Abstract

Abstract An aerial conveyor system comprises a pair of spaced apart cables extending from a first vehicle including material delivery apparatus across a material receiving zone, across an open area, and across a material discharge zone to a second vehicle. The cables support a plurality of conveyor support frames each comprising a pair of tubular members extending substantially parallel to the cables, a plurality of hook rollers for supporting the tubular members on the cables, and a plurality of transversely disposed conveyor support rollers. An endless conveyor belt is mounted for movement around a course defined by the conveyor support rollers of the conveyor support frames and functions to transport material received from the delivery apparatus of the first vehicle in the receiving zone across the open area to the discharge zone. The conveyor is driven by apparatus including a drive roller mounted at the discharge zone end of the conveyor support frame which is actuated by hydraulic fluid supplied through the tubular elongate members thereof. In the use of the aerial conveyor system, overburden is preferably removed in accordance with a series of vertically stacked zones. The aerial conveyor system is then employed to discharge the excavated material into a previously mined portion of the excavation in accordance with the same vertical sequence. By this means the original vertical configuration of the excavation is restored, thereby facilitating return of the mined area to productive usage.

Inventors

  • 👤 Charles R. Satterwhite

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 10:46
CPC Classifications
E; E21; E21C; E21C47/00; E21C41/00; E21C41/26

Claims Analysis

Total Claims: 11
Claim 1
Independent Claim 197 words
In a strip mining process of the type in which overburden covering an ore-bearing layer is excavated to facilitate mining of the ore-bearing layer, the improvement comprising: extending at least one cable across the excavation from a point adjacent the unexcavated overburden to a point above a previously mined portion of the excavation; supporting an aerial conveyor from the thus extended cable; removing overburden from one side of the excavation in accordance with a predetermined sequence of vertical zones including a topsoil zone and at least one subsoil zone and thereby progressively uncovering additional portions of the ore-bearing layer; receiving the removed overburden on the serial conveyor and conveying the removed overburden across the excavation to a point above a previously mined portion of the excavation; discharging the removed overburden from the conveyor and thereby refilling the previously mined portion of the excavation in accordance with the same sequence of vertical zones so that all of the overburden from the subsoil zone is positioned in a layer characterized by a substantially horizontal upper surface, said layer lying beneath all of the overburden from the topsoil zone and thereby facilitating return of the mind area to productive usage.
Claim 2
Dependent Claim 197 words
In a strip mining process of the type in which overburden covering an ore-bearing layer is excavated to facilitate mining of the ore-bearing layer, the improvement comprising: extending at least one cable across the excavation from a point adjacent the unexcavated overburden to a point above a previously mined portion of the excavation; supporting an aerial conveyor from the thus extended cable; removing overburden from one side of the excavation in accordance with a predetermined sequence of vertical zones including a topsoil zone and at least one subsoil zone and thereby progressively uncovering additional portions of the ore-bearing layer; receiving the removed overburden on the serial conveyor and conveying the removed overburden across the excavation to a point above a previously mined portion of the excavation; discharging the removed overburden from the conveyor and thereby refilling the previously mined portion of the excavation in accordance with the same sequence of vertical zones so that all of the overburden from the subsoil zone is positioned in a layer characterized by a substantially horizontal upper surface, said layer lying beneath all of the overburden from the topsoil zone and thereby facilitating return of the mind area to productive usage.
Claim 3
Dependent Claim 34 words
The strip mining process according to claim 1 wherein the conveying step is further characterized by conveying the removed overburden substantially horizontally from a location adjacent the point of removal to the discharge location.
Claim 4
Dependent Claim 34 words
The strip mining process according to claim 2 wherein the conveying step is further characterized by periodically receiving overburden in a hopper, and substantially continuously conveying overburden from the hopper to the discharge location.
Claim 5
Dependent Claim 30 words
The strip mining process according to claim 3 further characterized by selectively removing large rocks from the overburden prior to conveying the overburden across the excavation to the discharge location.
Claim 6
Dependent Claim 231 words
In a strip mining process of the type in which overburden covering an ore-bearing layer is excavated to facilitate mining of the ore-bearing layer, and in which the excavated overburden is utilized to refill a previously mined portion of the excavation, the improvement comprising: extending at least one cable across the excavation from a point adjacent the unexcavated overburden to a point above a previously mined portion of the excavation; supporting an aerial conveyor from the thus extended cable; initially removing overburden from a subsoil zone, receiving the subsoil overburden on the aerial conveyor, conveying the subsoil overburden on the aerial conveyor substantially horizontally across the excavation to a point above the previously mined portion thereof, and discharging all of the subsoil overburden from the aerial conveyor into the lowermost zone of the previously mined portion of the excavation to form a subsoil layer characterized by a substantially horizontal upper surface; and subsequently removing overburden from a topsoil zone, receiving the topsoil overburden on the aerial conveyor, conveying the topsoil overburden on the aerial conveyor substantially horizontally across the excavation to a point above the previously mined portion thereof, and discharging the topsoil overburden from the aerial coveyor into the uppermost zone of the previously mined portion of the excavation so that all of the overburden from the topsoil zone is positioned on top of the overburden from the subsoil zone.
Claim 7
Dependent Claim 231 words
In a strip mining process of the type in which overburden covering an ore-bearing layer is excavated to facilitate mining of the ore-bearing layer, and in which the excavated overburden is utilized to refill a previously mined portion of the excavation, the improvement comprising: extending at least one cable across the excavation from a point adjacent the unexcavated overburden to a point above a previously mined portion of the excavation; supporting an aerial conveyor from the thus extended cable; initially removing overburden from a subsoil zone, receiving the subsoil overburden on the aerial conveyor, conveying the subsoil overburden on the aerial conveyor substantially horizontally across the excavation to a point above the previously mined portion thereof, and discharging all of the subsoil overburden from the aerial conveyor into the lowermost zone of the previously mined portion of the excavation to form a subsoil layer characterized by a substantially horizontal upper surface; and subsequently removing overburden from a topsoil zone, receiving the topsoil overburden on the aerial conveyor, conveying the topsoil overburden on the aerial conveyor substantially horizontally across the excavation to a point above the previously mined portion thereof, and discharging the topsoil overburden from the aerial coveyor into the uppermost zone of the previously mined portion of the excavation so that all of the overburden from the topsoil zone is positioned on top of the overburden from the subsoil zone.
Claim 8
Dependent Claim 58 words
The strip mining process according to claim 5 further characterized by removing overburden by means of a dragline; periodically receiving overburden from a dragline in a hopper; and conveying material substantially continuously from the hopper on the aerial conveyor to the point over the previously mined portion of the excavation and discharging the material from the aerial conveyor.
Claim 9
Dependent Claim 23 words
The strip mining process according to claim 5 further characterized by selectively removing large rocks from the overburden prior to the conveying steps.
Claim 10
Dependent Claim 91 words
The strip mining process according to claim 5 further characterized by the intermediate steps of removing overburden from a zone located between the subsoil zone and the topsoil zone, receiving the soil from the intermediate zone on the aerial conveyor, conveying the material from the intermediate zone on the aerial conveyor substantially horizontally to the point above the previously mined portion of the excavation, and discharging the material from the aerial conveyor into a zone of the previously mined portion of the excavation located between the lowermost and uppermost zones thereof.
Claim 11
Dependent Claim 25 words
The strip mining process according to claim 5 wherein overburden is removed from the subsoil and from the topsoil zones by means of a dragline.

References Cited (Backward Citations)

US591047A Cited
US779043A Cited
US878575A Cited
DE406489C Cited
DE449847C Cited
US1684147A Cited
US1935638A Cited
US2316943A Cited
US2897564A Cited
US3387061A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1982-01-08 1982-07-10 1983-01-09 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1986-01-08 1986-07-10 1987-01-09 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1990-01-08 1990-07-10 1991-01-09 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag