Contruction method for continuous row of piles and earth drill for use therefor
Assignee: Individual
•
Filing: 1974-07-22
•
Granted: 1976-07-20
•
Expires: 1994-07-22
Abstract
Abstract A method of forming a row of concrete piles in ground is disclosed wherein it is possible to position piles sufficiently close that additional concrete shoring on either side or between piles is unnecessary. A hole for a pile is first bored, the ground forming the hole is hardened and thereafter filled with concrete. This process is repeated for subsequently drilled holes until the row is completed. A drill is also disclosed which includes jet means to force ground hardening liquid under high pressure into the ground surrounding the hole. The jet means may be rotatably and/or axially moveable within the hole.
Inventors
- 👤 Yoshio Ichise
- 👤 Akio Yamakado
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-10-30 17:57
CPC Classifications
E; E02; E02D; E02D5/00; E02D5/20; E02D5/02; E02D5/03; E02D5/10; E02D5/12; E02D5/22; E02D5/34; E02D5/46
Claims Analysis
Total Claims: 14
Claim 1
Independent Claim
119 words
A method for forming a continuous row of piles comprising the steps of: boring a first hole in the ground; hardening the ground surrounding said first hole by forcing a ground hardening liquid under high pressure into said ground surrounding said first hole; filling said first hole with mortar; boring a second hole adjacent said first hole; hardening the ground surrounding said second hole by forcing a ground hardening liquid under high pressure into said ground surrounding said second hole, a portion of the ground surrounding said first and second holes being common to both said holes; filling said second hole with mortar, and repeating said steps of forming said piles until a row of piles has been completed.
Claim 2
Independent Claim
119 words
A method for forming a continuous row of piles comprising the steps of: boring a first hole in the ground; hardening the ground surrounding said first hole by forcing a ground hardening liquid under high pressure into said ground surrounding said first hole; filling said first hole with mortar; boring a second hole adjacent said first hole; hardening the ground surrounding said second hole by forcing a ground hardening liquid under high pressure into said ground surrounding said second hole, a portion of the ground surrounding said first and second holes being common to both said holes; filling said second hole with mortar, and repeating said steps of forming said piles until a row of piles has been completed.
Claim 3
Dependent Claim
41 words
The method of claim 1, wherein the step of hardening the ground forming said holes is by forcing ground hardening liquid under high pressure into the ground surrounding each drilled hole in a direction toward the next hole to be drilled.
Claim 4
Dependent Claim
31 words
The method of claim 1, wherein the step of hardening the ground forming the holes is by forcing ground hardening liquid in a jet stream under high pressure into said ground.
Claim 5
Dependent Claim
30 words
The method of claim 1, wherein the step of hardening the ground forming the holes is by rotating a high pressure jet stream of ground hardening liquid in said holes.
Claim 6
Dependent Claim
34 words
The method of claim 1, wherein the step of hardening the ground forming the holes is by simultaneously rotating and axially moving a high pressure jet stream of ground hardening liquid in said holes.
Claim 7
Dependent Claim
13 words
The method of claim 1, including the steps of tangentially aligning said holes.
Claim 8
Dependent Claim
15 words
The method of claim 1, including the steps of overlapping the bores of said holes.
Claim 9
Dependent Claim
15 words
The method of claim 1, including the step of adding reinforcing metal to said piles.
Claim 10
Independent Claim
85 words
The method of forming a row of piles comprising the steps of: boring in sequence a row of holes; hardening the ground adjacent each hole after it has been bored by forcing a ground-hardening liquid under high pressure into said ground adjacent said hole; positioning each subsequent hole sufficiently close to the preceeding hole so that a portion of the hardened ground adjacent each hole is common to both holes, and filling each hole with mortar after the ground surrounding each hole has been hardened.
Claim 11
Independent Claim
85 words
The method of forming a row of piles comprising the steps of: boring in sequence a row of holes; hardening the ground adjacent each hole after it has been bored by forcing a ground-hardening liquid under high pressure into said ground adjacent said hole; positioning each subsequent hole sufficiently close to the preceeding hole so that a portion of the hardened ground adjacent each hole is common to both holes, and filling each hole with mortar after the ground surrounding each hole has been hardened.
Claim 12
Dependent Claim
13 words
The method of claim 9, including the step of tangentially aligning said holes.
Claim 13
Dependent Claim
12 words
The method of claim 9, including the step of overlapping said holes.
Claim 14
Dependent Claim
15 words
The method of claim 9, including the step of adding reinforcing metal to said piles.
References Cited (Backward Citations)
US2791886A
Cited
US3310952A
Cited
US3195311A
Cited
US3410095A
Cited
US3429126A
Cited
US3504497A
Cited
US3391544A
Cited
US3800544A
Cited
US3839871A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1979-07-20 | 1980-01-19 | 1980-07-20 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1983-07-20 | 1984-01-19 | 1984-07-20 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1987-07-20 | 1988-01-19 | 1988-07-20 | $7700.00 | Window Closed / Lapsed |