Method and apparatus for set point control for steam temperatures for start-up of the turbine and steam generator in unit power plants
Assignee: BBC Brown Boveri AG Switzerland
•
Filing: 1976-11-18
•
Granted: 1978-05-23
•
Expires: 1996-11-18
Abstract
Abstract Method and apparatus for controlling the set point for steam temperatures for cold start-up of a steam generator-turbine unit wherein inlet steam temperature and turbine load absorption are steadily and substantially simultaneously increased in accordance with a predetermined relationship so as to reach their final values substantially synchronously.
Inventors
- 👤 Heinz Bloch
- 👤 Max Salm
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-10-25 21:07
CPC Classifications
F; F01; F01K; F01K13/00; F01K13/02; F01D; F01D19/00; F01D19/02; F22; F22B; F22B35/00; F22B35/06; F22B35/14
Claims Analysis
Total Claims: 7
Claim 1
Independent Claim
92 words
A method for simultaneously starting up a steam turbine and a steam generator comprising the steps of: (a) steadily increasing the load absorption of said steam turbine from a first to a second value; (b) simultaneously and steadily increasing the temperature of said steam as it enters said turbine from a first to a second value; (c) coordinating the rate of change of said load absorption and said steam temperature such that both quantities reach their respective second value simultaneously and in a time which produces only acceptable stresses in said turbine.
Claim 2
Independent Claim
92 words
A method for simultaneously starting up a steam turbine and a steam generator comprising the steps of: (a) steadily increasing the load absorption of said steam turbine from a first to a second value; (b) simultaneously and steadily increasing the temperature of said steam as it enters said turbine from a first to a second value; (c) coordinating the rate of change of said load absorption and said steam temperature such that both quantities reach their respective second value simultaneously and in a time which produces only acceptable stresses in said turbine.
Claim 3
Dependent Claim
195 words
The method of claim 1 wherein the desired instantaneous temperature of said steam as it enters said turbine is controlled by a signal TES and wherein said signal is derived by the steps of: computing a value TS = TMO - TMM, which is representative of the turbine stress, where TMO is the turbine surface temperature and TMM is the mean metal temperature of said turbine; controlling the steam throughput using an acceleration regulator so as to maintain said value TS at a desired value TSS given by machine data; and computing the value of said signal TES in accordance with the following equation: TES = TMM + TSS + + TA + TDMN × P.sub.n /MAX(P,P.sub.MIN) wherein; Ta is the temperature drop given by machine data from the entrance of said turbine to the point at which a probe measuring said value TMM is located; P is the load; P min is the minimum load; P n is the nominal load; Tdmn is the measured temperature drop steam to metal at said nominal load P n ; and Max (p,p min ) is the maximum of the two quantities P and P MIN .
Claim 4
Dependent Claim
114 words
The method of claim 2 further including the step of computing a predicted mean load variation according to the relationship: BG = 100 × GMZ/(TDEL (1 + ATM × TK)), where: Bg = dp/dt = the mean load variation in time, Gmz = the mean metal temperature variation with respect to time, calculated as GMZ = TSS/ZKS wherein ZKS is a characteristic time constant determined by the dimensions and material constants of said probe, Tdel = the measured temperature difference traversed by the metal temperature TM during the start-up procedure, Atm = the calculated deviation of the mean value of the mean metal temperature, Tk = the combined temperature coefficient of the material constants.
Claim 5
Dependent Claim
21 words
The method of claim 2 wherein said predicted mean load variation is utilized to control the load absorption of said turbine.
Claim 6
Dependent Claim
528 words
Apparatus for controlling the set point steam temperatures for start-up of a steam generator-turbine combination wherein start-up is optimized, characterized by the following apparatus units: a. measured value transmitter (2) for generating a signal representative of the turbine mean metal temperature (TMM); b. means (19) for generating a signal TMO representative of the surface metal temperature c. a first desired value transmitter (3) for generating a signal representative of the desired value (TSS) of a signal TS = TMO - TMM generated by a start-up probe, wherein TMO is the turbine surface temperature and TMM is the mean metal temperature of said turbine; d. a first analog value transmitter (4) for generating a signal representative of the temperature drop (TA) between turbine inlet and said start-up probe; e. a second analog value transmitter (5) for generating a signal representative of the temperature difference (TDMN) steam-to-metal at full load; f. a second desired value transmitter (8) for generating a signal representative of the load set point (P); g. a third analog value transmitter (9) for generating a signal representative of the value (P MIN ) of the minimum boiler load; h. a maximum value transformer (7) for generating a signal MAX (P,P MIN ) representing the maximum of the two signals P,P MIN ; i. a first divider circuit circuit (6) for generating a signal representative of the value TDMN/MAX (P,P MIN ); j. a totalling circuit (1) for generating a signal TES representative of the desired value of the steam inlet temperature in accordance with the following equation: TES = TMN + TSS + TA + TDMN × P.sub.n /MAX (P,P.sub.MIN); k. a fifth analog value transmitter (17) for generating a signal representative of the steam end temperature (TFE); l. an analog memory (19) for storing the surface metal temperature (TMO) at the beginning of start-up; m. a second totalling circuit (16) for generating a signal TDEL representative of the quantity [TFE -TDMN - TSS - TA - TMO]; n. a first multiplying circuit (20) for multiplying said signal TDEL by the constant factor 0.5; o. a fixed value transmitter (21) for generating a signal T representative of a predetermined reference temperature; p. a third totalling circuit (18) for generating a signal ATM representative of the quantity [RMO + 0.5 TDEL - T]; q. a fourth analog value transmitter (12) for generating a signal representative of the combined mean temperature coefficient (TK); r. a second multiplying circuit (13) for multiplying said signal representative of said combined mean temperature coefficient (TK) signal by said signal ATM; s. an adding circuit (14) for adding the output signal of said first multiplying circuit (13) and the quantity "1"; and for generating an output signal representative of said added quantity; t. a third multiplying circuit (15) for multiplying said signal TDEL by said signal generated by said adding circuit (14); u. a sixth analog value transmitter (10) for generating a signal representative of the mean metal temperature variation in time (GMZ = dTM/dt) permissible at said predetermined reference temperature; and v. a second dividing circuit (11) for generating a signal BG representative of the value GMZ/TDEL [1 = ATM × (TK)] .
Claim 7
Dependent Claim
528 words
Apparatus for controlling the set point steam temperatures for start-up of a steam generator-turbine combination wherein start-up is optimized, characterized by the following apparatus units: a. measured value transmitter (2) for generating a signal representative of the turbine mean metal temperature (TMM); b. means (19) for generating a signal TMO representative of the surface metal temperature c. a first desired value transmitter (3) for generating a signal representative of the desired value (TSS) of a signal TS = TMO - TMM generated by a start-up probe, wherein TMO is the turbine surface temperature and TMM is the mean metal temperature of said turbine; d. a first analog value transmitter (4) for generating a signal representative of the temperature drop (TA) between turbine inlet and said start-up probe; e. a second analog value transmitter (5) for generating a signal representative of the temperature difference (TDMN) steam-to-metal at full load; f. a second desired value transmitter (8) for generating a signal representative of the load set point (P); g. a third analog value transmitter (9) for generating a signal representative of the value (P MIN ) of the minimum boiler load; h. a maximum value transformer (7) for generating a signal MAX (P,P MIN ) representing the maximum of the two signals P,P MIN ; i. a first divider circuit circuit (6) for generating a signal representative of the value TDMN/MAX (P,P MIN ); j. a totalling circuit (1) for generating a signal TES representative of the desired value of the steam inlet temperature in accordance with the following equation: TES = TMN + TSS + TA + TDMN × P.sub.n /MAX (P,P.sub.MIN); k. a fifth analog value transmitter (17) for generating a signal representative of the steam end temperature (TFE); l. an analog memory (19) for storing the surface metal temperature (TMO) at the beginning of start-up; m. a second totalling circuit (16) for generating a signal TDEL representative of the quantity [TFE -TDMN - TSS - TA - TMO]; n. a first multiplying circuit (20) for multiplying said signal TDEL by the constant factor 0.5; o. a fixed value transmitter (21) for generating a signal T representative of a predetermined reference temperature; p. a third totalling circuit (18) for generating a signal ATM representative of the quantity [RMO + 0.5 TDEL - T]; q. a fourth analog value transmitter (12) for generating a signal representative of the combined mean temperature coefficient (TK); r. a second multiplying circuit (13) for multiplying said signal representative of said combined mean temperature coefficient (TK) signal by said signal ATM; s. an adding circuit (14) for adding the output signal of said first multiplying circuit (13) and the quantity "1"; and for generating an output signal representative of said added quantity; t. a third multiplying circuit (15) for multiplying said signal TDEL by said signal generated by said adding circuit (14); u. a sixth analog value transmitter (10) for generating a signal representative of the mean metal temperature variation in time (GMZ = dTM/dt) permissible at said predetermined reference temperature; and v. a second dividing circuit (11) for generating a signal BG representative of the value GMZ/TDEL [1 = ATM × (TK)] .
References Cited (Backward Citations)
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1981-05-22 | 1981-11-21 | 1982-05-23 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1985-05-22 | 1985-11-21 | 1986-05-23 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1989-05-22 | 1989-11-21 | 1990-05-23 | $7700.00 | Window Closed / Lapsed |