Method for improving the effective permeability of formations
Assignee: Texaco Inc
•
Filing: 1979-12-13
•
Granted: 1981-07-21
•
Expires: 1999-12-13
Abstract
Abstract A method to increase the effective permeability of a subterranean hydrocarbon-bearing formation employing a deviated well-drilling scheme and a fracturing technique.
Inventors
- 👤 Thomas E. Williams
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-08 02:40
CPC Classifications
E; E21; E21B; E21B43/00; E21B43/25; E21B43/26; E21B43/261; E21B43/30; E21B43/305
Claims Analysis
Total Claims: 12
Claim 1
Independent Claim
180 words
A method to increase the effective permeability of a subterranean hydrocarbon-bearing formation having at least one productive interval comprising the steps of: (a) drilling a first well bore traversing said productive interval of said hydrocarbon-bearing formation, (b) fracturing said first well bore adjacent said productive interval, (c) setting a bridge plug above said productive interval in said first well bore and thereafter undertaking a cementing operation in said first well bore to a desired depth, (d) drilling a second well bore having the upper portion thereof in common with said first well bore and deviated from said first well bore from the top of said cementing operation and thereafter fracturing said productive interval adjacent said deviated second well bore, (e) setting a bridge plug above the productive interval in said second well bore and thereafter undertaking a cementing operation in said second well bore to a desired depth, (f) repeating steps (d) and (e) to provide additional similarly deviated well bores, (g) drilling a final similarly deviated well bore and completing said final well bore by setting tubing and packer.
Claim 2
Independent Claim
180 words
A method to increase the effective permeability of a subterranean hydrocarbon-bearing formation having at least one productive interval comprising the steps of: (a) drilling a first well bore traversing said productive interval of said hydrocarbon-bearing formation, (b) fracturing said first well bore adjacent said productive interval, (c) setting a bridge plug above said productive interval in said first well bore and thereafter undertaking a cementing operation in said first well bore to a desired depth, (d) drilling a second well bore having the upper portion thereof in common with said first well bore and deviated from said first well bore from the top of said cementing operation and thereafter fracturing said productive interval adjacent said deviated second well bore, (e) setting a bridge plug above the productive interval in said second well bore and thereafter undertaking a cementing operation in said second well bore to a desired depth, (f) repeating steps (d) and (e) to provide additional similarly deviated well bores, (g) drilling a final similarly deviated well bore and completing said final well bore by setting tubing and packer.
Claim 3
Dependent Claim
18 words
The method of claim 1 wherein said fracturing is accomplished by sequentially fracturing segments of said productive interval.
Claim 4
Dependent Claim
74 words
The method of claim 2 wherein said fracturing of said segments employs the steps of: (a) setting a retrievable packer and a retrievable bridge plug to isolate one of said segments, (b) fracturing said one segment, (c) relocating said packer and said bridge plug to isolate a second segment of said interval, (d) fracturing said second segment of said interval, (e) repeating steps (a) and (b) to accomplish the fracturing of said productive interval.
Claim 5
Dependent Claim
16 words
The method of claim 1 wherein said subterranean hydrocarbon-bearing formation comprises more than one productive interval.
Claim 6
Dependent Claim
23 words
The method of claim 1 wherein said well bore is cleaned out and a production test is performed prior to the cementing operation.
Claim 7
Dependent Claim
19 words
The method of claim 1 wherein a plurality of similarly deviated well bores are drilled through said productive interval.
Claim 8
Dependent Claim
30 words
The method of claim 1 wherein said deviated well bores are spaced apart and whereby communication below said bridge plugs is established among said deviated well bores upon said fracturing.
Claim 9
Dependent Claim
18 words
The method of claim 1 wherein said deviated well bores are drilled to substantially the same productive depth.
Claim 10
Dependent Claim
18 words
The method of claim 1 wherein said final deviated well bore is completed as a production well means.
Claim 11
Dependent Claim
18 words
The method of claim 1 wherein said final deviated well bore is completed as an injection well means.
Claim 12
Dependent Claim
27 words
The method of claim 1 wherein said final deviated well bore is completed to serve as both an injection well means and as a production well means.
References Cited (Backward Citations)
US2788072A
Cited
US2788956A
Cited
US3002454A
Cited
US3003557A
Cited
US3161235A
Cited
US3223158A
Cited
US3289762A
Cited
US3587743A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1984-07-20 | 1985-01-19 | 1985-07-21 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1988-07-20 | 1989-01-19 | 1989-07-21 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1992-07-20 | 1993-01-19 | 1993-07-21 | $7700.00 | Window Closed / Lapsed |