Patent US4288732A successfully refreshed from Google Patents.
US4288732A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Forced commutated starting circuit for load commutated inverter drive system
Assignee: General Electric Co
•
Filing: 1978-11-30
•
Granted: 1981-09-08
•
Expires: 1998-11-30
Abstract
Abstract In an inverter-synchronous machine drive system wherein a synchronous machine is excited by an inverter from a source of direct current, a pair of controlled bidirectional conduction means are serially coupled across the source of direct current potential, and are coupled at their junction through a commutating capacitor to the machine neutral terminal. Each controlled bidirectional conduction means, together with corresponding phase connected thyristor within the inverter, is correspondingly gated in a predetermined sequence so as to cause alternating voltage to be applied across each corresponding machine phase for initial machine excitation.
Inventors
- 👤 James W. A. Wilson
- 👤 Robert L. Steigerwald
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-01 21:02
CPC Classifications
H; H02; H02P; H02P1/00; H02P1/16; H02P1/46
Claims Analysis
Total Claims: 7
Claim 1
Independent Claim
268 words
In an inverter polyphase synchronous machine drive system including a polyphase synchronous machine excited from a source of direct current potential by an inverter, said inverter providing forced machine commutation for initial excitement thereof, said inverter comprising: a plurality of pairs of serially-connected unidirectional conduction means corresponding in number to the number of machine phases, each pair of said conduction means connected across said source of direct current potential and coupled at the pair junction to a corresponding machine phase, respectively, each said conduction means controlling current therein in response to a gate control signal impressed thereon; first and second controlled bidirectional conduction means serially connected across said source of direct current potential, each said controlled bidirectional conduction means conducting current in a direction determined by an external gate signal impressed thereon; capacitor means connected between the junction of said first and second controlled bidirectional conduction means and the neutral terminal of said polyphase machine; means for determining the charge of said capacitor; and means for providing gate control signals to each of said unidirectional conduction means and each of said bidirectional current means to cause current to flow in a predetermined sequence through said machine phases with energy supplied by said capacitor, when said capacitor charge is above a predetermined value and for providing gate control signals to each of said unidirectional conduction means and each of said bidirectional current means to cause current to flow in said predetermined sequence through said machine phases and to charge said capacitor, with energy supplied by said source of DC potential when said capacitor charge is below a predetermined value.
Claim 2
Dependent Claim
268 words
In an inverter polyphase synchronous machine drive system including a polyphase synchronous machine excited from a source of direct current potential by an inverter, said inverter providing forced machine commutation for initial excitement thereof, said inverter comprising: a plurality of pairs of serially-connected unidirectional conduction means corresponding in number to the number of machine phases, each pair of said conduction means connected across said source of direct current potential and coupled at the pair junction to a corresponding machine phase, respectively, each said conduction means controlling current therein in response to a gate control signal impressed thereon; first and second controlled bidirectional conduction means serially connected across said source of direct current potential, each said controlled bidirectional conduction means conducting current in a direction determined by an external gate signal impressed thereon; capacitor means connected between the junction of said first and second controlled bidirectional conduction means and the neutral terminal of said polyphase machine; means for determining the charge of said capacitor; and means for providing gate control signals to each of said unidirectional conduction means and each of said bidirectional current means to cause current to flow in a predetermined sequence through said machine phases with energy supplied by said capacitor, when said capacitor charge is above a predetermined value and for providing gate control signals to each of said unidirectional conduction means and each of said bidirectional current means to cause current to flow in said predetermined sequence through said machine phases and to charge said capacitor, with energy supplied by said source of DC potential when said capacitor charge is below a predetermined value.
Claim 3
Dependent Claim
29 words
The invention according to claim 1 wherein each of said controlled unidirectional conduction means comprises a thyristor having a gate terminal adapted for receiving an external gate control signal.
Claim 4
Dependent Claim
43 words
The invention according to claim 1 wherein each of said first and second controlled bidirectional conduction means comprises: a pair of controlled unidirectional conduction means connected in parallel-opposition, each controlled conduction means respectively conducting current in response to a gating signal impressed thereupon.
Claim 5
Dependent Claim
27 words
The invention according to claim 3 wherein each of said controlled unidirectional conduction means comprises a thyristor having a gate electrode adapted to receive a gating signal.
Claim 6
Independent Claim
498 words
A method of sequencing three main pairs of unidirectional switch means during forced commutation of a 3 phase bridge inverter supplying 3 phase power to a star connected load, said inverter having auxiliary switch means appropriately conducting during each of the following steps to provide a complete current path through a phase of said load, the method comprising the consecutive steps of: (a) Switching the upper switch means in the first main pair on while switching the lower switch means in the third main pair off; (b) Switching the lower switch means in the third main pair on while switching the upper switch means in the first main pair off; (c) Repeating step a followed by step b a plurality of times, the number of repetitions being dependent upon the desired period of the current supplied to said load; (d) Switching the lower switch means in the third main pair on while switching the upper switch means in the second main pair off; (e) Switching the upper switch means in the second main pair on while switching the lower switch means in the third main pair off; (f) Repeating step d followed by step e a plurality of times, the number of repetitions being dependent upon the desired period of the current supplied to said load; (g) Switching the upper switch means in the second main pair on while switching the lower switch means in the first main pair off; (h) Switching the lower switch means in the first main pair on while switching the upper switch means in the second main pair off; (i) Repeating step g followed by step h a plurality of times, the number of repetitions being dependent upon the desired period of the current supplied to said load; (j) Switching the lower switch means in the first main pair on while switching the upper switch means in the third main pair off; (k) Switching the upper switch means in the third main pair on while switching the lower switch means in the first main pair off; (l) Repeating step j followed by step k a plurality of times, the number of repetitions being dependent upon the desired period of the current supplied to said load; (m) Switching the upper switch means in the third main pair on while switching the lower switch means in the second main pair off; (n) Switching the lower switch means in the second main pair on while switching the upper switch means in the third main pair off; (o) Repeating step m followed by step n a plurality of times, the number of repetitions being dependent upon the desired period of current supplied to said load; (p) Switching the lower switch means in the second main pair on while switching the lower switch means in the second main pair off; (q) Switching the upper switch means in the first main pair on while switching the lower switch means in the second main pair off; (r) Repeating steps a-r.
Claim 7
Independent Claim
498 words
A method of sequencing three main pairs of unidirectional switch means during forced commutation of a 3 phase bridge inverter supplying 3 phase power to a star connected load, said inverter having auxiliary switch means appropriately conducting during each of the following steps to provide a complete current path through a phase of said load, the method comprising the consecutive steps of: (a) Switching the upper switch means in the first main pair on while switching the lower switch means in the third main pair off; (b) Switching the lower switch means in the third main pair on while switching the upper switch means in the first main pair off; (c) Repeating step a followed by step b a plurality of times, the number of repetitions being dependent upon the desired period of the current supplied to said load; (d) Switching the lower switch means in the third main pair on while switching the upper switch means in the second main pair off; (e) Switching the upper switch means in the second main pair on while switching the lower switch means in the third main pair off; (f) Repeating step d followed by step e a plurality of times, the number of repetitions being dependent upon the desired period of the current supplied to said load; (g) Switching the upper switch means in the second main pair on while switching the lower switch means in the first main pair off; (h) Switching the lower switch means in the first main pair on while switching the upper switch means in the second main pair off; (i) Repeating step g followed by step h a plurality of times, the number of repetitions being dependent upon the desired period of the current supplied to said load; (j) Switching the lower switch means in the first main pair on while switching the upper switch means in the third main pair off; (k) Switching the upper switch means in the third main pair on while switching the lower switch means in the first main pair off; (l) Repeating step j followed by step k a plurality of times, the number of repetitions being dependent upon the desired period of the current supplied to said load; (m) Switching the upper switch means in the third main pair on while switching the lower switch means in the second main pair off; (n) Switching the lower switch means in the second main pair on while switching the upper switch means in the third main pair off; (o) Repeating step m followed by step n a plurality of times, the number of repetitions being dependent upon the desired period of current supplied to said load; (p) Switching the lower switch means in the second main pair on while switching the lower switch means in the second main pair off; (q) Switching the upper switch means in the first main pair on while switching the lower switch means in the second main pair off; (r) Repeating steps a-r.
References Cited (Backward Citations)
SU259256A1
Cited
US3487289A
Cited
SU576645A1
Cited
SU515244A1
Cited
JPS4725921U
Cited
US3763417A
Cited
US3838330A
Cited
SU541252A1
Cited
US3935528A
Cited
SU526993A1
Cited
US4100469A
Cited
US4136382A
Cited
US4180853A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1984-09-07 | 1985-03-09 | 1985-09-08 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1988-09-07 | 1989-03-09 | 1989-09-08 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1992-09-07 | 1993-03-09 | 1993-09-08 | $7700.00 | Window Closed / Lapsed |