US5533568A Expired / Lapsed US ⏱️ 0.0 years remaining

Managing supplementary heat during defrost on heat pumps

Assignee: Carrier Corp
•
Filing: 1995-07-11
•
Granted: 1996-07-09
•
Expires: 2015-07-11
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method of controlling a current defrost cycle for an outdoor coil of a heat pump system, the heat pump system having a plurality of supplemental heating elements for heating an air stream passing from an indoor coil to an air supply duct during defrost operation, wherein an initial quantity of supplemental heating elements energized is a function of a most recent previous defrost cycle. The initial quantity of supplemental heating elements is energized upon initiation of a defrost cycle. Whether the initial quantity of supplemental heating elements provided is insufficient or excessive is determined. At least one of the supplemental heating elements is deactivated if the initial quantity of supplemental heating elements being provided is excessive. At least one of the supplemental heating elements is activated if the initial quantity of supplemental heating elements being provided is if the initial quantity of supplemental heating elements being provided is insufficient, and at least one additional supplemental heating element is available. Information as to an initial quantity of supplemental heating elements to be activated for a following defrost cycle is retained. The initial quantity of supplemental heating elements to be activated for a following defrost cycle is equal to a number of supplemental heating elements activated upon termination of the current defrost cycle. The heat pump is kept on to complete the defrost cycle during an overshoot condition.

Inventors

  • 👤 Don A. Schuster
  • 👤 Hongmei Liang
  • 👤 Larry J. Burkhart
  • 👤 Gary D. Wedlake

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 06:02
CPC Classifications
F; F25; F25D; F25D21/00; F25D21/06; F25D21/08; F24; F24F; F24F11/00; F24F11/30; F24F11/41

Claims Analysis

Total Claims: 17
Claim 1
Independent Claim 222 words
A method of controlling a current defrost cycle for an outdoor coil of a heat pump system, the heat pump system having a plurality of supplemental heating elements for heating an air stream passing from an indoor coil to an air supply duct during defrost operation, wherein an initial quantity of supplemental heating elements energized is a function of a most recent previous defrost cycle, comprising the steps of: energizing the initial quantity of supplemental heating elements upon initiation of a defrost cycle; determining whether the initial quantity of supplemental heating elements provided is excessive; holding the heat pump on during an overshoot condition to allow completion of the defrost cycle; deactivating at least one of the supplemental heating elements if the initial quantity of supplemental heating elements being provided is excessive; determining whether the initial quantity of supplemental heating elements provided is insufficient; activating, if the initial quantity of supplemental heating elements being provided is insufficient, at least one additional supplemental heating element if said element is available; and retaining information as to an initial quantity of supplemental heating elements to be activated for a following defrost cycle, wherein said initial quantity of supplemental heating elements to be activated for a following defrost cycle is equal to a number of supplemental heating elements activated upon termination of the current defrost cycle.
Claim 2
Independent Claim 222 words
A method of controlling a current defrost cycle for an outdoor coil of a heat pump system, the heat pump system having a plurality of supplemental heating elements for heating an air stream passing from an indoor coil to an air supply duct during defrost operation, wherein an initial quantity of supplemental heating elements energized is a function of a most recent previous defrost cycle, comprising the steps of: energizing the initial quantity of supplemental heating elements upon initiation of a defrost cycle; determining whether the initial quantity of supplemental heating elements provided is excessive; holding the heat pump on during an overshoot condition to allow completion of the defrost cycle; deactivating at least one of the supplemental heating elements if the initial quantity of supplemental heating elements being provided is excessive; determining whether the initial quantity of supplemental heating elements provided is insufficient; activating, if the initial quantity of supplemental heating elements being provided is insufficient, at least one additional supplemental heating element if said element is available; and retaining information as to an initial quantity of supplemental heating elements to be activated for a following defrost cycle, wherein said initial quantity of supplemental heating elements to be activated for a following defrost cycle is equal to a number of supplemental heating elements activated upon termination of the current defrost cycle.
Claim 3
Dependent Claim 26 words
The process according to claim 1 comprising the additional step of determining whether the initial quantity of supplemental heating elements provided is neither excessive nor insufficient.
Claim 4
Dependent Claim 63 words
The process according to claim 2 wherein said step of determining whether the initial quantity of supplemental heating elements provided is neither excessive nor insufficient comprises determining if defrost is completed while both supplemental and primary heat are being requested and within a first predetermined time and, if so, then maintaining a same quantity of activated supplemental heating elements as the initial quantity.
Claim 5
Dependent Claim 17 words
The process according to claim 3 wherein said first predetermined time is between 120 and 480 seconds.
Claim 6
Dependent Claim 14 words
The process according to claim 4 wherein said first predetermined time is 240 seconds.
Claim 7
Dependent Claim 38 words
The process according to claim 1 wherein said step of determining whether the initial quantity of supplemental heating elements provided is excessive comprises determining if there is a call for supplemental heat without a call for primary heat.
Claim 8
Dependent Claim 21 words
The process according to claim 1 wherein said at least one additional supplemental heating element is a single supplementary heating element.
Claim 9
Dependent Claim 36 words
The process according to claim 1 wherein said step of determining whether the initial quantity of supplemental heating elements provided is excessive continues for a second predetermined time after defrost is terminated by an outdoor control.
Claim 10
Dependent Claim 17 words
The process according to claim 8 wherein said second predetermined time is between 30 and 240 seconds.
Claim 11
Dependent Claim 14 words
The process according to claim 9 wherein said second predetermined time is 90 seconds.
Claim 12
Dependent Claim 59 words
The process according to claim 1 where the step of determining whether the initial quantity of supplemental heating elements provided is insufficient comprises the steps of: determining if a call for supplemental heat is issued within a predetermined time range, determining if a call for primary heat is maintained, and determining if the call for supplemental heat is maintained.
Claim 13
Dependent Claim 17 words
The process according to claim 11 wherein said predetermined time range is between 30 and 900 seconds.
Claim 14
Dependent Claim 17 words
The process according to claim 11 wherein said predetermined time range is between 90 and 660 seconds.
Claim 15
Dependent Claim 23 words
The process according to claim 1 wherein said at least one said supplemental heating element being deactivated is a single supplemental heating element.
Claim 16
Dependent Claim 19 words
The process according to claim 1 wherein if overshoot occurs, at least one said supplemental heating element is deactivated.
Claim 17
Dependent Claim 39 words
The process according to claim 1 wherein a maximum time period is provided to allow successful completion of said defrost cycle, said maximum time period providing allowing for an override if a malfunction has occurred in the heat pump.

References Cited (Backward Citations)

US4292813A Cited
US4353409A Cited
US4335847A Cited
US4356962A Cited
US4725001A Cited
US4759498A Cited
US5332028A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1999-07-09 2000-01-08 2000-07-09 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2003-07-09 2004-01-08 2004-07-09 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2007-07-09 2008-01-08 2008-07-09 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag