P n i =Probability of emission of a delayed neutron for each daughter isotope, dimensionless; and F=Flow rate of primary coolant through the reactor core, in cm 3 /second; T h =Isotopic holdup time of delayed-neutron emitter in moving from reaction in the fuel to the coolant, in seconds; T t =Transit time of the delayed-neutron emitter in the coolant in flowing from breach to the inlet of the detector loop flow circuit, in seconds; and T d =Transit time of the delayed-neutron emitter in the coolant in flowing from the inlet of the detector loop to the detector, in seconds.
Claim 7
Dependent Claim 43 words
The method of detecting breached fuel cladding according to claim 4, wherein the calculations are made according to Eqs. (1) and (2) for the parent isotopes of tellurium 137 ( 137 Te), selenium 88 ( 88 Se), and selenium 89 ( 89 Se).
Claim 8
Dependent Claim 79 words
The method of detecting breached fuel cladding according to claim 4, further including evaluating the severity of the cladding breach by using the equation: ##EQU8## where ERA=Equivalent recoil area of breached operational fuel, in cm 2 ; C=Slope of best-fit line for measured versus predicted delayed-neutron activity, dimensionless; α=Fission rate of fuel, in fissions/gram/second; ρ=Density of fuel, in g/cm 3 ; W=Recoil distance in the fuel, in cm; and S rc =Area of calibration fuel, in cm 2 .
Claim 9
Dependent Claim 70 words
The safety control combination according to claim 1, wherein the calculations are made according to Eqs. (1) and (2) for the parent isotope of tellurium 137 ( 137 Te), selenium 88 ( 88 Se), selenium 89 ( 89 Se), tellurium 138 ( 138 Te), selenium 87 ( 87 Se), krypton 93 ( 93 Kr), antimony 136 ( 136 Sb), krypton 94 ( 94 Kr), and tellurium 139 ( 139 Te).
Claim 10
Dependent Claim 73 words
The method of detecting breached fuel cladding according to claim 4, wherein the calculations are made according to Eqs. (1) and (2) for the parent isotopes of tellurium 137 ( 137 Te), selenium 88 ( 88 Se), selenium 89 ( 89 Se), tellurium 138 ( 138 Te), selenium 87 ( 87 Se), krypton 93 ( 93 Kr), antimony 136 ( 136 Sb), krypton 94 ( 94 Kr), and tellurium 139 ( 139 Te).

References Cited (Backward Citations)

US3786257A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1986-11-14 1987-05-16 1987-11-15 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1990-11-14 1991-05-16 1991-11-15 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1994-11-14 1995-05-16 1995-11-15 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag