Abstract

Abstract An electrode boiler comprises a container for containing water and electrodes within the container which serves to pass electrical current through such water and which is generally upright when in use. Feed and drain systems are connected to the container to enable water to be fed to and drained therefrom. An outlet is provided through which steam generated inside the container can pass. An electrode current indicator provides an indication of the value of the electrical current passing through the electrodes. A controlling computer is connected to the feed and drain systems and the electrode current indicator. The controlling computer is set to cause the feed system to open when a predetermined drop in the electrode current has occurred owing to a boiling away of water from the boiler, and then to cause the feed system to close when a predetermined increase in the electrode current has occurred owing to the introduction of water into the boiler. Current-increase-rate measuring device is provided in the controlling computer to provide a measure of the rate of increase of electrode current when the feed system is opened. The controlling computer is to open the drain system, for a drain period, in dependence upon the measured value of the current-increase-rate.

Inventors

  • 👤 Howard C. Jones

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 21:10
CPC Classifications
F; F22; F22B; F22B1/00; F22B1/28; F22B1/30

Claims Analysis

Total Claims: 25
Claim 1
Independent Claim 247 words
An electrode boiler comprising a container for containing water, electrodes within the container which serve to pass electrical current through such water and which extend in a generally vertical direction when the boiler is in use, feed and drain means connected to the container to enable water to be fed to and drained from the container, outlet means of the container through which steam generated inside the container can pass when the boiler is in use, an electrode current indicator arranged to provide an indication of the value of the electrical current passing through the electrodes, and control means connected to the feed and drain means and the electrode current indicator, in which the control means are such as to cause the feed means to open when a predetermined drop in the electrode current has occurred owing to boiling away of water from the boiler, and then to cause the feed means to close when a predetermined increase in the electrode current has occurred owing to the introduction of water into the boiler through the feed means, in which measuring means are provided in the control means to provide a measure of a parameter that varies with the rate of increase of electrode current when the feed means are opened, and in which the control means are such as to open the drain means, for a drain period, upon the occurrence of a change in sense of the gradient of said measure as a function of time.
Claim 2
Dependent Claim 247 words
An electrode boiler comprising a container for containing water, electrodes within the container which serve to pass electrical current through such water and which extend in a generally vertical direction when the boiler is in use, feed and drain means connected to the container to enable water to be fed to and drained from the container, outlet means of the container through which steam generated inside the container can pass when the boiler is in use, an electrode current indicator arranged to provide an indication of the value of the electrical current passing through the electrodes, and control means connected to the feed and drain means and the electrode current indicator, in which the control means are such as to cause the feed means to open when a predetermined drop in the electrode current has occurred owing to boiling away of water from the boiler, and then to cause the feed means to close when a predetermined increase in the electrode current has occurred owing to the introduction of water into the boiler through the feed means, in which measuring means are provided in the control means to provide a measure of a parameter that varies with the rate of increase of electrode current when the feed means are opened, and in which the control means are such as to open the drain means, for a drain period, upon the occurrence of a change in sense of the gradient of said measure as a function of time.
Claim 3
Dependent Claim 26 words
An electrode boiler according to claim 1, in which said measure is the time it takes for the said predetermined increase in electrode current to occur.
Claim 4
Dependent Claim 29 words
An electrode boiler according to claim 1, in which said measure is the increase in electrode current that occurs over a predetermined interval while the feed means are open.
Claim 5
Dependent Claim 28 words
An electrode boiler according to claim 1, in which said measure is the gradient of electrode current as a function of time when the feed means are open.
Claim 6
Dependent Claim 57 words
An electrode boiler according to claim 1, in which a value of said measure is provided every time the feed means are open, and an inhibit latch is provided in the control means to inhibit opening of the drain means until a predetermined number of boil/fill cycles have occurred after a desired electrode current has been reached.
Claim 7
Dependent Claim 14 words
An electrode boiler according to claim 5, in which said predetermined number is fifteen.
Claim 8
Dependent Claim 28 words
An electrode boiler according to claim 1, in which said measure is a rolling average of values taken from a predetermined number of the most recent boil/fill cycles.
Claim 9
Dependent Claim 14 words
An electrode boiler according to claim 7, in which the predetermined number is five.
Claim 10
Dependent Claim 46 words
An electrode boiler according to claim 1, in which said parameter is given by the expression REF/FT, in which REF is a reference value stored in the control means, and FT is the feed time for which the feed means are open during a boil/fill cycle.
Claim 11
Dependent Claim 70 words
An electrode boiler according to claim 9, in which REF is the value of the feed time at the start of operation of the boiler once the desired electrode current has been reached so that REF/FT is an indication of the concentration of the electrolytic contents of the water in the boiler in terms of the initial value it had at start up with the desired current having been reached.
Claim 12
Dependent Claim 40 words
An electrode boiler according to claim 9, in which, in the event that such a decrease in the value of said parameter occurs before the value of that parameter has reached a predetermined value, the value of REF is reset.
Claim 13
Dependent Claim 15 words
An electrode boiler according to claim 11, in which said predetermined value is about 1.5.
Claim 14
Dependent Claim 72 words
An electrode boiler according to claim 11, in which the new value to which REF is reset is given by the equation REF.sub.new =10(REF.sub.init -FT.sub.RA current)/CF, in which REF new is the new reference value, REF init is the value it had, FT RA current is the most recent value of FT RA , and CF is a value of concentration which is dependent upon the set value of the electrode current.
Claim 15
Dependent Claim 28 words
An electrode boiler according to claim 13, in which the value of CF is given by a table of values stored in a memory of the control means.
Claim 16
Dependent Claim 74 words
An electrode boiler according to claim 13, in which CF has a value of about 3 for operation conditions in which the electrode current is set to be 100% of the desired maximum current when the boiler is full, and a value of about 1.5 for operation conditions in which the electrode current is set to be at about 22% of that desired maximum current, the values of CF between those points increasing exponentially.
Claim 17
Dependent Claim 60 words
An electrode boiler according to claim 1, in which said parameter is given by CN=REF/FT RA in which REF is the value of the feed time at the start of operation of the boiler once the desired electrode current has been reached, CN is the value of the parameter, and FT RA is a rolling average of the feed time.
Claim 18
Dependent Claim 99 words
An electrode boiler according to claim 1 in which said parameter is given by CN=REF/10 (FT RA /ΔI) in which REF is the value of the feed time at the start of operation of the boiler once the desired electrode current has been reached, ΔI is, expressed as a percentage, said predetermined drop or said predetermined increase, said predetermined increase in any case being substantially equal to said predetermined drop whilst the boiler is operating in a state of dynamic equilibrium, CN is the value of the parameter, and FT RA is a rolling average of the feed time.
Claim 19
Dependent Claim 19 words
An electrode boiler according to claim 17, in which said predetermined drop or said predetermined increase is about 10%.
Claim 20
Independent Claim 228 words
A method of operating an electrode boiler comprising a container for containing water, electrodes within the container which serve to pass electrical current through such water and which extend in a generally vertical direction when the boiler is in use, feed and drain means connected to the container to enable water to be fed to and drained from the container, outlet means of the container through which steam generated inside the container can pass when the boiler is in use, an electrode current indicator arranged to provide an indication of the value of the electrical current passing through the electrodes, and control means connected to the feed and drain means and the electrode current indicator, the method comprising the steps of: (a) causing the feed means to open when a predetermined drop in the electrode current has occurred owing to a boiling away of water from the boiler; (b) causing the feed means to close when a predetermined increase in the electrode current has occurred owing to the introduction of water into the boiler through the feed means; and (c) opening the drain means, for a drain period, in dependence upon the occurrence of a change in sense of the gradient of a measure as a function of time, of a parameter which varies with the rate of increase of electrode current when the feed means are opened.
Claim 21
Independent Claim 228 words
A method of operating an electrode boiler comprising a container for containing water, electrodes within the container which serve to pass electrical current through such water and which extend in a generally vertical direction when the boiler is in use, feed and drain means connected to the container to enable water to be fed to and drained from the container, outlet means of the container through which steam generated inside the container can pass when the boiler is in use, an electrode current indicator arranged to provide an indication of the value of the electrical current passing through the electrodes, and control means connected to the feed and drain means and the electrode current indicator, the method comprising the steps of: (a) causing the feed means to open when a predetermined drop in the electrode current has occurred owing to a boiling away of water from the boiler; (b) causing the feed means to close when a predetermined increase in the electrode current has occurred owing to the introduction of water into the boiler through the feed means; and (c) opening the drain means, for a drain period, in dependence upon the occurrence of a change in sense of the gradient of a measure as a function of time, of a parameter which varies with the rate of increase of electrode current when the feed means are opened.
Claim 22
Dependent Claim 33 words
A method according to claim 19 further comprising the step of determining said rate of increase of electrode current by determining the time for a predetermined increase in said electrode current to occur.
Claim 23
Dependent Claim 33 words
A method according to claim 19 further comprising the step of determining said rate of increase of electrode current by determining an increase in said electrode current over a predetermined period of time.
Claim 24
Dependent Claim 29 words
A method according to claim 19 further comprising the step of determining said rate of increase of electrode current by determining the gradient of said electrode current over time.
Claim 25
Dependent Claim 35 words
A method according to claim 19 further comprising the step of inhibiting the opening of the drain means until a predetermined number of boil/fill cycles have occurred after a desired electrode current has been reached.

References Cited (Backward Citations)

US3682141A Cited
US3780261A Cited
US3944785A Cited
US3937920A Cited
US4196341A Cited
US4347430A Cited
US4418269A Cited
US4675505A Cited
US4952779A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1998-08-07 1999-02-06 1999-08-08 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2002-08-07 2003-02-06 2003-08-08 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2006-08-07 2007-02-06 2007-08-08 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.