Assignee: Mobil Oil AS
•
Filing: 1980-04-07
•
Granted: 1981-05-12
•
Expires: 2000-04-07
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method for protecting the steel casing and production tubing in a carbon dioxide production well from the corrosive effects of the produced carbon dioxide. The cased well is filled with corrosion inhibitor liquid and fluid communication between the producing formation and the casing is established by perforating or the like. A pump means, e.q. electrically driven, centrifugal pump system and a packer means are lowered on the production tubing to a point adjacent or slightly above the producing formation. The packer means is set to isolate the pump means from the well annulus above the packer means. The corrosion inhibitor liquid below the packer is pumped to the surface through the production tubing and the well is now ready to produce carbon dioxide. The corrosion inhibitor liquid in the well annulus above the packer remains in place and will absorb any carbon dioxide that may leak by or permeate through the packer means thereby alleviating the corrosive effects of such carbon dioxide on both the casing and tubing above the packer means.

Inventors

  • 👤 Louis N. Halstead

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-03 17:12
CPC Classifications
E; E21; E21B; E21B41/00; E21B41/02; E21B43/00; E21B43/12; E21B43/121; E21B43/128; Y; Y10; Y10S; Y10S166/00; Y10S166/902

Claims Analysis

Total Claims: 8
Claim 1
Independent Claim 128 words
A method of completing a well for producing carbon dioxide from a subterranean formation comprising: drilling a well into said formation; casing said well with a first conduit; filling said first conduit with a corrosion inhibitor liquid; establishing fluid communication between said formation and the interior of said first conduit; lowering a pump means on a second conduit into first conduit to a point adjacent or slightly above said formation, said first and second conduits forming an annulus therebetween; isolating said pump means from said annulus above said pump means; and pumping out said corrosion inhibitor liquid from the isolated portion of said well surrounding said pump means through said second conduit while leaving said corrosion inhibitor liquid in said annulus above said isolated portion of said well.
Claim 2
Independent Claim 128 words
A method of completing a well for producing carbon dioxide from a subterranean formation comprising: drilling a well into said formation; casing said well with a first conduit; filling said first conduit with a corrosion inhibitor liquid; establishing fluid communication between said formation and the interior of said first conduit; lowering a pump means on a second conduit into first conduit to a point adjacent or slightly above said formation, said first and second conduits forming an annulus therebetween; isolating said pump means from said annulus above said pump means; and pumping out said corrosion inhibitor liquid from the isolated portion of said well surrounding said pump means through said second conduit while leaving said corrosion inhibitor liquid in said annulus above said isolated portion of said well.
Claim 3
Dependent Claim 18 words
The method of claim 1 wherein said pump means comprises: an electrically driven, submergible, multistage centrifugal pump system.
Claim 4
Dependent Claim 30 words
The method of claim 2 wherein said step of isolating said pump means comprises: setting a packer means around said pump means at a point slightly above said pump means.
Claim 5
Dependent Claim 18 words
The method of claim 3 wherein said packer means is affixed to and lowered with said second conduit.
Claim 6
Dependent Claim 21 words
The method of claim 4 wherein said corrosion inhibitor liquid comprises: water containing a cationic, film forming, amine corrosion inhibitor compound.
Claim 7
Dependent Claim 94 words
In a method for producing carbon dioxide from a carbon dioxide production well having a pump means suspended on a production tubing in said well to boost the pressure of the produced carbon dioxide to a value sufficient to produce carbon dioxide at the surface above its critical pressure, the improvement comprising: setting a packer means just above said pump means to isolate said pump means from the annulus formed between the wellbore and said production tubing above said packer means; and filling said annulus above said packer means with a corrosion inhibitor liquid.
Claim 8
Dependent Claim 94 words
In a method for producing carbon dioxide from a carbon dioxide production well having a pump means suspended on a production tubing in said well to boost the pressure of the produced carbon dioxide to a value sufficient to produce carbon dioxide at the surface above its critical pressure, the improvement comprising: setting a packer means just above said pump means to isolate said pump means from the annulus formed between the wellbore and said production tubing above said packer means; and filling said annulus above said packer means with a corrosion inhibitor liquid.

References Cited (Backward Citations)

CA495832A Cited
US2089035A Cited
US2357559A Cited
US2510771A Cited
US2654436A Cited
US2801697A Cited
US2795278A Cited
US2773551A Cited
US3076503A Cited
US3385358A Cited
US3369606A Cited
SU426029A1 Cited
US4031955A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1984-05-11 1984-11-10 1985-05-12 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1988-05-11 1988-11-10 1989-05-12 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1992-05-11 1992-11-10 1993-05-12 $7700.00 Window Closed / Lapsed