Claims Analysis
Total Claims: 8
Claim 1
Independent Claim
130 words
In combination: an electric power system having a hierarchy of branches; a plurality of overcurrent protection devices each in an assigned branch in said hierarchy of branches, and comprising trip means having an assigned overcurrent/time trip characteristic for generating a trip signal; said assigned overcurrent/time trip characteristic of each protection device being assigned to coordinate operation of said plurality of protection devices such that a first protection device above a fault in said hierarchy of branches generates a trip signal first in response to said fault; a communications link connected to said plurality of protection devices; and central test means initiating over said communications link simultaneous testing of said protection devices using a pattern of assigned test currents simulating a fault at a specified location in said hierarchy of branches.
Claim 2
Dependent Claim
130 words
In combination: an electric power system having a hierarchy of branches; a plurality of overcurrent protection devices each in an assigned branch in said hierarchy of branches, and comprising trip means having an assigned overcurrent/time trip characteristic for generating a trip signal; said assigned overcurrent/time trip characteristic of each protection device being assigned to coordinate operation of said plurality of protection devices such that a first protection device above a fault in said hierarchy of branches generates a trip signal first in response to said fault; a communications link connected to said plurality of protection devices; and central test means initiating over said communications link simultaneous testing of said protection devices using a pattern of assigned test currents simulating a fault at a specified location in said hierarchy of branches.
Claim 3
Dependent Claim
88 words
The combination of claim 1 wherein said protection devices have memory means for storing said assigned test current and wherein said trip means includes test means implementing a test of said trip means using said assigned test currents to said protection devices over said communications link for storage in said memory means, and means broadcasting a test signal over said communications link to all of said protection devices actuating said test means to implement a test of said trip means using said assigned test current stored in memory.
Claim 4
Dependent Claim
49 words
The combination of claim 2 wherein said electric power system includes devices which have affects on fault current in selected ones of said hierarchy of branches and wherein said central test means includes means generating said pattern of assigned test currents taking into account said effects of said devices.
Claim 5
Dependent Claim
58 words
The combination of claim 3 wherein said trip means includes means recording in said memory means a trip time at which said overcurrent protection device trips in response to the assigned test current, and wherein said central test means comprises means recovering a trip time from said memory means in each overcurrent protection device over said communications link.
Claim 6
Dependent Claim
78 words
The combination of claim 4 wherein certain of said overcurrent protection devices include zone interlock means responsive to an assigned test current indicating a fault below said certain protection device in said hierarchy of branches blocking generation of a trip signal in an overcurrent protection device in a branch higher than said certain overcurrent protection device in said hierarchy of branches to give said certain overcurrent protection device time for its trip means to respond to said fault.
Claim 7
Independent Claim
100 words
A method of testing overcurrent/time trip characteristic coordination of overcurrent protection devices in an electric power system comprising: establishing a pattern of test currents for said overcurrent protection devices which simulates a fault at a specified location in said electric power system; storing stored test currents assigned in accordance with said pattern of test currents in said overcurrent protection devices; simultaneously testing said overcurrent protection devices by applying said stored test currents to said overcurrent protection devices simultaneously; and recording responses of said overcurrent protection devices to said stored test currents assigned in accordance with said pattern of test currents.
Claim 8
Independent Claim
100 words
A method of testing overcurrent/time trip characteristic coordination of overcurrent protection devices in an electric power system comprising: establishing a pattern of test currents for said overcurrent protection devices which simulates a fault at a specified location in said electric power system; storing stored test currents assigned in accordance with said pattern of test currents in said overcurrent protection devices; simultaneously testing said overcurrent protection devices by applying said stored test currents to said overcurrent protection devices simultaneously; and recording responses of said overcurrent protection devices to said stored test currents assigned in accordance with said pattern of test currents.