Abstract

Abstract A permeable wall (4) is located in the material of an aquifer (2), in the path of an approaching plume (3) of a contaminant (eg a chlorinated solvent). The wall comprises a body (7) of permeable filler material, eg sand and gravel, which is placed in a trench (5) that has been cut down into the aquifer material. Biologically-aided breakdown of the contaminant is aided by the presence of nutrients in the groundwater, and injection ports (18) are provided in the wall, through which the nutrients are injected periodically. The permeability of the wall helps the injected nutrients to spread laterally through the plume. The injected substances are contained in a volume of water; this water may be water which has been extracted from the trench, draw-off wells (9) being provided in the trench for that purpose. A second permeable wall (29) may be provided downstream for injection of eg air.

Inventors

  • 👤 John F. Devlin

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 15:34
CPC Classifications
C; C02; C02F; C02F3/00; C02F3/02; C02F3/12; C02F3/1205; C02F3/1231; B; B09; B09C; B09C1/00; B09C1/002; B09C1/10; C02F3/34; E; E02; E02D; E02D31/00; B09C2101/00; C02F2103/00; C02F2103/06; Y; Y02; Y02W; Y02W10/00; Y02W10/10

Claims Analysis

Total Claims: 18
Claim 1
Independent Claim 143 words
Procedure for delivering a substance into an aquifer, comprising the steps; of excavating a trench in the material of the aquifer; placing a body of a filler material in the trench; where the nature of the filler material is such that the permeability of the filler material is not less than the permeability of the material of the aquifer; of providing a conduit having an injection port; of so locating and disposing the conduit and the port within the body of filler material in the trench that the port is in operative communication with water within the trench; of injecting a substance into water in the trench through the injection port; the arrangement of the conduit and port, and the manner of the injection, are such that the injected substance, upon injection through the port, spreads along, into, and through the filler material.
Claim 2
Dependent Claim 143 words
Procedure for delivering a substance into an aquifer, comprising the steps; of excavating a trench in the material of the aquifer; placing a body of a filler material in the trench; where the nature of the filler material is such that the permeability of the filler material is not less than the permeability of the material of the aquifer; of providing a conduit having an injection port; of so locating and disposing the conduit and the port within the body of filler material in the trench that the port is in operative communication with water within the trench; of injecting a substance into water in the trench through the injection port; the arrangement of the conduit and port, and the manner of the injection, are such that the injected substance, upon injection through the port, spreads along, into, and through the filler material.
Claim 3
Dependent Claim 32 words
Procedure of claim 1, where the nature of the filler material is such that the permeability of the filler material is substantially greater than the permeability of the material of the aquifer.
Claim 4
Dependent Claim 51 words
Procedure of claim 1, where the trench has sides, and the nature of the sides is such that groundwater may pass, substantially completely freely, through the sides of the trench from the material of the aquifer into the filler material, and from the filler material into the material of the aquifer.
Claim 5
Dependent Claim 87 words
Procedure of claim 1, wherein: the trench has sides, and the procedure includes the step of inserting fabric material into the sides of the trench; whereby the fabric material acts to prevent infiltration of the material of the aquifer into the body of filler material; and the nature of the fabric material is such as to permit groundwater to pass through the sides of the trench from the material of the aquifer into the filler material, and from the filler material into the material of the aquifer.
Claim 6
Dependent Claim 51 words
Procedure of claim 1, wherein the step of injecting the substance into the water includes the steps: of providing a volume of water, and of mixing the substance to be injected into the volume of water; and of injecting the volume of water and the substance together through the injection port.
Claim 7
Dependent Claim 33 words
Procedure of claim 5, wherein the substance to be injected is, or includes, a mix of nutrients of such a composition as will promote the biochemical breakdown of the contaminant, within the aquifer.
Claim 8
Dependent Claim 22 words
Procedure of claim 5, wherein the said volume of water is roughly equal to the volume of the body of filler material.
Claim 9
Dependent Claim 19 words
Procedure of claim 5, wherein the said volume of water includes water that has been extracted from the trench.
Claim 10
Dependent Claim 42 words
Procedure of claim 8, wherein the procedure includes the steps of providing a well in the body of the filler material, and of providing a water draw-off port within the well, and of extracting water from the trench through the draw-off port.
Claim 11
Dependent Claim 37 words
Procedure of claim 5, including the step of injecting such volumes of water periodically, wherein the time taken for the injection of each volume of water is comparatively short, and the time between injections is comparatively long.
Claim 12
Dependent Claim 32 words
Procedure of claim 10, wherein the said comparatively short time, being the time taken for injection, is no longer than the time taken for the moving groundwater to traverse through the trench.
Claim 13
Dependent Claim 42 words
Procedure of claim 11, wherein the comparatively long time, being the time between injections, is long enough to allow a volume of groundwater of between five and twenty times the volume of the body of filler material to traverse through the trench.
Claim 14
Dependent Claim 66 words
Procedure of claim 1, including the steps: of plotting the extent of a plume of contaminant in a body of groundwater contained within an aquifer, and of determining the velocity of the said plume; of positioning the trench laterally across the line of the velocity of the plume, the trench being of sufficient depth and extent that substantially all of the contaminant passes through the trench.
Claim 15
Dependent Claim 19 words
Procedure of claim 13, wherein the contaminant is of the kind that can be biochemically reduced under anaerobic conditions.
Claim 16
Dependent Claim 11 words
Procedure of claim 14, wherein the contaminant is a chlorinated solvent.
Claim 17
Dependent Claim 18 words
Procedure of claim 14, where the substance to be injected includes nutrients for promoting the said biochemical reduction.
Claim 18
Dependent Claim 29 words
Procedure of claim 13, wherein the substance to be injected is, or includes, oxygen, and the contaminant is of the kind that can be broken down under aerobic conditions.

References Cited (Backward Citations)

JPS52460A Cited
US4288174A Cited
US4469176A Cited
US4543016A Cited
US4678582A Cited
US4687372A Cited
US4850745A Cited
US4982788A Cited
US5076727A Cited
US5057227A Cited
US5180503A Cited
US5249888A Cited
US5384048A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1998-10-09 1999-04-10 1999-10-10 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2002-10-09 2003-04-10 2003-10-10 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2006-10-09 2007-04-10 2007-10-10 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag