Method for improving the effective permeability of formations

Assignee: Texaco Inc
•
Filing: 1979-12-13
•
Granted: 1981-07-21
•
Expires: 1999-12-13
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method to increase the effective permeability of a subterranean hydrocarbon-bearing formation employing a deviated well-drilling scheme and a fracturing technique.

Inventors

  • 👤 Thomas E. Williams

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-29 06:30
CPC Classifications
E; E21; E21B; E21B43/00; E21B43/25; E21B43/26; E21B43/261; E21B43/30; E21B43/305

Claims Analysis

Total Claims: 12
Claim 1
Independent Claim 180 words
A method to increase the effective permeability of a subterranean hydrocarbon-bearing formation having at least one productive interval comprising the steps of: (a) drilling a first well bore traversing said productive interval of said hydrocarbon-bearing formation, (b) fracturing said first well bore adjacent said productive interval, (c) setting a bridge plug above said productive interval in said first well bore and thereafter undertaking a cementing operation in said first well bore to a desired depth, (d) drilling a second well bore having the upper portion thereof in common with said first well bore and deviated from said first well bore from the top of said cementing operation and thereafter fracturing said productive interval adjacent said deviated second well bore, (e) setting a bridge plug above the productive interval in said second well bore and thereafter undertaking a cementing operation in said second well bore to a desired depth, (f) repeating steps (d) and (e) to provide additional similarly deviated well bores, (g) drilling a final similarly deviated well bore and completing said final well bore by setting tubing and packer.
Claim 2
Independent Claim 180 words
A method to increase the effective permeability of a subterranean hydrocarbon-bearing formation having at least one productive interval comprising the steps of: (a) drilling a first well bore traversing said productive interval of said hydrocarbon-bearing formation, (b) fracturing said first well bore adjacent said productive interval, (c) setting a bridge plug above said productive interval in said first well bore and thereafter undertaking a cementing operation in said first well bore to a desired depth, (d) drilling a second well bore having the upper portion thereof in common with said first well bore and deviated from said first well bore from the top of said cementing operation and thereafter fracturing said productive interval adjacent said deviated second well bore, (e) setting a bridge plug above the productive interval in said second well bore and thereafter undertaking a cementing operation in said second well bore to a desired depth, (f) repeating steps (d) and (e) to provide additional similarly deviated well bores, (g) drilling a final similarly deviated well bore and completing said final well bore by setting tubing and packer.
Claim 3
Dependent Claim 18 words
The method of claim 1 wherein said fracturing is accomplished by sequentially fracturing segments of said productive interval.
Claim 4
Dependent Claim 74 words
The method of claim 2 wherein said fracturing of said segments employs the steps of: (a) setting a retrievable packer and a retrievable bridge plug to isolate one of said segments, (b) fracturing said one segment, (c) relocating said packer and said bridge plug to isolate a second segment of said interval, (d) fracturing said second segment of said interval, (e) repeating steps (a) and (b) to accomplish the fracturing of said productive interval.
Claim 5
Dependent Claim 16 words
The method of claim 1 wherein said subterranean hydrocarbon-bearing formation comprises more than one productive interval.
Claim 6
Dependent Claim 23 words
The method of claim 1 wherein said well bore is cleaned out and a production test is performed prior to the cementing operation.
Claim 7
Dependent Claim 19 words
The method of claim 1 wherein a plurality of similarly deviated well bores are drilled through said productive interval.
Claim 8
Dependent Claim 30 words
The method of claim 1 wherein said deviated well bores are spaced apart and whereby communication below said bridge plugs is established among said deviated well bores upon said fracturing.
Claim 9
Dependent Claim 18 words
The method of claim 1 wherein said deviated well bores are drilled to substantially the same productive depth.
Claim 10
Dependent Claim 18 words
The method of claim 1 wherein said final deviated well bore is completed as a production well means.
Claim 11
Dependent Claim 18 words
The method of claim 1 wherein said final deviated well bore is completed as an injection well means.
Claim 12
Dependent Claim 27 words
The method of claim 1 wherein said final deviated well bore is completed to serve as both an injection well means and as a production well means.

References Cited (Backward Citations)

US2788072A Cited
US2788956A Cited
US3002454A Cited
US3003557A Cited
US3161235A Cited
US3223158A Cited
US3289762A Cited
US3587743A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1984-07-20 1985-01-19 1985-07-21 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1988-07-20 1989-01-19 1989-07-21 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1992-07-20 1993-01-19 1993-07-21 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag