Patent US4679890A successfully refreshed from Google Patents.
Patent US3178616A successfully refreshed from Google Patents.
US3178616A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Equipment for protecting electrical systems including inverse-time-delay response
Assignee: Westinghouse Electric Corp
•
Filing: 1961-05-09
•
Granted: 1965-04-13
•
Expires: 1981-05-09
Abstract
No abstract record available.
Inventors
- 👤 John L Blackburn
- 👤 William E Glassburn
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-01 19:41
CPC Classifications
H; H02; H02H; H02H7/00; H02H7/26; H02H7/30
Claims Analysis
Total Claims: 2
Claim 1
Independent Claim
158 words
IN A RELAYING ASSEMBLY, A FIRST THREE-PHASE RELAY UNIT FOR PROTECTING A POLYPHASE ALTERNATING-CURRENT ELECTRICAL SYSTEM RESPONSIVE FOR OPERATION WHEN ENERGIZED BY ALTERNATING VOLTAGE AND CURRENT QUANTITIES OCCURRING DURING LINE-TO-LINE FAULT CONDITIONS OF A THREE-PHASE ALTERNATINGCURRENT ELECTRICAL SYSTEM ONLY TO A MAGNITUDE OF A FUNCTION OF IMPEDANCE HAVING A PREDETERMINED ANGLE WHICH FALLS IN A RANGE EXTENDING BETWEEN A FIRST MAGNITUDE AND A SECOND MAGNITUDE, A SECOND THREE-PHASE RELAY UNIT RESPONSIVE FOR OPERATION WHEN ENERGIZED BY ALTERNATING VOLTAGE AND CURRENT QUANTITIES OCCURRING DURING FAULTS INVOLVING THREE LINES OF THREE-PHASE ALTERNATING CURRENT ELECTRICAL SYSTEM TO A MAGNITUDE OF A FUNCTION OF IMPEDANCE, TIME-DELAY RELAY MEANS RESPONSIVE TO OPERATION OF ONE OF SAID RELAY UNITS FOR BEING TRANSFERRED FROM INEFFECTIVE TO EFFECTIVE CONDITION, SAID TIME-DELAY RELAY MEANS WHEN IN EFFECTIVE CONDITION HAVING A TIME-DELAY WHICH VARIES INVERSELY RELATIVE TO THE MAGNITUDE OF THE ENERGIZATION OF SUCH TIME-DELAY RELAY MEANS, AND TRANSLATING MEANS RESPONSIVE TO OPERATION OF THE TIME-DELAY RELAY MEANS.
Claim 2
Dependent Claim
158 words
IN A RELAYING ASSEMBLY, A FIRST THREE-PHASE RELAY UNIT FOR PROTECTING A POLYPHASE ALTERNATING-CURRENT ELECTRICAL SYSTEM RESPONSIVE FOR OPERATION WHEN ENERGIZED BY ALTERNATING VOLTAGE AND CURRENT QUANTITIES OCCURRING DURING LINE-TO-LINE FAULT CONDITIONS OF A THREE-PHASE ALTERNATINGCURRENT ELECTRICAL SYSTEM ONLY TO A MAGNITUDE OF A FUNCTION OF IMPEDANCE HAVING A PREDETERMINED ANGLE WHICH FALLS IN A RANGE EXTENDING BETWEEN A FIRST MAGNITUDE AND A SECOND MAGNITUDE, A SECOND THREE-PHASE RELAY UNIT RESPONSIVE FOR OPERATION WHEN ENERGIZED BY ALTERNATING VOLTAGE AND CURRENT QUANTITIES OCCURRING DURING FAULTS INVOLVING THREE LINES OF THREE-PHASE ALTERNATING CURRENT ELECTRICAL SYSTEM TO A MAGNITUDE OF A FUNCTION OF IMPEDANCE, TIME-DELAY RELAY MEANS RESPONSIVE TO OPERATION OF ONE OF SAID RELAY UNITS FOR BEING TRANSFERRED FROM INEFFECTIVE TO EFFECTIVE CONDITION, SAID TIME-DELAY RELAY MEANS WHEN IN EFFECTIVE CONDITION HAVING A TIME-DELAY WHICH VARIES INVERSELY RELATIVE TO THE MAGNITUDE OF THE ENERGIZATION OF SUCH TIME-DELAY RELAY MEANS, AND TRANSLATING MEANS RESPONSIVE TO OPERATION OF THE TIME-DELAY RELAY MEANS.
References Cited (Backward Citations)
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1968-04-12 | 1968-10-12 | 1969-04-13 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1972-04-12 | 1972-10-12 | 1973-04-13 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1976-04-12 | 1976-10-12 | 1977-04-13 | $7700.00 | Window Closed / Lapsed |