Claims Analysis
Total Claims: 13
Claim 1
Independent Claim
215 words
A method for the underground mining of subsidable mineral deposits comprising: (a) providing at least one longitudinally extending tunnel within said subsidable deposit and adjacent the base thereof; (b) inserting a plurality of hydraulic excavators a predetermined distance laterally into said deposits from at least one side of said tunnel, each of said excavators being positioned such that during operation, there is fluidic interaction between heads of adjacent excavators; (c) commencing mining of said deposit at a location remote from said tunnel by fluidizing a zone of said deposit adjacent each said excavator head, and withdrawing mined material from said zone by suction; (d) independently advancing and retracting each of said excavator heads, by programmed reciprocational movement thereof, thus expanding the fluidized zone over a predetermined distance, while permitting subsidence of minable material into said mining zone; (e) continually extracting samples of mined materials from the material produced by each said excavator for determining the presence of any overburden therein; (f) relocating each said excavator head by the retraction of each said excavator a predetermined distance towards said tunnel following evidence of overburden in said samples and continuing mining at the new location in the manner as originally done; and (g) terminating excavation by each said excavator when said mining zone lies adjacent said tunnel.
Claim 2
Independent Claim
215 words
A method for the underground mining of subsidable mineral deposits comprising: (a) providing at least one longitudinally extending tunnel within said subsidable deposit and adjacent the base thereof; (b) inserting a plurality of hydraulic excavators a predetermined distance laterally into said deposits from at least one side of said tunnel, each of said excavators being positioned such that during operation, there is fluidic interaction between heads of adjacent excavators; (c) commencing mining of said deposit at a location remote from said tunnel by fluidizing a zone of said deposit adjacent each said excavator head, and withdrawing mined material from said zone by suction; (d) independently advancing and retracting each of said excavator heads, by programmed reciprocational movement thereof, thus expanding the fluidized zone over a predetermined distance, while permitting subsidence of minable material into said mining zone; (e) continually extracting samples of mined materials from the material produced by each said excavator for determining the presence of any overburden therein; (f) relocating each said excavator head by the retraction of each said excavator a predetermined distance towards said tunnel following evidence of overburden in said samples and continuing mining at the new location in the manner as originally done; and (g) terminating excavation by each said excavator when said mining zone lies adjacent said tunnel.
Claim 3
Dependent Claim
49 words
The method according to claim 1 including lining said at least one tunnel by the installation of a double set of mining arches installed in inwardly facing pairs and in side-abutting relationship, certain of said mining arches being adapted to provide access for said excavators to the mineral deposit.
Claim 4
Dependent Claim
40 words
The method according to claim 2 wherein the excavators are spaced one from the other in parallel array in the longitudinal direction of the tunnel and that during advancement to their respective mining locations, the distance therebetween is substantially maintained.
Claim 5
Dependent Claim
123 words
The method according to claim 1 wherein independent advancement of each said excavator to its mining location is achieved by: (a) providing said excavator in a number of sections, each attachable one to the other; (b) driving a first section carrying said excavator head into said deposit while passing sufficient pressurized fluid through said section to fluidize only the area immediately surrounding said head, the fluidized material being extracted by suction means via a suction port in said head; (c) connecting, in fluid tight relation, a second excavator section to said first section and similarly driving said second section into said deposit; (d) continuing the attachment, and driving, of subsequent excavator sections into said deposit, until the desired mining location has been reached.
Claim 6
Dependent Claim
34 words
The method according to claim 4 wherein reciprocation of said excavation heads to expand the mining zone is achieved by alternately withdrawing and advancing at least one section of said excavator within said tunnel.
Claim 7
Dependent Claim
70 words
The method according to claim 2 wherein said at least one tunnel is formed by hydraulic excavation, at least one main excavator being utilized to excavate in the direction of advance of said tunnel, and a tunnel profile excavator associated with said mining arches for movement thereon, said profile excavator being adapted to excavate only to the limit of the tunnel outline; the excavated material being removed by suction means.
Claim 8
Dependent Claim
59 words
The method according to claim 1 wherein a plurality of tunnels are provided, each adapted for progressive extension by hydraulic mining methods through said deposit, said tunnels being equidistantly spaced, parallel one with the other and wherein said excavators are extended laterally from each side of said tunnel to a mining position substantially mid-way between adjacent of said tunnels.
Claim 9
Dependent Claim
60 words
The method according to claim 3 wherein a first set of excavators are spaced one from the other and are extended in substantially parallel array into said deposit, and wherein additional excavators are positioned above said first set of excavators in one or more tiers and are extended into said deposit at differing angles to said first set of excavators.
Claim 10
Dependent Claim
109 words
A mining system comprising: (a) at least one tunnel, within a sudsidable mineral deposit and adjacent the base thereof; (b) a plurality of hydraulic excavators adapted to be extended laterally from at least one side of said tunnel a substantial distance into said deposit, each of said excavators including an excavator head having a plurality of nozzles for the emmission of fluid under pressure, and at least one suction nozzle for the withdrawal of mined material; (c) means for supplying fluid under pressure to said excavator head; (d) means for effecting withdrawal of mined material via said suction nozzle; (e) means for reciprocating said excavator head within said deposit.
Claim 11
Dependent Claim
109 words
A mining system comprising: (a) at least one tunnel, within a sudsidable mineral deposit and adjacent the base thereof; (b) a plurality of hydraulic excavators adapted to be extended laterally from at least one side of said tunnel a substantial distance into said deposit, each of said excavators including an excavator head having a plurality of nozzles for the emmission of fluid under pressure, and at least one suction nozzle for the withdrawal of mined material; (c) means for supplying fluid under pressure to said excavator head; (d) means for effecting withdrawal of mined material via said suction nozzle; (e) means for reciprocating said excavator head within said deposit.
Claim 12
Dependent Claim
63 words
The system according to claim 9 and wherein said at least one tunnel comprises a plurality of oppositely disposed pairs of arch sections, each of said arch sections comprising a base portion forming a floor and a cantilever portion extending upwardly from said base portion at a generally acute angle and forming a roof, said arch section being free of any permanent interconnection.
Claim 13
Dependent Claim
75 words
The system according to claim 10 and wherein each said excavator is a compound tubular structure having a first passage therethrough for supplying pressurized fluid to said excavator head, and a second passage through which fluidized material can be withdrawn, each said excavator being additionally formed in longitudinal sections adapted for attachment one with the other in fluid tight relationship, the length of each said section being determined by the transverse dimensions of said tunnel.